Appeal by defendant from judgment entered 31 January 2000 by Judge Carl
L. Tilghman in Lenoir County Superior Court. Heard in the Court of Appeals
29 March 2001.
Moore & Van Allen, PLLC, by Lewis A. Cheek and Michael A. DeFranco, for
plaintiff-appellees.
Mayer, Brown & Platt, by Robert B. Cordle and Mary K. Mandevilla;
Walker, Clark, Allen, Herrin & Morano, L.L.P., by Jerry A. Allen, Jr.,
for defendant-appellant.
MARTIN, Judge.
Plaintiffs brought this action to recover damages for personal injuries
to Horace Leon Whaley (hereinafter Whaley) and loss of consortium by
Rosalind Bailey Whaley following Whaley's injury by an electric shock
sustained at defendant's manufacturing plant in Kinston, North Carolina.
Plaintiffs alleged, inter alia, that Whaley's injuries were caused by
negligence on the part of defendant White Consolidated Industries, Inc.
(hereinafter defendant White) and its employee, Bobby Patton. Defendant
White filed its answer, denying negligence and asserting, as affirmative
defenses, negligence on the part of Whaley and on the part of his employer,
E & R, Inc., and co-worker, Hugh Sutton.
Briefly summarized to the extent necessary to an understanding of the
issues raised on appeal, the evidence presented at trial tended to show that
defendant White contracted to expand its plant to enable it to produce
dishwasher racks. The expansion required the installation of electrical
equipment, including substations, which would deliver power to the industrial
equipment. R.N. Rouse & Co. (Rouse) served as the general contractor for
the expansion project; Rouse subcontracted all electrical work to Triple-R
Electric, which in turn hired E & R, Inc., Whaley's employer, to perform thehigh voltage electrical work. E & R's responsibilities
included the assembly
and installation of three substations, the installation of the high voltage
cables to the HVL switch, and the connection of the high voltage cables from
the switch to the new substations. The target date for completion of the job
was Thanksgiving weekend 1995. Because certain substation equipment was not
delivered on time, E & R could not finish its work by this date. Although
the equipment was not fully assembled and thus not ready for operation, the
evidence showed that Bobby Patton, defendant's manufacturing engineer and
expansion project liaison, made the decision to move ahead with the original
plan to energize the high voltage cable over the Thanksgiving weekend.
Energizing the cable in turn energized the unfinished substations. William
Hardy Rouse, Jr., Vice President of Triple-R Electric, testified that
anything to do with electricity, especially turning the circuits on and
energizing equipment, is under our jurisdiction. Once the cable and
substations were energized, Patton padlocked the HVL switch handles.
Nevertheless, Patton did not tag the equipment. Certified Safety
Professional Raymond Boylston testified that, according to OSHA standards, a
danger tag must be placed on any piece of energized equipment anytime you
lock out a power circuit for electrical safety. Patton also did not
barricade the area. Although Patton testified that he warned several people
that the cable would be energized, including Whaley and his co-worker,
Sutton, all these people testified that they were not warned. The equipment
E & R needed to complete work on the substations arrived in early December,
and Whaley and Sutton returned to finish the job on 14 December 1995. Patton
testified that he knew the men would be working on the substations, but
believed they would be working on the distribution panels and not in the
cabinet containing the HVL switch. Shortly after starting work, while
reaching inside the cabinet to insert a bolt, Whaley leaned against an
energized metal bar and incurred a severe electric shock. He sufferedserious burns and remained in the Burn Center at UNC Hospitals until
22
January 1996; he also lost most of the function in his right arm.
Defendant's motion for directed verdict at the close of all the evidence
was denied. The jury returned a verdict finding defendant White negligent,
that such conduct was willful and wanton, and that neither Whaley nor his
employer was negligent. The jury awarded plaintiffs $1.27 million in
compensatory damages and $2.1 million in punitive damages. Defendant's post-
trial motions for judgment notwithstanding the verdict and, in the
alternative, for a new trial, were denied. Defendant appeals.
_______________
I.
[1]Assigning error to the denial of its motions for directed verdict,
judgment notwithstanding the verdict, and, alternatively, a new trial, as to
plaintiffs' claim for punitive damages, defendant White argues there was
insufficient evidence to support a finding that the conduct of its employee,
Patton, was willful or wanton. We disagree.
A motion for directed verdict pursuant to G.S. § 1A-1, Rule 50(a) tests
the sufficiency of the evidence to support a verdict for the non-moving
party.
Manganello v. Permastone, Inc., 291 N.C. 666, 231 S.E.2d 678 (1977).
A motion for judgment notwithstanding the verdict pursuant to G.S. § 1A-1,
Rule 50(b) is essentially a renewal of an earlier motion for directed
verdict.
Bryant v. Nationwide Mutual Fire Ins. Co., 313 N.C. 362, 329 S.E.2d
333 (1985). The same test is applied when ruling on either motion.
Id. On
a defendant's motion for a directed verdict or judgment notwithstanding the
verdict, the plaintiff's evidence must be taken as true and considered in the
light most favorable to him, and the motion should be denied only if, as a
matter of law, such evidence is insufficient to justify a verdict for the
plaintiff.
Dickinson v. Pake, 284 N.C. 576, 201 S.E.2d 897 (1974).
In considering any motion for directed verdict, the trialcourt must view all the evidence t
hat supports the
non-movant's claim as being true and that evidence must
be considered in the light most favorable to the
non-movant, giving to the non-movant the benefit of every
reasonable inference that may legitimately be drawn from
the evidence with contradictions, conflicts, and
inconsistencies being resolved in the non-movant's favor.
Bryant at 369, 329 S.E.2d at 337-38 (citation omitted).
While a motion for directed verdict or judgment notwithstanding the
verdict raises an issue of law, a motion for a new trial pursuant to G.S. §
1A-1, Rule 59 is addressed to the trial court's discretion.
Bryant, supra.
In this case, defendant White assigns error to the denial of its motion for
a new trial made upon the grounds contained in Rule 59(a)(7): Insufficiency
of the evidence to justify the verdict or that the verdict is contrary to
law. A motion made upon such grounds authorizes the trial court to appraise
the evidence and to grant a new trial if, in the opinion of the court, the
verdict is contrary to the greater weight of the credible evidence.
In re
Will of Buck, 350 N.C. 621, 628, 516 S.E.2d 858, 863 (1999). Appellate
review of a trial court's ruling on a Rule 59(a)(7) motion raises no question
of law, but presents only the question of whether the record affirmatively
demonstrates an abuse of discretion, i.e., a probable 'substantial
miscarriage of justice', by the trial judge.
Id. at 625, 516 S.E.2d at 861
(citations omitted).
To support an award of punitive damages, plaintiff must show that
defendant's conduct went beyond negligence and was 'done willfully or under
circumstances of rudeness or oppression, or in a manner which evinces a
reckless and wanton disregard of plaintiff's rights.'
Beck v. Carolina
Power & Light Co., 57 N.C. App. 373, 383, 291 S.E.2d 897, 903,
affirmed, 307
N.C. 267, 297 S.E.2d 397 (1982) (citation omitted). Punitive damages may be
awarded only when
the defendant commits the actionable legal wrong
willfully (i.e., knowingly, intentionally andvoluntarily), wantonly (i.e., in conscious and
intentional disregard of and indifference to the rights
and safety of the plaintiff), or maliciously (i.e.,
motivated by personal hatred, ill will or spite for the
plaintiff).
Hornby v. Pennsylvania Nat'l. Mut. Cas. Ins. Co., 77 N.C. App. 475, 481, 335
S.E.2d 335, 339 (1985),
disc. review denied, 316 N.C. 193, 341 S.E.2d 570
(1986) (citation omitted). 'An act is wanton when it is done of wicked
purpose or when done needlessly, manifesting a reckless indifference to the
rights of others.'
Siders v. Gibbs, 39 N.C. App. 183, 187, 249 S.E.2d 858,
861 (1978) (citation omitted).
In the present case, Patton, acting as liaison for defendant White, made
the decision to energize the high voltage cable over Thanksgiving weekend
1995, in spite of the fact that the substations lacked necessary equipment
and were not operational. Patton energized the cable, which in turn
energized the substations, knowing employees from E & R still had work to
perform on the substations. Patton testified that he believed plaintiff and
Sutton were aware the line was energized; he also claimed to have told three
other people involved in the project that the line was energized, but those
people testified that they were never warned. Although Patton padlocked the
HVL switch handles, these locks did not prevent exposure to potentially
deadly electrical currents for those working inside the cabinet. Finally,
Patton did not tag the substations, as OSHA standards require, to notify
other workers that the equipment was energized. Taken in a light most
favorable to plaintiff, the evidence presented was sufficient to go to the
jury on the question of whether Patton's behavior demonstrated a reckless
indifference for the rights of others. Furthermore, in light of such
evidence, we cannot say the trial court's discretionary ruling denying
defendant White's alternative motion for a new trial pursuant to Rule
59(a)(7) on the issue of punitive damages amounted to a miscarriage of
justice or an abuse of discretion.
See In re Will of Buck,
supra. II.
[2]Defendant White next argues that the trial court erred in denying
its motions for directed verdict, judgment notwithstanding the verdict, and,
alternatively, a new trial, because Whaley was contributorily negligent as a
matter of law. We disagree.
It is well established in North Carolina that a claimant's contributory
negligence is a complete bar to recovery on a claim for damages sustained by
reason of a defendant's negligent conduct.
Smith v. Fiber Controls Corp., 300
N.C. 669, 268 S.E.2d 504 (1980). The doctrine of contributory negligence has
been summarized by the North Carolina Supreme Court:
Every person having the capacity to exercise ordinary
care for his own safety against injury is required by law
to do so, and if he fails to exercise such care, and such
failure, concurring and cooperating with the actionable
negligence of defendant contributes to the injury
complained of, he is guilty of contributory negligence.
Ordinary care is such care as an ordinarily prudent
person would exercise under the same or similar
circumstances to avoid injury.
Id. at 673, 268 S.E.2d at 507 (citation omitted). [A] plaintiff is
contributorily negligent as a matter of law, thereby entitling a defendant to
a directed verdict, when 'the evidence taken in the light most favorable to
[the] plaintiff establishes [his] negligence so clearly that
no other
reasonable inferences or conclusions may be drawn therefrom.'
Wolfe v.
Wilmington Shipyard, Inc., 135 N.C. App. 661, 667, 522 S.E.2d 306, 311 (1999)
(emphasis added) (quoting
Dunbar v. City of Lumberton, 105 N.C. App. 701,
703, 414 S.E.2d 387, 388 (1992)).
The evidence tends to show that defendant White's employee, Patton, was
the only individual who knew the high voltage cable and unfinished
substations were energized on 14 December 1995. Further, E & R contracted to
perform the high voltage electrical work and thus had no reason to assume the
lines would be energized prior to the completion of the substations. William
Rouse, of Triple-R Electric, the company which contracted with defendant tocomplete all the electrical work for the project, testified that
he was not
aware the cable was energized. Rouse further stated that it was not
reasonable to assume plaintiff would have been aware the line was energized:
Based on the condition of the equipment--I mean, they
wrapped the equipment up. We put light bulbs in it to
keep moisture out of it. There shouldn't have been any
power on it. I wouldn't have asked myself. I would
probably have done just like he did: went in there and
gone back to work. I mean, that was his responsibility
to do it. That's what they got paid for.
We hold the evidence, taken in the light most favorable to plaintiffs, does
not so clearly show that Whaley failed to exercise ordinary care for his own
safety as to compel the conclusion that he was contributorily negligent.
See
Partin v. Carolina Power & Light Co., 40 N.C. App. 630, 253 S.E.2d 605,
disc.
review denied, 297 N.C. 611, 257 S.E.2d 219 (1979) (citation omitted).
Therefore, defendant was not entitled to a directed verdict or judgment
notwithstanding the verdict based on Whaley's contributory negligence.
Similarly, the trial court did not abuse its discretion in denying defendant
White's motion for a new trial on the grounds the verdict finding that Whaley
was not contributorily negligent was against the greater weight of the
evidence.
[3]In a related assignment of error, defendant White contends the trial
court erred in instructing the jury as to the standard of care required of
plaintiff Whaley to avoid injury to himself. The trial court instructed:
[a] person is under a duty to use ordinary care to
protect himself and others from injury. Ordinary care
means that degree of care which a reasonable and prudent
person would use under the same or similar circumstances
to protect himself and others from injury.
Defendant White contends the court should have instructed the jury, in
accordance with its requested instruction, that Whaley was held to a
heightened standard of care which required utmost diligence and foresight
and which was commensurate with the danger to be avoided. However, as our
Supreme Court has observed, the standard of care does not vary. The standard is
always the rule of the prudent man, or
the care which a prudent man ought to use under like
circumstances. What reasonable care is, of course,
varies in different cases and in the presence of
different conditions. The standard is due care, and due
care means commensurate care under the circumstances.
(citations omitted).
Jenkins v. Leftwich Elec. Co., 254 N.C. 553, 559-60, 119 S.E.2d 767, 772
(1961). We believe the instruction given in this case adequately informed
the jury that Whaley was required to use due care, that is, care commensurate
with the circumstances. The trial court was not required to use the exact
language requested by defendant White, as the charge given was correct and
included in substance the requirement that Whaley exercise that same degree
of care as a reasonable man would exercise commensurate with the
circumstances.
See King v. Higgins, 272 N.C. 367, 158 S.E.2d 67 (1967);
Williams v. Randolph, 94 N.C. App. 413, 380 S.E.2d 553,
disc. review denied,
325 N.C. 437, 384 S.E.2d 547 (1989).
III.
In its next assignment of error, defendant White contends it is
entitled, pursuant to G.S. § 97-10.2(e), to a reduction in the damages
awarded Whaley by the jury in the amount of the worker's compensation
benefits which he received because the negligence of his employer, E & R,
Inc., through Whaley's co-worker, Hugh Sutton, combined to produce the
injury. As required by the statute, the issue of E & R's negligence was
submitted to the jury; the jury determined that Whaley's injury was not
caused by negligence on the part of E & R, Inc. Nevertheless, defendant
White contends the trial court erred in denying its motion for a directed
verdict and judgment notwithstanding the verdict, and alternatively, for a
new trial, on the issue because the evidence showed that Sutton was negligent
as a matter of law. We disagree.
There was evidence tending to show that Sutton arrived on the job-site
before Whaley and, thus, had perhaps more time to observe the surroundingsthan did Whaley. Sutton admitted seeing the padlocks on the swit
ch handles.
Nevertheless, he testified that seeing the padlocks did not lead him to
believe the substations were energized because no lock-out tags were found
on the substations. In addition, electrical contractor Rouse admitted during
the trial that, based on the look of the substations, [t]here shouldn't have
been any power on it. I wouldn't have asked myself. Finally, Sutton spoke
with defendant White's project liaison on the morning of the accident, but
Patton did not tell him that the line was energized. Thus, the issue of
Sutton's negligence was properly submitted to the jury, and defendant White's
motions were properly denied.
IV.
[4]n its final assignment of error, defendant White contends the trial
court erred when it refused to declare a mistrial after the trial was
interrupted due to flooding caused by Hurricane Floyd. The decision as to
whether to declare a mistrial is within the discretion of the trial court;
accordingly, 'unless the ruling is clearly erroneous so as to amount to a
manifest abuse of discretion, it will not be disturbed on appeal.'
State v.
Parker, 119 N.C. App. 328, 336, 459 S.E.2d 9, 13 (1995) (citation omitted).
In its Memorandum Decision and Order, the trial court explained:
the Court made inquiry of the jury regarding their
ability to continue with the case and discharge their
duty. All jurors, without hesitating, indicated that
they could continue as jurors and complete the case
despite the flood and its effect on them, and despite the
two-week delay.
Although the trial was delayed by extensive flooding caused by Hurricane
Floyd and was completed under arguably trying circumstances, it affirmatively
appears from the record that the trial court made inquiry as to the effect of
the delay and reached a reasoned decision based upon the jurors' responses.
Hence, defendant White has failed to show a manifest abuse of discretion in
the trial court's decision to deny defendant's motion for a mistrial andcomplete the trial following the two week delay. This assignment o
f error is
overruled.
No error.
Judges BIGGS and JOHN concur.
*** Converted from WordPerfect ***