In the Matter of: Petition of Utilities, Inc., for Transfer of
the Certificate of Public Convenience and Necessity for Providing
Sewer Utility Service on North Topsail Island and Adjacent
Mainland Areas in Onslow County from North Topsail Water and
Sewer, Inc., and for Temporary Operating Authority
1. Utilities--certificate of public convenience and necessity--operation of sewage
treatment facilities--operational and managerial trouble
The North Carolina Utilities Commission did not err in its order granting Utilities, Inc.'s
application under N.C.G.S. §§ 62-111(a) and 62-116 to acquire the certificate of public
convenience and necessity for operation of the pertinent sewage treatment facility by concluding
that the sewage treatment facility was not an operationally and managerially troubled utility,
because: (1) all of the Commission's findings on this issue were supported by the testimony of
customers at the hearings to the effect that service by the current management under the
supervision of the Commission was satisfactory; and (2) the only operational violations found by
the Commission occurred during the period of prior management.
2. Utilities--certificate of public convenience and necessity--operation of sewage
treatment facilities--acquisition adjustment
The North Carolina Utilities Commission did not err in its order granting Utilities, Inc.'s
(UI) application under N.C.G.S. §§ 62-111(a) and 62-116 to acquire the certificate of public
convenience and necessity for operation of the pertinent sewage treatment facility by denying
UI's request to include the purchase price for the sewage treatment facility in the rate base and by
failing to give adequate weight to the alleged harmful conduct of the prior owners, because: (1)
the Commission pointed out that it is incumbent on the hearing examiner to look at each
acquisition adjustment on a case-by-case basis; (2) the Commission observed that a majority of
regulatory agencies had not allowed the acquisition adjustment to be reflected in rate base; and
(3) the Commission weighed all the evidence bearing upon its articulated standard and
determined UI had failed to carry its burden.
3. Utilities--certificate of public convenience and necessity--operation of sewage
treatment facilities--connection fees
The North Carolina Utilities Commission did not err in its order granting Utilities, Inc.'s
(UI) application under N.C.G.S. §§ 62-111(a) and 62-116 to acquire the certificate of public
convenience and necessity for operation of the pertinent sewage treatment facility by reducing
connection fees in the instant transfer proceeding under N.C.G.S. § 62-111 without complying
with the general rate case procedures established under N.C.G.S. § 62-133, because: (1) UI did
not preserve this issue for appellate review by failing to object, and UI is estopped from asserting
on appeal a position contrary to that advanced before the Commission; and (2) the Commissiondetermined that the issue of connection fees wa
s appropriate in the instant proceeding and that a
general rate case was not required.
Attorney General Michael F. Easley, by Assistant Attorney
General Margaret A. Force for appellee Attorney General.
JOHN, Judge.
Utilities, Inc. (UI), appeals a 6 January 2001 order (the
Order) of the North Carolina Utilities Commission (the Commission)
granting UI's application pursuant to N.C.G.S. §§ 62-111(a)(1999)
and 62-116 (1999) to acquire the certificate of public convenience
and necessity for operation of the sewage treatment facilities of
North Topsail Water and Sewer, Inc. (North Topsail) in Onslow
County. UI challenges certain provisions of the Order. We affirm
the Commission.
Pertinent procedural and factual background information
includes the following: From 1981 to 1994, North Topsail had been
owned and operated in the Topsail Beach and Sneads Ferry area of
Onslow County by developers Marlow Bostic (Bostic) and Roger Page
(Page). During that time, North Topsail repeatedly failed to meet
its public utility responsibilities and the developers engaged in
multiple improper and fraudulent actions. By 1994, the system hadbecome degraded, North Topsail was subject to numerous judgments
and other debts, the state had imposed environmental penalties, and
the accounting of funds was deficient. As a consequence, the
Commission intervened, removed Bostic from active management, and
appointed a manager directly responsible to the Commission.
Subsequently, Bostic filed personal bankruptcy, including
ownership of fifty percent of the corporate stock of North Topsail
among his assets. In 1999, UI filed a bid to purchase North
Topsail with the federal bankruptcy court, which bid contained no
acquisition adjustment allowing rate base treatment of the purchase
price. Rate base is the capital investment upon which a public
utility is permitted to earn a rate of return or profit.
UI subsequently entered into a 7 May 1999 Asset Purchase
Agreement (the Agreement) with the bankruptcy trustee for
acquisition of the sewer assets of North Topsail for $2.7 million,
subject to Court Approval and Regulatory Consent. The sale
included conveyance of the fifty percent interest of Page. Court
Approval was obtained in consequence of an Order Approving Sale
issued 11 June 1999 by the bankruptcy court
Regulatory Consent was defined in the Agreement as consent
of the [] Commission and its Public Staff to the sale contemplated
hereunder. On 23 June 1999, UI petitioned the Commission for
approval of the purchase and acquisition of the requisite
certificate of public convenience and necessity to operate the
sewage treatment facilities of North Topsail. UI also sought
permission to include the $2.7 million purchase price within its
rate base. Following evidentiary hearings conducted 30 September and 12
October 1999 (the hearings), the Commission issued its 6 January
2000 Order authorizing transfer of the certificate, but denying
rate base treatment of the purchase price. Included in the
Commission's thorough and detailed Order were the following
findings of fact:
53. Although [North Topsail] is a
financially-troubled utility, there are no
serious operational problems currently
affecting the system. The sewer system is
currently being operated in a satisfactory
manner.
54. All other things remaining equal,
inclusion of the proposed acquisition
adjustment in rate base would support a $12.00
per month or 38% increase in [North Topsail's]
residential rates.
55. The purchase price of $2.7 million that
UI agreed to pay for the North Topsail system,
which was established through an arms length
bidding process, was prudent.
56. UI is obligated to purchase North Topsail
whether the proposed acquisition adjustment is
included in rate base or not.
57. Approval of the proposed acquisition
adjustment is not in the public interest since
the benefits to customers resulting from the
allowance of rate base treatment of an
acquisition adjustment in this case would not
outweigh the resulting burden or harm to
customers associated therewith.
58. The proper level of connection fees is
$1,200 per residential equivalent unit.
. . . .
63. The transfer of the franchise and assets
of [North Topsail] to UI is in the public
interest and should be approved.
In addition, the Commission found that the North Topsail sewer
collection system was adequately serving the needs of [its]customers, that no new customer had been denied service, and that
the public had expressed no service complaints.
N.C.G.S. § 62-94 (1999) prescribes the scope of appellate
review of a decision by the Commission. State ex rel. Utilities
Comm'n. v. Southern Bell Tel. & Tel. Co., 88 N.C. App. 153, 165,
363 S.E.2d 73, 80 (1987). According to the section, the reviewing
court:
(b) . . . may affirm or reverse the decision of
the Commission, declare the same null and void,
or remand the case for further proceedings; or
it may reverse or modify the decision if the
substantial rights of the appellants have been
prejudiced because the Commission's findings,
inferences, conclusions or decisions are:
(1) In violation of constitutional provisions, or
(2) In excess of statutory authority or jurisdiction
of the Commission, or
(3) Made upon unlawful proceedings, or
(4) Affected by other errors of law, or
(5) Unsupported by competent, material and
substantial evidence in view of the entire
record as submitted , or
(6) Arbitrary or capricious.
G.S. § 62-94(b).
Further, on appeal, a, rule, regulation, finding,
determination, or order made by the Commission is deemed prima
facie just and reasonable. State ex rel. Utilities Comm'n. v.
Public Staff, 123 N.C. App. 43, 45, 472 S.E.2d 193, 195 (1996);
N.C.G.S. § 62-94(e)(1999). The appellate standard of review is
whether the Commission's findings of fact are supported by
competent, material and substantial evidence. State ex rel.
Utilities Comm'n. v. Nantahala Power & Light Co., 313 N.C. 614,
745, 332 S.E.2d 397, 474, rev'd on other grounds, 476 U.S. 953, __L. Ed. 2d ___ (1986); N.C.G.S. § 62-94(b)(5). Substantial ev
idence
is defined as
more than a scintilla or a permissible
inference. It means such relevant evidence as
a reasonable mind might accept as adequate to
support a conclusion.
State ex rel. Utilities. Comm'n. v. Southern Coach Co., 19 N.C.
App. 597, 601, 199 S.E.2d 731, 733 (1973). All findings of fact
made by the Commission which are supported by competent, material
and substantial evidence are conclusive. State ex rel. Utilities
Comm'n. v. Public Staff and Lacy H. Thornburg, 317 N.C. 26, 34, 343
S.E.2d 898, 903 (1986).
In determining whether to uphold the Commission's actions, the
appellate court is to review the whole record. N.C.G.S. § 62-94(c)
(1999). In doing so, the court may not replace the Commission's
judgment with its own when there are two reasonably conflicting
views of the evidence, State ex rel. Utilities Comm'n. v. Carolina
Indus. Group for Fair Utility Rates, 130 N.C. App. 636, 639, 503
S.E.2d 697, 699-700 (1998), and
it is for the administrative body . . . to
determine whether the weight and sufficiency
of the evidence and the credibility of the
witnesses, to draw inferences from the facts
and to appraise conflicting and circumstantial
evidence,
State ex rel. Utilities Comm'n. v. Thornburg, 314 N.C. 509, 515,
334 S.E.2d 772, 775 (1985). Finally, the appellate court . . .
may not substitute its judgment, either with respect to factual
disputes or policy disagreements, for that of the Commission. State ex rel. Utilities Commission v. North Carolina Textile
Manufacturers Association, 59 N.C. App. 240, 245, 296 S.E.2d 487,
490 (1982), rev'd on other grounds, 309 N.C. 238, 306 S.E.2d 113
(1983).
In order to facilitate appellate review, the Commission must
comply with the following statutory provisions:
(a) All final orders and decisions of the
Commission shall be sufficient in detail
to enable the court on appeal to
determine the controverted questions
presented in the proceedings and shall include:
(1) Findings and conclusions and the reasons
or bases therefor upon all the material issues
of fact, law, or discretion presented in the
record, and
(2) The appropriate rule, order, sanction,
relief or statement of denial thereof.
N.C.G.S. § 62-79(a) (1999). Further, although the Commission need
not comment upon every single fact or item of evidence presented by
the parties, Nantahala at 745, 332 S.E.2d at 474,
[t]he failure to include all the necessary
findings of fact is an error of law and a
basis for remand upon N.C.G.S. § 62-94(b)(4)
because it frustrates appellate review.
State ex rel. Utilities Comm'n. v. The Public Staff, 317 N.C. 26,
34, 343 S.E.2d 898, 904 (1986).
Bearing the foregoing principles in mind, we now turn to a
consideration of UI's assignments of error.
&
nbsp;I.
[1]Relying heavily upon the uncontroverted evidence of
mismanagement of North Topsail when operated by Bostic and Page, UI
first challenges the Commission's finding and subsequent conclusion
that North Topsail was not an operationally and manageriallytroubled utility. UI contends the Commission's determination was
not based upon record evidence and was in any event arbitrary and
capricious. We do not agree.
The significance of this first issue lies in the requirements
that ownership transfer of a public utility serve the public
convenience and necessity, see G.S. § 62-111(a), and that the
Commission inquire into all aspects of anticipated service and
rates occasioned and engendered by the proposed transfer, see State
ex rel. Utilities Comm. v. Village of Pinehurst, 99 N.C. App. 224,
229, 393 S.E.2d 111, 115 (1990).
In addition to the findings noted earlier, the Commission
found that the North Topsail system did
not suffer from the various system
deficiencies, ongoing environmental regulatory
violations and frequent customer complaints
that typify operationally-troubled systems,
and found and concluded that
the facilities owned and operated by [North
Topsail] are in satisfactory condition and are
currently sufficient to provide sewer utility
service to [its] customers.
We initially reiterate that the Order was most comprehensive
and replete with detail. The Commission thereby met the
obligations imposed upon it by Comm'n. v. Public Staff, 317 N.C. at
34, 343 S.E.2d at 904. Examination of the whole record, see G.S.
§ 62-94(c), moreover, reveals that all the Commission's findings
touching upon the first issue were supported by the testimony of
customers at the hearings to the effect that service by the current
management of North Topsail (under the supervision of theCommission) was satisfactory, the sole problem mentioned being
occasional odor from a pumping station, as well as by the testimony
of UI's own witness that there were no immediate plans for
substantial changes in operation of the system. Indeed, the only
operational violations found by the Commission occurred during the
period of management by Bostic and Page, and the record sustains
the Commission's observation that since 1994, [North Topsail]
management has operated its facilities in a sound and reasonable
manner. The Commission's not operationally troubled utility
finding was thus supported by competent, material, and substantial
evidence, see Comm. v. Nantahala Power & Light Co., 313 N.C. at
745, 332 S.E.2d at 474, is thereby conclusive, see Comm. v. Public
Staff and Lacy Thornburg, 317 N.C. at 34, 343 S.E.2d at 903, and
supports its like conclusion.
As to UI's contention the Order was arbitrary and capricious,
we note initially that such a characterization is difficult to
sustain. The actions of an administrative agency may be considered
arbitrary and capricious only when there is a lack of fair and
careful consideration; [and] when they fail to indicate 'any course
of reasoning and the exercise of judgment.' White v. N.C. Dept of
E.H.N.R., 117 N.C. App. 545, 547, 451 S.E.2d 376, 378, disc. review
denied, 340 N.C. 263, 456 S.E.2d 839 (1995). In the case sub
judice, careful review of the record and Order reflects fair and
thorough consideration by the Commission of the issues before it,
and compels the determination that the Commission's final decision
was the product of reasoning and the exercise of judgment. Accordingly, we reject UI's first argument.
&
nbsp;II.
[2]UI next advances what appears to be its primary
contention, i.e., that the Commission erred by denying UI's request
to include the purchase price for North Topsail in the rate base.
According to UI, the Commission fundamentally altered the
standard applied in prior acquisition adjustment cases. The
Commission's new standard, UI continues, requires the buying
utility to show it will create benefits for the ratepayer
in the period beginning after the transfer
that are separate and apart from those arising
from replacing the old owner and that outweigh
the negative rate impact of including the
plant acquisition adjustment in rate base.
Thus, UI concludes,
the acquiring utility must make concessions or
promise improvements above and beyond those
that accrued to ratepayers by relieving them
of the negative features of the erstwhile
owner's management that can be quantified and
shown to outweigh the negative rate impact of
return on increased investment before rate
base treatment of the plant acquisition
adjustment can be allowed.
UI also maintains the Commission failed to give adequate
weight to the harmful conduct of Bostic and Page, asserting it
seemed to dismiss this conduct as irrelevant because it did not
impact current operations. We consider UI's assertions under its
second argument ad seriatim.
It appears our appellate courts have not previously addressed
the acquisition adjustment issue. In its Order, however, the
Commission carefully analyzed its own prior decisions, see N.C.G.S.§ 62-65 (1999) (Commission may take judicial notice of its
opinions), and determined it had not articulated a single,
definitive test for resolving acquisition adjustment issues in
water and sewer transfer cases. The Commission pointed out its
earlier observation that it is incumbent upon the Hearing Examiner
to look at each acquisition adjustment on a case-by-case basis.
In re Carolina Water Service, Inc. of North Carolina (Carolina I),
76 NCUC Orders and Decisions 739, 755 (1986).
In addition, the Commission set out numerous factors that
appeared to have been considered in prior cases:
the prudence of the purchase price paid by the
acquiring utility; the extent to which the
size of the acquisition adjustment resulted
from an arms length transaction; the extent to
which the selling utility is financially or
operationally 'troubled;' the extent to which
the purchase price will facilitate system
improvements; the size of the acquisition
adjustment; the impact of including the
acquisition adjustment in rate base on the
rates paid by customers of the acquired and
acquiring utilities; [and] the desirability of
transferring small systems to professional
operators . . .,
none of which, the Commission noted, had been deemed universally
dispositive.
Nonetheless, the Commission, citing treatises on public
utility law, observed that a majority of regulatory agencies had
not allowed the acquisition adjustment to be reflected in rate
base:
most commissions are skeptical of transfers
between utilities at excess costs, so rate
base adjustments are generally not made unless
the utility can demonstrate actual, distinct
and substantial benefits to all affected
ratepayers. J Bonbright, A. Danielson, and D.Kamerschen, Principles of Public Utility Rates
286 (1987). See also 1 A. Priest, Principles
of Public Utility Regulation 189 (1969)
(although the majority of regulatory
commissions have refused to include
acquisition adjustments in rate base, such
treatment has been allowed where 'the
transactions was at arm's length,' 'resulted
in operating efficiencies,' 'received
regulatory approval as having been in the
public interest,' or 'made possible a
desirable integration of facilities).
Ultimately, the Commission concluded it was appropriate to
articulate a test for identifying the circumstances in which
inclusion of acquisition adjustments in rate base might be
appropriate. According to the Commission, the virtually
unlimited number of relevant considerations, some of which have
been set out above, all
relate to the question of whether the
acquiring utility paid too much for the
acquired utility and whether the customers of
both the acquired and the acquiring utilities
are better off after the transfer than they
were before that time.
Accordingly, the Commission adopted an approach, contrary to
[those] advocated by [] UI and the Public Staff, under which the
Commission would
refrain from allowing rate base treatment of
an acquisition adjustment unless the
purchasing utility [has] establishe[d] by the
greater weight of the evidence [] that the
price the purchaser agreed to pay for the
acquired utility was prudent and that both the
existing customers of the acquiring utility
and the customers of the acquired utility
would be better off (or at least no worse off)
with the proposed transfer, including rate
base treatment of any acquisition adjustment,
than would otherwise be the case.
The Commission commented that the foregoing method of analysiswas consistent with sound regulatory policy and with
the
construction of G.S. § 62-111(a) adopted by this Court, that is,
that the Commission must inquire into all aspects of anticipated
service and rates occasioned and engendered by the proposed
transfer, Village of Pinehurst, 99 N.C. App. at 229, 393 S.E.2d at
115. We agree.
Contrary to UI's assertion of a fundamentally altered
standard, the lengthy quotations from the Order quoted above amply
reveal that the Commission merely reviewed factors it had
previously deemed relevant as well as those cited by treatises on
regulatory law, and then simply articulated a standard
incorporating consideration of all such factors. See id. Rather
than failing to give appropriate weight to the troubled aspect of
North Topsail, as UI insists, moreover, review of the Order
indicates the Commission carefully weighed all the evidence bearing
upon its articulated standard and determined UI had failed to carry
its burden. Again, it is for the Commission to determine the
weight and sufficiency of the evidence. Comm. v. Thornburg, 314
N.C. at 515, 334 S.E.2d at 775.
First, the Commission considered whether the purchase price
was prudent. Taking judicial notice that North Topsail was
located in an area which is experiencing or is likely to
experience significant growth, the Commission found that a prudent
purchaser might well elect to pay more than net book value on the
assumption that acquiring the right to operate North Topsail had
independent value over and above the net book value of its assets. The Commission also observed that the purchase price had been
established in an arm's length bidding process in the bankruptcy
court and that the price agreed to by UI was the minimum amount
apparently necessary [for it] to prevail in the bidding. Based
upon these factors, the Commission concluded that the purchase
price was prudent.
The Commission next reviewed the evidence bearing upon
benefits and costs of the transfer should an acquisition adjustment
be allowed. Regarding whether North Topsail was a troubled
utility, the Commission commented that this question, while
relevant to a proper resolution of the acquisition adjustment
issue, should not be deemed dispositive. Indeed, as pointed out
by the Commission, placing undue weight upon the troubled
condition of the system would be inconsistent with the requirements
of G.S. § 62-111(a) and Comm. v. Village of Pinehurst, 99 N.C. App.
at 229, 393 S.E.2d at 115, that the Commission consider all
relevant factors.
The Commission concluded North Topsail at the time of the
hearing was financially troubled, but that North Topsail's past
travails, notwithstanding [t]he fervor of the parties' advocacy,
were relevant to the acquisition adjustment issue to the extent
that earlier developments impact[ed] North Topsail's current
situation. The Commission went on to observe that North Topsail
customers were not plagued with serious operational problems at the
time of the transfer and that transfer would not immediately affect
the quality of service provided to them.
In addition, the Commission noted UI's willingness to purchasethe system was not conditioned on inclusion of
the proposed
acquisition adjustment in the rate base, and that North Topsail's
customers would
get the benefit of ownership and operation by
an adequately-capitalized and professionally-
run utility regardless of [the Commission's]
decision
regarding the acquisition adjustment. Further, the Commission
pointed out that
[t]he fact that UI's obligation to purchase
North Topsail is not conditioned upon approval
of the proposed acquisition adjustment
distinguishes this case from the numerous
recent Commission decision upon which UI
places emphasis.
The Commission also considered the impact of the acquisition
adjustment on rates. It found that inclusion of the acquisition
adjustment would increase North Topsail's per-customer investment
from $503.00 to $1,390.00 and would
place upward pressure on the uniform rates
charged by UI's largest North Carolina
subsidiary in the event the two systems were
to be consolidated.
Before the Commission, UI relied heavily upon In re Heater
Utilities, Inc. (Hardscrabble), NCUC Docket No. W-274, Sub 122, 9
(1997), a case in which purchase of the utility was not conditioned
upon inclusion of the purchase price in rate base. The Commission
distinguished Hardscrabble, calculating the impact on rates of the
proposed acquisition in the case sub judice to be eight times that
allowed in Hardscrabble.
Finally, the Commission observed that UI's willingness to
purchase North Topsail was not conditioned upon inclusion of theacquisition adjustment in rate base and that at least one other
adequately-capitalized utility had attempted to buy North Topsail
without seeking rate base treatment for an acquisition adjustment.
Accordingly, the Commission concluded, customers of North Topsail
would obtain the benefit of ownership and operation by an
adequately capitalized and professionally run utility whether or
not inclusion of the acquisition adjustment in rate base was
approved.
In short, UI's assertions to the contrary, the Commission did
not create a new standard, but rather properly considered all
factors and rendered a decision consistent with prior acquisition
adjustment cases. We therefore reject UI's second argument.
&
nbsp;III.
[3]Lastly, UI assigns error to the Commission's reduc[tion
of] rates outside of a general rate case. UI cites the
Commission's reduction in the instant transfer proceeding under
G.S. § 62-111 of connection or tap fees and contends the
Commission erred in doing so without complying with the general
rate case procedures established in N.C.G.S. § 62-133 (1999). UI's
final argument is unfounded.
First, we note Public Staff's (Staff) response in its
appellate brief. Staff, in statements sustained by reference to
the instant record, observed that UI
stated in its proposed order [to the
Commission], 'At the hearing and in its
proposed order, UI agreed with the Public
Staff recommendation that connection feescharged after the transfer should be reduced'
. . . . [UI] offered no evidence during the
hearing contesting a lowering of the
connection fee. There is also nothing in the
record to substantiate the claim in [UI]'s
brief that ' . . . the substantial reduction
ordered in this case affects revenues to a
substantial degree and significantly lowers
rate of return.'
It appears, therefore, that UI may have failed to preserve
this final contention for our review, see N.C.R. App. P. 10(b)
(1999) (to preserve a question for appellate review, a party must
have presented to the trial [tribunal] a timely request, objection
or motion, stating the specific grounds for the ruling the party
desired), and that it is in any event estopped from asserting on
appeal a position contrary to that advanced before the Commission,
see Weil v. Herring, 207 N.C. 6, 10, 175 S.E. 836, 838 (1934) (the
law does not permit parties to swap horses between courts in order
to get a better mount [on appeal]).
Further, N.C.G.S. § 62-137 (1999) provides in pertinent part
as follows:
the Commission shall declare the scope of the
hearing by determining whether it is to be a
general rate case, under G.S. 62-133, or
whether it is to be a case confined to the
reasonableness of a specific single rate, a
small part of the rate structure, or some
classification of users involving questions
which do not require a determination of the
entire rate structure and overall rate of
return.
G.S. § 62-137. In its 3 August 1999 order setting a public hearing
on the proposed transfer of North Topsail to UI, the Commission
designated appropriate tap-fees as among the issues to be
addressed. Finally,
[c]ourts should be hesitant to disturb the
Commission's expert determination with regard
to the nature of the case presented,
particularly when its determination is made
prior to hearing and for the initial purpose
of setting the scope of the hearing and the
resulting amount of information which the
public utility will be required to furnish.
State ex rel. Utilities Comm'n. v. Rail Common Carriers, 42 N.C.
App. 314, 318, 256 S.E.2d 508, 511 (1979).
In short, the Commission having determined that the issue of
connection fees was appropriate in the instant proceeding and that
a general rate case was not required, and UI having interposed no
objection thereto, we decline to disturb the Commission's
determination. See id.
Affirmed.
Chief Judge EAGLES and Judge MCCULLOUGH concur.
*** Converted from WordPerfect ***