1. Construction Claims_delays_allocation of responsibility by
architect_action between contractors
The trial court did not err when sitting without a jury on a
construction claim between the heating contractor (plaintiff) and
the general contractor (defendant) by holding that the
architect's failure to assign any direct liability for delay to
defendant served as an implicit determination that defendant was
not directly responsible to plaintiff for delays in plaintiff's
performance. Article 15 of the general conditions of the project
vested authority in the architect to determine responsibility for
delay among the prime contractors, and plaintiff did not meet its
burden of establishing that the architect's failure to allocate
liability to defendant was dishonest or a mistake.
2. Construction Claims _delays_action between
contractors_causation required
An injured contractor may not recover delay damages by
merely demonstrating that such damages were within the
contemplation of the parties at the time the contract was
entered. Although there was evidence here that defendant may
have contributed to the overall project delay, plaintiff failed
to show how delays specifically caused by defendant impacted
plaintiff's work performance.
3. Damages_construction claim_measurement_total cost
method_failure to show practicability
A prime contractor in a construction action against another
prime contractor failed to prove that it sustained damages that
can be ascertained and measured with reasonable certainty where
plaintiff failed to establish practicability, the first of four
criteria for the total cost method of determining losses, and
failed to properly establish responsibility for its additional
costs, since it did not isolate the nature and extent of specific
delays and connect them to an act or omission by defendant.
4. Construction Claims_action between contractors_delays_notice
The trial court, sitting without a jury on a construction
claim between prime contractors, did not err by finding that
plaintiff failed to provide defendant with timely notice of its
claims. It was necessary for the architect, the arbiter of
disputes between the prime contractors, to be notified when one
contractor caused delay to another. Discussions at weekly
foremen's meetings and monthly progress meetings with the
architect and owner did not constitute sufficient notice.
Plaintiff never gave written or verbal notice of potential claimsat these meetings and never gave notice that it was suffering
potential harm; moreover, plaintiff accepted final payment, which
constituted a waiver of all claims.
Erwin and Bernhardt, P.A., by Fenton T. Erwin, Jr., for
plaintiff-appellant.
Safran Law Offices, by Perry R. Safran, for defendant-
appellee.
THOMAS, Judge.
This breach of contract case between prime contractors is
based on a claim of delay in the construction of the University of
North Carolina Neuropsychiatric Hospital on the Chapel Hill campus.
Plaintiff, Biemann and Rowell Company, was the heating and
ventilating contractor, while defendant, The Donohoe Companies,
Inc., D/B/A Donohoe Construction Company, was the general
contractor.
In a bench trial, the trial court entered judgment in favor of
defendant on all of plaintiff's claims. Plaintiff appeals,
advancing the following four arguments: (1) the trial court erred
in its determination of the architect's role in apportioning
liability among the prime contractors; (2) it is not necessary to
prove that defendant proximately caused injury to plaintiff; (3)
the evidence establishes that plaintiff incurred damages for which
defendant is liable; and (4) defendant's actual knowledge of
potential claims against it was sufficient notice. For the reasons
herein, we affirm the decision of the trial court.
On or about 1 July 1992, plaintiff and defendant entered intoseparate contracts with the State of North Carolina, t
hrough the
University of North Carolina at Chapel Hill (owner), to build the
multi-million dollar Neuropsychiatric Hospital. The parties
operated under a multiple-prime contract pursuant to N.C. Gen.
Stat. § 143-128, which requires that separate contracts be awarded
for the major branches of work when a public building project's
expected costs exceed $500,000. N.C. Gen. Stat. § 143-128 (1999).
Each separate contractor is directly liable to the State of North
Carolina and to the other contractors. N.C. Gen. Stat. § 143-
128(b) (1999). Accordingly, a prime contractor may be sued by
another prime contractor for economic loss resulting from the first
prime contractor's failure to fully perform its duties under the
terms of the separate contracts. See Bolton v. T.A. Loving Co., 94
N.C. App. 392, 397, 380 S.E.2d 796, 800, disc. review denied 325
N.C. 545, 385 S.E.2d 496 (1989).
As the general contractor, defendant was assigned the role of
project expediter. While the owner hired a schedule coordinator to
develop the progress schedule of the contractors, under Article
14(j) of the general conditions of the separate contracts defendant
remained responsible for maintain[ing] the progress schedule,
making monthly adjustments, updates, corrections, etc., that are
necessary, keeping all Contractors and the [architect] fully
informed.
The original critical path method progress schedule provided
for completion of the project within 1004 days. Delays, ultimately
totaling 369 days, occurred throughout the project. They were at
least partially attributable to poor weather, logistical problems
due to the number of contractors working within the limited area ofthe site, a structural defect which caused the building to settle,
and revisions made by the owner to the sixth floor plans during the
course of the project. As a result, the contractors were
frequently forced to complete work out of the anticipated sequence.
To accelerate completion of the project, it was the
understanding of the contractors, architect, and schedule
coordinator that defendant would dry-in the building by
installing a moisture seal at the fifth floor level. Normally,
work is restricted until the roof is built because lower levels
would otherwise be exposed to moisture accumulation in inclement
weather. This temporary building seal was intended to allow work
to take place at the lower levels before the roof was installed.
None of those involved who testified had previously seen a building
seal, however, or knew of an agreement among the parties as to what
specifically would be done to create one. Defendant never
installed the building seal.
Letters and summaries written by HKS Architects (architect)
indicate that defendant was failing to complete work according to
the project schedule and to fulfill its duties as project
expediter. Neither the architect nor the owner, however, ever
assigned any direct liability for delay to defendant. Meeting
minutes and observation reports, which list delays of plaintiff's
activities, indicate that plaintiff also contributed to overall
project delay. Substantial completion of the project occurred on
15 May 1996, and the owner took beneficial occupancy on that date.
Plaintiff maintains that defendant's failure to install the
building seal, as well as defendant's failure to supervise and
properly schedule its subcontractors, caused delays to plaintiff'swork and as a consequence plaintiff suffered economic loss.
Plaintiff did not notify defendant of its claims against them until
October of 1996. By that time, plaintiff had released 78 of its 80
subcontractors.
Initially, we note that a trial court's findings of fact in a
bench trial have the force of a jury verdict and are conclusive on
appeal if there is competent evidence to support them, even though
the there may be evidence that would support findings to the
contrary. State v. Coronel, 145 N.C. App. 237, 250, 550 S.E.2d
561, 510 (2001). However, conclusions of law reached by the trial
court are reviewable de novo. Mann Contractors v. Flair with
Goldsmith Consultants--II, Inc., 135 N.C. App. 772, 775, 522 S.E.2d
118, 121 (1999).
[2]Plaintiff argues by the second assignment of error that it
is not necessary to prove that defendant proximately caused injury
to plaintiff. The contention is that under Bolton, an injured
contractor may recover delay damages by merely demonstrating that
such damages were within the contemplation of the parties at the
time the contract was entered. We disagree.
A prime contractor has a duty to the other prime contractors
for the full performance of all duties and obligations due under
the terms of the separate contracts and in accordance with the
plans and specifications. N.C. Gen. Stat. § 143-128. Bolton did
not dispense with the causation element necessary to maintain this
statutory cause of action for breach of contractual duties. See
Bolton, 94 N.C. App. at 406-07, 380 S.E.2d 805-06. Rather, this
Court in Bolton held that in order to recover special damages, theplaintiff must not only prove the elements of a breach of c
ontract
claim, but also that the requested damages were contemplated at the
time of contracting. Id. Plaintiff's reliance on Bolton is
mistaken. To recover damages, plaintiff must show that the
contract was breached by defendant and that the breach caused
plaintiff's damages.
Although there is evidence here that defendant may have
contributed to overall project delay, plaintiff failed to show how
delays specifically caused by defendant impacted plaintiff's work
performance. Central to plaintiff's argument is defendant's
failure to install the temporary building seal. The installation
of the temporary seal, however, first appeared as an activity on
the critical path in April of 1994, long after the project began
experiencing delays. Plaintiff, moreover, merely presented a chart
of instances of delay allegedly attributable to plaintiff, and
relied on anecdotal testimony about the delays. Finally, plaintiff
failed to take into account delays attributable to other causes.
We accordingly dismiss plaintiff's second assignment of error.
[3]Plaintiff next assigns as error the trial court's holding
that plaintiff failed to prove that it sustained damages for which
defendant was liable. A plaintiff has an obligation to prove such
facts as will furnish a basis for the calculation of damages. See
Esteel Co. v. Goodman, 82 N.C. App. 692, 698, 348 S.E.2d 153, 157
(1986), disc. review denied 318 N.C. 693, 351 S.E.2d 745 (1987).
For the breach of an executory contract, a plaintiff may recover
only such damages as can be ascertained and measured with
reasonable certainty. See Tillis v. Calvine Cotton Mills, Inc.,251 N.C. 359, 366, 111 S.E.2d 606, 612 (1959). Moreover, wh
ere
both parties contribute to the delay, neither can recover damages,
unless there is proof of clear apportionment of the delay and
expense attributable to each party. See Blinderman Constr. Co. v.
United States, 695 F.2d. 552, 559 (Fed. Cir. 1982) (quoting Coath
& Goss, Inc. v. United States, 101 Ct. Cl. 702, 714-15 (1944)).
Rather than using a direct or actual cost method of
quantifying actual losses incurred resulting from defendant's
actions, plaintiff relied on the modified total cost method, a
variation of the total cost method, to prove delay damages. Under
the total cost method, a contractor seeks the difference between
its total costs incurred in performance of the contract and its bid
price. See Youngdale & Sons Const. Co., Inc. v. United States, 27
Fed. Cl. 516, 541 (1993). This method is condoned only where no
other way to compute damages is feasible, because it blandly
assumes--that every penny [sic] of the plaintiff's costs are prima
facie reasonable, that the bid was accurately and reasonably
computed, and that the plaintiff is not responsible for any
increases in cost. Id. (citing Urban Plumbing & Heating Co. v.
United States, 408 F.2d. 382, 394 (Ct. Cl. 1969), cert. denied 398
U.S. 958, 26 L.Ed. 2d 542 (1970)); F.H. McGraw & Co. v. United
States, 130 F. Supp. 394, 400 (Ct. Cl. 1955).
Plaintiff must satisfy the conjunctive four-part test for
recovery under the total cost method: (i) the impracticability of
proving actual losses directly; (ii) the reasonableness of its bid;
(iii) the reasonableness of its actual costs; and (iv) the lack of
responsibility for the added costs. Id. (citing Servidone Constr.
Corp. v. United States, 931 F.2d 860, 861 (Fed. Cir. 1991));Boyajian v. United States, 423 F.2d 1231, 1243 (Ct. Cl. 1970). The
modified total cost method is the total cost method with
adjustments for any deficiencies in plaintiff's proof in satisfying
the four requirements. The modified approach assumes the elements
of a total cost claim have been established, but permits the court
to modify the test so that the amount plaintiff would have received
under the total cost method is only the starting point from which
the court will adjust the amount downward to reflect the
plaintiff's inability to satisfy the test. Youngdale, 27 Fed. Cl.
at 541 (citing Servidone, 931 F.2d at 862).
The trial court determined that plaintiff failed to establish
impracticability, the first of the four criteria for using the
total cost method in determining losses. Plaintiff kept a daily
log book of labor overrun throughout the project but made no
attempt to tie the extra labor costs to any specific delay. In
addition, plaintiff failed to establish that its bid was
reasonable. Plaintiff's employees testified that the bid was
aggressive, and plaintiff produced no other bids for the heating
and ventilation work for comparison. Plaintiff also failed to
properly establish responsibility for its additional costs, since
it did not isolate the nature and extent of specific delays and
connect them to an act or omission by defendant. Instead,
plaintiff allocated only a narrow set of costs to itself, and then
attributed the remainder of the cost overrun entirely to defendant.
Plaintiff failed to prove that it sustained damages that can be
ascertained and measured with reasonable certainty and consequently
we reject this assignment of error.
*** Converted from WordPerfect ***