1. Construction Claims_payment bond_subcontractor's employee
The trial court correctly granted summary judgment for
defendants Ellis-Don, Federal, Travelers, and Aegis with respect
to payment bond claims arising from construction at Raleigh
Durham International Airport. None of the work which was the
subject of the complaint was performed in prosecution of the
work called for in the contract between Ellis-Don and Reis
Trucking, so that plaintiff was not entitled to reimbursement
under any payment bond issued by the parties in this case.
N.C.G.S. § 44A-25(5).
2. Civil Procedure_affidavit_service_day of summary judgment
hearing
The trial court erred by excluding an affidavit from
consideration on summary judgment where the affidavit was mailed
the day before the hearing and filed in superior court on the day
of the hearing. Although this approach afforded no actual notice
prior to the hearing, it was proper under the then applicable
rules. N.C.G.S. § 1A-1, Rule 5(c)(1999).
3. Corporations_piercing corporate veil_material issue of fact
The trial court erred by granting summary judgment on a
claim for piercing the corporate veil where defendants presented
an affidavit asserting that their company was not
undercapitalized and that company funds were not intermingled
with personal funds, and plaintiff submitted an affidavit
asserting undercapitalization, commingling of funds, and a
failure to keep formal records.
Bugg, Wolf & Wilkerson, P.A., by William J. Wolf, for
plaintiff-appellants.
Safran Law Offices, by Todd A. Jones, for defendant-appellees
Reis Trucking & Construction, Inc., Larry Reis, and Gwen M.Reis.
Maupin Taylor & Ellis, P.A., by Gilbert C. Laite, III and
Kevin W. Benedict, for defendant-appellee Aegis Security
Insurance Company.
Nigle B. Barrow, Jr., for defendant-appellees Ellis-Don
Construction, Inc., Federal Insurance Company, and Travelers
Casualty and Surety Company.
GREENE, Judge.
Mr. Berry O. Monteau (Monteau) and his company, Bay Area Turf,
Inc. (collectively Plaintiff) appeal 26 May 2000 orders granting
summary judgment in favor of defendants Larry and Gwen Reis (the
Reises), Ellis-Don Construction, Inc. (Ellis-Don), Travelers
Casualty and Surety Company (Travelers), Federal Insurance Company
(Federal), and Aegis Security Insurance Company (Aegis). Plaintiff
also appeals a concurrent order sustaining objections by defendants
Reis Trucking and Construction, Inc. (Reis Trucking), the Reises,
and Aegis to an affidavit submitted by Plaintiff in opposition to
summary judgment.
In November 1997, Plaintiff entered into an oral agreement
with Reis Trucking, owned by the Reises, to perform certain
estimating and bidding preparation services in return for $500 per
week in expenses plus a six percent commission on gross receipts
from successfully bid projects that resulted in a contract award.
Plaintiff, pursuant to its contract obligations, enabled Reis
Trucking to submit bids to general contractors who were bidding on
a project for the Raleigh Durham International Airport (RDU). On
9 January 1998, the RDU project was awarded to Ellis-Don as general
contractor. Ellis-Don issued a labor and material payment bond toRDU on 13 January 1998, wherein Ellis-Don and its sureties, Federal
and Travelers, promised that every claimant . . . who has not been
paid in full before the expiration of a period of ninety (90) days
after the date on which the last of such claimant's work or labor
was done or performed . . . may sue on this bond . . . . The bond
defined a proper claimant as one having a direct contract with the
Principal [Ellis-Don] or with a Subcontractor of the Principal for
labor, material, or both, used or reasonably required for use in
the performance of the [RDU] Contract. On 17 January 1998, Ellis-
Don hired Reis Trucking as a sub-contractor, and a written contract
to that effect was signed by Reis Trucking on 6 March 1998 and by
Ellis-Don on 9 March 1998.
From 13 February 1998 to 15 February 1998, Plaintiff performed
some project management work for Reis Trucking at the RDU site even
though, as Plaintiff's deposition testimony shows, Plaintiff and
Reis Trucking had not yet agreed on any compensation and there was
no intention to apply any future salary retrospectively.
Plaintiff's November 1997 agreement with Reis Trucking terminated
on 6 March 1998. On 9 March 1998, Reis Trucking issued a
subcontract labor and material payment bond to Ellis-Don mirroring
the language of the Ellis-Don bond and underwritten by Aegis as
surety. Reis Trucking had paid Plaintiff's expenses pursuant to
their November 1997 agreement but failed to pay the six percent
commission ($58,087.80) Plaintiff claims it earned by securing the
RDU project. On 26 June 1998, Plaintiff sent Reis Trucking and
the Reises written notice claiming payment under the payment bond
issued by Reis Trucking. On 18 August 1998, Plaintiff sent anotice to Ellis-Don requesting payment under the January 1998
payment bond.
On 5 March 1999, Plaintiff filed a complaint seeking relief
against Reis Trucking and the Reises for breach of contract and
nonpayment under the March 1998 bond. The complaint alleged the
Reises, as sole officers and directors of Reis Trucking, had
operated Reis Trucking as their mere alter ego, grossly
undercapitalized the business, and intermingled the company
finances with their personal finances. Plaintiff prayed for relief
in the amount of $58,078.80, [t]he value of the labor and services
provided by Plaintiff to Reis [Trucking] on the [RDU] project.
Plaintiff asserted Reis Trucking became indebted to Plaintiff for
this amount [u]pon Ellis-Don's acceptance of Reis[] [Trucking's]
bid.
In addition, Plaintiff joined in its complaint Ellis-Don,
Travelers, Federal, and Aegis as defendants. Plaintiff sought
judgment against Ellis-Don as principal and Travelers and Federal
as sureties under the January 1998 payment bond in the amount of
$58,078.80 for work performed by Plaintiff on the RDU project.
Plaintiff also requested relief against Aegis as surety under the
March 1998 payment bond issued by Reis Trucking.
All defendants except Reis Trucking moved for summary
judgment. In support of the motion, Ellis-Don submitted an
affidavit denying Plaintiff performed any labor on the project.
The Reises presented an affidavit denying any undercapitalization
or intermingling of funds and stating that the Reises and Reis
Trucking maintained separate bank accounts. On 22 May 2000,Plaintiff mailed to all defendants an opposing affidavit in which
Monteau stated Reis Trucking was grossly undercapitalized, the
Reises intermingled business and personal funds, committed to
projects while lacking the capital to properly perform the work,
failed to meet payroll obligations, and did not adhere to formal
record keeping. On 22 May 2000 after the close of business, copies
of Plaintiff's affidavit were also faxed to defendants' attorneys.
The affidavit was filed on 23 May 2000, the day of the summary
judgment hearing. Defendants Reis Trucking, the Reises, and Aegis
objected to the affidavit on the grounds that service by mail and
by fax on 22 May 2000 was not timely. The trial court sustained
defendants' objection.
*** Converted from WordPerfect ***