BARBARA B. NOLAN, Individually and as Trustee of BARBARA B. NOLAN
TRUST, Plaintiff, v. PARAMOUNT HOMES, INC., Defendant and Third-
Party Plaintiff, v. STO CORPORATION; LADD EXTERIOR WALL SYSTEMS,
INC.; CAROLINA BUILDERS CORPORATION; and CEDAR ROOFS OF RALEIGH,
INC., Third-Party Defendants
Statute of Limitations--statute of repose--real property improvements--substantial
completion--last act or omission
Summary judgment was properly granted for defendant based upon the statute of repose
in an action for breach of implied warranties of habitability and workmanlike construction
arising from the construction and sale of a house where a certificate of compliance was issued
for the house on 6 June 1991 and plaintiff brought her action on 23 October 1997. Under
N.C.G.S. § 1-50(a)(5)(a), plaintiff has the burden of showing that she brought her action within
six years of either the substantial completion of her house or the specific last act or omission of
defendant giving rise to the action. The house was substantially completed upon issuance of the
certificate of compliance since it then could be used for its intended purpose and, since all of
defendant's claims relate to defendant's construction of the house, defendant's last act giving
rise to this action must have occurred while defendant was constructing the home. Work on the
punch list was not the last act and did not constitute substantial completion because that work
did not give rise to the cause of action and there is no evidence that the items on the list
prevented or materially interfered with plaintiff using the home as a residence. References in
prior cases tending to support the proposition that N.C.G.S. § 1-50(a)(5)(a) runs from the date of
sale are dicta.
Appeal by plaintiff from judgment entered 25 August 1998 by
Judge E. Lynn Johnson in Durham County Superior Court. Heard in
the Court of Appeals 23 August 1999.
Spears, Barnes, Baker, Wainio & Whaley, L.L.P., by Jessica
S. Cook and Alexander H. Barnes, for plaintiff-appellants.
Brown, Todd & Heyburn, P.L.L.C., by Julie M. Goodman, for
defendant and third party plaintiff-appellee.
Smith, Helms, Mulliss & Moore, L.L.P., by Gary R. Govert,
for defendant and third party plaintiff-appellee.
No brief filed for third party defendant-appellee Sto
Corporation.
No brief filed for third party defendant-appellee Ladd
Exterior Wall Systems, Inc.
No brief filed for third party defendant-appellee Carolina
Builders Corporation.
No brief filed for third party defendant-appellee Cedar
Roofs of Raleigh Inc.
EAGLES, Chief Judge.
This appeal considers the question of what event triggers
the running of the real property improvements statute of repose
N.C.G.S. § 1-50(a)(5)(a) (Supp. 1998).
This lawsuit arises out of defendant Paramount Homes Inc.'s
construction and sale of a house to plaintiff Barbara B. Nolan.
Defendant is in the business of building and selling houses. In
the spring of 1991, defendant built a house at 3411 Fairway Lanein Durham, North Carolina, for speculation. On 6 June 1991, the
Durham City-County Inspections Department issued a Certificate of
Compliance for the house. The certificate stated that the house
was in substantial compliance with applicable building and zoning
ordinances. On 9 December 1991, plaintiff Barbara Nolan purchased
the house from defendant. Defendant completed work pursuant to a
punch list sometime in March or April of 1992.
On 23 October 1997 plaintiff filed suit alleging that
defendant was negligent and breached its implied warranties of
habitability and workmanlike construction. On 8 January 1998,
defendant moved for summary judgment alleging that the applicable
statute of repose, N.C.G.S. § 1-50(a)(5)(a) (Supp. 1998), bars
plaintiff's claim. The trial court granted defendant's summary
judgment motion. Plaintiff appeals.
These facts present the question of what event triggers the
running of the real property improvements statute of repose. Our
research disclosed no controlling precedent in North Carolina.
See Cage v. Colonial Building Co., 337 N.C. 682, 448 S.E.2d 115
(1994); Duncan v. Ammons Construction Co., 87 N.C. App. 597, 361
S.E.2d 906 (1987); Colony Hill Condominium I Assoc. v. Colony
Co., 70 N.C. App. 390, 320 S.E.2d 273 (1984), disc. review
denied, 312 N.C. 796, 325 S.E.2d 485 (1985). The instant case is
before us on a motion for summary judgment. Summary judgment isproper if there is no genuine issue of material fact and the
moving party is entitled to judgment as a matter of law. N.C.G.S.
§ 1A-1, N.C.R. Civ. Pro. 56(c) (1990); Robinson, Bradshaw &
Hinson P.A. v. Smith, 129 N.C. App. 305, 314, 498 S.E.2d 841,
848, disc. review denied, 348 N.C. 695, 511 S.E.2d 650 (1998). We
must take all inferences in favor of the nonmoving party. Id. The
running of a statute of repose presents a purely legal question.
Lamb v. Wedgewood South Corp., 308 N.C. 419, 425, 302 S.E.2d 868,
872 (1983).
The North Carolina real property improvement statute of
repose provides:
No action to recover damages based upon or
arising out of the defective or unsafe
condition of an improvement to real property
shall be brought more than six years from the
later of the specific last act or omission of
the defendant giving rise to the cause of
action or substantial completion of the
improvement.
N.C.G.S. § 1-50(a)(5)(a). Plaintiff has the burden of showing
that she brought this action within six years of either (1) the
substantial completion of the house or (2) the specific last act
or omission of defendant giving rise to this cause of action. See
Sink v. Andrews, 81 N.C. App. 594, 597, 344 S.E.2d 831, 833
(1986).
N.C.G.S. § 1-50(a)(5)(c) defines substantial completion asbeing that degree of completion of a project, improvement or
specified area or portion thereof upon attainment of which the
owner can use the same for the purpose for which it was
intended. An owner of a residential dwelling may use it as a
residence when the appropriate government agency issues a final
certificate of compliance. See N.C.G.S. § 153A-363 (Supp. 1998);
N.C.G.S. § 160A-423 (1994). The owner may then utilize the
residence for the purpose which it was intended and the home is
substantially completed under N.C.G.S. § 1-50(a)(5).
The Durham City-County Inspections Department issued a
certificate of compliance for the house on 6 June 1991. The certificate of compliance noted that the house was a single
family dwelling. It also stated that defendant had constructed
the house in compliance with all applicable building and zoning
ordinances. Under this certificate of compliance an owner could
utilize the property as a residence on 6 June 1991. See N.C.G.S.
§ 153A-363; N.C.G.S. § 160A-423. Since it could be utilized for
its intended purposes, upon issuance of the certificate of
compliance, we hold that the house was substantially completed
for purposes of N.C.G.S. § 1-50(a)(5) on 6 June 1991. Therefore,
defendant substantially completed the house in question more than
six years before plaintiff filed her claim.
Plaintiff argues that defendant did not actually
substantially complete work on the house until it had completed
the work done on the punch list in March-April 1992. We are not
persuaded. N.C.G.S. § 1-50(a)(5) clearly states that as soon as
the property may be used for its intended purpose, it is
substantially completed. There is no evidence in this record that
the items on the punch list prevented or materially interfered
with plaintiff using the house as a residence. Therefore,
defendant substantially completed the home on 6 June 1991 and not
when it completed the work on the punch list.
N.C.G.S. § 1-50 does not define last act or omission.
However, the plain language indicates that the statute of repose clock begins to run from the specific last act or omission
giving rise to the cause of action. Section 1-50(a)(5)(a).
Plaintiff must establish a direct connection between the harm
alleged and that last specific act or omission. Plaintiff
attempts to make this connection with her claim for the breach of
the implied warranty of workmanlike construction. Under this
warranty, the builder-vendor warrants that it constructed the
house in a workmanlike manner and that the house is free from
major structural defects at the time of sale or the taking of
possession whichever occurs first. Hartley v. Ballou, 286 N.C.
51, 62, 209 S.E.2d 776, 783 (1974). Plaintiff argues that her
action for breach of an implied warranty of workmanlike
construction did not arise until defendant sold the house to her.
Since defendant cannot breach this warranty without the act of
sale, plaintiff claims that defendant's last act giving rise to
this action is necessarily the sale of the house and not the
completion of construction.
We are not persuaded by plaintiff's argument. Unlike a
statute of limitations, a statute of repose will begin to run
when a specific event occurs, regardless of whether a cause of
action has accrued or whether any injury has resulted. Black v.
Littlejohn, 312 N.C. 626, 633, 325 S.E.2d 469, 474-75 (1985);
Monson v. Paramount Homes, Inc., ___ N.C. App. ___, 515 S.E.2d 445 (1999). The statute serves as an unyielding and absolute
barrier preventing a plaintiff's claim even before his cause of
action accrues. Black, 312 N.C. at 633, 325 S.E.2d at 475. If
plaintiff fails to file within the prescribed period, the statute
gives defendant a vested right not to be sued. Colony Hill, 70
N.C. App. at 394, 320 S.E.2d at 276.
Our courts have made it clear that a statute of repose may
operate to cut off a defendant's liability even before an injury
occurs. Plaintiff's alleged injury occurred at the earliest on 23
October 1997 when defendant sold her the house. However,
defendant's last act giving rise to this action took place when
it completed construction on 6 June 1991. Plaintiff alleges that
defendant breached the implied warranty of habitability, implied
warranty of workmanlike construction, and that defendant
negligently constructed the house. Plaintiff points particularly
to the construction of the home's walls as being deficient. These
claims all relate to defendant's improper construction of the
home. Any act or omission giving rise to a claim must have
occurred while defendant was constructing the home. Accordingly,
we hold that N.C.G.S. § 1-50(a)(5) began to run on the last day
that defendant performed construction relating to the harm
alleged and not on the day of sale.
Here defendant completed construction on 6 June 1991. On that day, Durham City-County Inspections Office issued its
certificate of compliance. Defendant did not engage in any
construction after that date. Thus, the statute began to run on 6
June 1991. Since plaintiff did not file her action until 23
October 1997, the statute of repose bars her claim.
Plaintiff argues that the courts of our state have already
held that N.C.G.S. § 1-50(a)(5)(a) runs from the date of sale.
See Cage v. Colonial Building Co., 111 N.C. App. 828, 833, 433
S.E.2d 827, 830, (1993), rev'd, 337 N.C. 682, 448 S.E.2d 115
(1994); Duncan, 87 N.C. App. at 600, 361 S.E.2d at 909; Colony
Hill, 70 N.C. App. at 395, 320 S.E.2d at 276. Upon a careful
examination of these cases, we conclude that our courts have
never previously decided this issue. We further conclude that any
reference in these cases tending to support plaintiff's
proposition is mere dicta. Trustees of Rowan Tech. v. Hammond
Assoc., 313 N.C. 230, 242, 328 S.E.2d 274, 281 (1985).
In Duncan, defendants completed construction on a home
sometime prior to the purchase date of 10 September 1979. Duncan,
87 N.C. App. at 598, 361 S.E.2d at 907. On 14 May 1986,
plaintiffs filed suit against the contractor alleging injuries
related to faulty construction. Id. In affirming the trial
court's order for summary judgment based on the statute of
repose, the Duncan court stated, Defendants in the present action completed construction on plaintiffs' home prior to 10
September 1979. Plaintiffs had an outside time limit of six years
from that date, or until 10 September 1985, to bring an action
for negligent construction. Id. at 600, 361 S.E.2d at 909.
We note that the Duncan court did not decide whether the
defendants' last act for purposes of the statute of repose was
the completion of construction or the sale of the house. Id.
Resolution of that issue was unnecessary to the court's decision
because plaintiffs' claim failed under either date. Id.
Therefore, we conclude that Duncan is not helpful concerning the
running of the statute of repose. Trustees of Rowan Tech., 313
N.C. at 242, 328 S.E.2d at 281.
Likewise, we conclude that we are not bound by Colony Hill.
This Court decided Colony Hill under an earlier version of the
real property improvements statute of repose. See 1963 N.C. Sess.
Laws c. 1030. Plaintiffs claimed defendants owed them a
continuing duty because of the defendants' continuing ownership
interest in the property. Colony Hill, 70 N.C. App. at 395, 320
S.E.2d at 276. Without deciding the effect of a continuing
ownership interest on the statute of repose, the Colony Hill
court discounted plaintiffs' argument. Id. In Colony Hill, the
defendants conveyed away the alleged ownership interest more than
six years from the time of filing. Id. Since that alleged ownership interest did not have any bearing on the outcome of
Colony Hill we are not persuaded that the statute of repose ran
from the date of sale.
Finally, we hold that Cage does not bind us here. In Cage,
plaintiff sued the defendant general contractor on 25 January
1991 for defective construction of a house she bought on 7
December 1984. Cage, 337 N.C. at 684-85, 448 S.E.2d at 116. This
Court held that N.C.G.S. § 1-52(16)(1991) applied giving
plaintiff a ten year statute of repose. Id. at 685, 448 S.E.2d at
117. In noting that plaintiff's claim fell within the statute of
repose, this court stated Plaintiff's filing was also well
within the ten year statute of repose which began to run on 7
December 1984 when defendant sold the townhouse to plaintiff.
Cage v. Colonial Building Co., 111 N.C. App. 828, 833, 433 S.E.2d
827, 830 (1993), rev'd, 337 N.C. 682, 448 S.E.2d 115 (1994). The
Supreme Court reversed, holding that N.C.G.S. § 1-50(a)(5)(a)
applied giving plaintiff a six year statute of repose only. Cage,
337 N.C. at 685-86, 448 S.E.2d at 117. The Supreme Court then
held that defendant's conduct occurred more than six years before
plaintiff brought her claim. Id. In so holding, the Court did not
specify the conduct of defendant to which it was referring. Id.
Both the date of sale and implicitly the completion of
construction took place outside of the six year period. Id. at 684, 448 S.E.2d at 116. Therefore, this opinion sheds no light on
whether N.C.G.S. § 1-50(a)(5)(a) runs from the date of sale or
the last day of construction.
Plaintiff argues alternatively that defendant's completion
of the work on the punch list constitutes the last act or
omission. We are not persuaded by this argument. A careful
examination of the punch list shows that defendant did not
perform work related to the harm complained of here. In order to
constitute a last act or omission, that act or omission must give
rise to the cause of action. Here, the work on the punch list did
not give rise to this action and therefore does not constitute
defendant's last act or omission.
For the reasons stated, we hold that the trial court's entry
of summary judgment for defendant is affirmed.
Affirmed.
Judges WALKER and McGEE concur.
*** Converted from WordPerfect ***