1. Damages and Remedies--breach of contract
The trial court's decision must be remanded since it erred in a non-jury breach of
contract trial by concluding plaintiff is entitled to recover damages of $36,000, based on the
finding of fact that plaintiff had carried its burden of proof only as to the amount which it
claimed was due by reason of changes mandated by the government officials of Guilford
County, because the trial court failed to address the factual dispute with respect to the necessity
or the cost of the required changes.
2. Appeal and Error--appealability--cross-assignment of error versus cross-appeal
In a non-jury breach of contract case, plaintiff improperly cross-assigned error to the trial
court's findings that the written contract was not properly executed and that plaintiff failed to
carry its burden of proof with respect to the amount of damages for changes other than those
prescribed by government officials because neither of the cross-assignments would provide an
alternative basis for upholding the $36,000 judgment as required by N.C. R. App. P. 10(d), and
therefore, plaintiff should have cross-appealed from the judgment.
Harkey, Lambeth, Nystrom, Fiorella & Morrison, L.L.P, by
Philip D. Lambeth, for plaintiff-appellee.
James, McElroy & Diehl, P.A., by William K. Diehl, Jr.,
Richard B. Fennell, Paul P. Browne and John R. Buric, for
defendant-appellant.
MARTIN, Judge.
Plaintiff Mann Contractors, Inc., brought this action to
recover monies allegedly owed by reason of an alleged contract with
defendant Flair with Goldsmith Consultants-II to construct
improvements upon property owned by defendant in Greensboro, N.C.
In its amended complaint, plaintiff alleged that it had fully
performed its obligations under the contract and that it was oweda balance of at least $80,000 for the work. Defendant answered,
denying that it had entered into the contract, denying that
plaintiff had performed the work required by the contract, and,
alternatively, alleging that it had paid plaintiff in full for all
of the work done by plaintiff. By counterclaim, defendant asserted
that plaintiff had wrongfully and negligently failed in the
performance of the renovations to defendant's property in a number
of respects, resulting in damages to defendant exceeding $10,000.
Neither party having requested a jury trial, the case was
heard by Judge Lamm sitting without a jury. After hearing the
evidence, the trial court found facts as follows:
1. This Court has jurisdiction over the
parties and the subject matter of this case,
and the case is properly before the Court.
2. Although the written contract introduced
by the Plaintiff has not been properly
executed, it is the document under which the
parties proceeded and to which by their
conduct they have agreed to be bound.
3. The contract between the parties provided
that the Plaintiff was to perform upfitting of
the Defendant's gym facility in Greensboro,
North Carolina for a contract price of
$246,850.00, together with the cost, plus ten
(10%) per cent [sic], of any change orders and
overages.
4. The contract also provided that all unpaid
balances would bear interest at the rate of 1
and 1/2% per month, or 18% per annum.
5. The Plaintiff presented evidence and
contended that it was entitled to recover from
the Defendant damages in the sum of
$140,969.02, plus interest. The Defendant
presented evidence and contended that the
Plaintiff was entitled to recover nothing from
the Defendant.
6. The Defendant has failed to pay all sums
due the Plaintiff under the contract. However, the Plaintiff has failed to carry its
burden of proof as to the amount of claimed
change orders and overages except regarding
those changes mandated by the governmental
officials of Guilford County.
7. The Defendant failed to present evidence
in support of its counterclaim against the
Plaintiff.
Based upon those findings of fact, the trial court made the
following conclusions of law:
1. The Defendant has breached its contract
with the Plaintiff.
2. The Plaintiff is entitled to recover from
the Defendant damages in the amount of
$36,000.00, together with interest thereon at
the rate of eighteen (18%) per cent [sic] per
annum from July 14, 1998 until the date of
this judgment, and at the legal rate
thereafter.
3. The Defendant's counterclaim should be
dismissed for lack of evidence in support
thereof.
The trial court entered judgment in favor of plaintiff in the
amount of $36,000, plus interest at 18% from 14 July 1998 until the
date of the judgment, 6 August 1998, and at the legal rate
thereafter, and dismissed defendant's counterclaim. Defendant gave
notice of appeal.
On 20 October 1998, upon motion of plaintiff asserting a
clerical error in the judgment, Judge Patti amended the judgment to
provide that the principal amount of the judgment was to bear
interest at 18% from 14 July 1994 until 6 August 1998, and then at
the legal rate. Defendant also gave notice of appeal from that
order.
*** Converted from WordPerfect ***