Link to original WordPerfect file
How to access the above link?
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the
print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
NO. COA01-238
NORTH CAROLINA COURT OF APPEALS
Filed: 4 June 2002
INTERMOUNT DISTRIBUTION, INC.
Plaintiff-Appellee,
v. Henderson County
No. 99 CVS 499
PUBLIC SERVICE COMPANY OF
NORTH CAROLINA, INC.,
Defendant-Appellant.
Appeal by defendant from judgment entered 21 December 2000
by Judge Ronald K. Payne in Henderson County Superior Court.
Heard in the Court of Appeals 5 December 2001.
Ronald E. Sneed for plaintiff-appellee.
Van Winkle, Buck, Wall, Starnes & Davis, P.A., by Jones P.
Byrd, P. Michelle Rippon and Donald R. Pocock, for
defendant-appellant.
TIMMONS-GOODSON, Judge.
Public Service Company of North Carolina, Inc. (PSNC)
appeals from an order granting partial summary judgment in favor
of Intermount Distribution, Inc. (Intermount). The relevant
facts are as follows: Intermount acquired title to certainproperty located in Henderson County, North Carolina from Bessie
Riddle (Riddle). The land was subject to an easement acquired
by PSNC from Riddle pursuant to a right-of-way agreement dated 7
October 1955. The agreement granted PSNC and its successors and
assigns, the right to maintain, construct, replace, change the
size of, or lay one or more pipelines across the property for the
transportation of natural gas and other materials that may be
transported through a pipeline. The agreement gave PSNC the right
to select the route by laying the first pipeline. Shortly after
obtaining the right-of-way across the property, PSNC laid an
eight-inch diameter high pressure transmission pipeline (T-1.)
for the transportation of natural gas from Gastonia, North
Carolina to Asheville, North Carolina.
In late 1997, PSNC began installing its second pipeline (T-
1B.) on the property. The second pipeline was twelve inches in
diameter and parallel to T-1. The installation of T-1B was
necessary to satisfy increasing demands on its pipeline system in
Western North Carolina. In March of 1998, PSNC sent a letter to
Intermount concerning the installation of its proposed pipeline.
Before installing T-1B, PSNC learned that Intermount planned
to construct a building to the east of T-1. In accordance with
industry and its own regulations, PSNC had maintained for many
years that its easement was thirty-five (35) feet to the west andfifteen feet (15) to the east. However, in an effort to
accommodate Intermount's construction plans, PSNC relocated its
easement and constructed T-1B to the west of T-1 rather than to
the east, which gave Intermount an additional twenty feet east of
T-1 to start construction. This accommodation would keep any
building construction fifteen feet from T-1 and would also
provide sufficient space to maneuver and operate any specialized
equipment required to install, maintain, and repair the
pipelines.
Intermount subsequently began to design and construct its
building within ten feet of T-1. PSNC continued to advise
Intermount that a clearance of fifteen feet was necessary for
safety reasons. When PSNC refused to acquiesce, Intermount filed
this action.
On 14 April 2000, PSNC moved for summary judgment. The only
issue before the court was the enforceable width of the easement
or right-of-way claimed by PSNC. On 21 December 2000, the court
granted partial summary judgment holding that PSNC's pipeline
easement was eight inches wide. The court then certified that
its order affected a substantial right of the parties,
particularly PSNC, therefore providing the basis for this appeal.
____________________________________________________
The dispositive issue on appeal is whether the trial court
erred in entering partial summary judgment in favor of Intermount
and determining, as a matter of law, that the actual width of
PSNC's easement is eight inches.
At the outset, we note that the denial of a motion for
summary judgment is not typically appealable. See Lamb v.
Wedgewood South Corp., 308 N.C. 419, 424, 302 S.E.2d 868, 871
(1983). Likewise, [a] grant of partial summary judgment,
because it does not completely dispose of the case, is an
interlocutory order from which there is ordinarily no right of
appeal. Liggett Group v. Sunas, 113 N.C. App. 19, 23, 437
S.E.2d 674, 677 (1993). The order appealed from in the instant
case granted partial summary judgment in favor of plaintiff and
therefore, it is an interlocutory order. As a general rule, a
party has no right to immediate appellate review of an
interlocutory order. See Tise v. Yates Construction Co., 122
N.C. App. 582, 584, 471 S.E.2d 102, 105 (1996). However, appeal
from an interlocutory order is permissible under two specific
statutory exceptions. Town Center Assoc. v. Y & C Corp., 127 N.C.
App. 381, 384, 489 S.E.2d 434, 436 (1997). First, if the order
or judgment is final as to some but not all of the claims or
parties, and the trial court certifies the case for appeal
pursuant to N.C. Gen. Stat. § 1A-1, Rule 54(b), an immediateappeal will lie. N.C. Dept. of Transportation v. Page, 119 N.C.
App. 730, 734, 460 S.E.2d 332, 334 (1995). The order appealed
from in the instant case contained the trial court's
certification pursuant to Rule 54(b). We now allow the appeal
and address the merits of the case.
Summary judgment is appropriate if the pleadings,
depositions, answers to interrogatories, and admissions on file,
together with the affidavits, if any, show that there is no
genuine issue as to any material fact and that any party is
entitled to a judgment as a matter of law. N.C. Gen. Stat. §
1A-1, Rule 56(c)(2001). The party moving for summary judgment has
the burden of showing that either an essential element of the
plaintiff's claim does not exist or that plaintiff cannot produce
evidence to support an essential element of the claim. Evans v.
Appert, 91 N.C. App. 362, 365, 372 S.E.2d 94, 96, disc. review
denied, 323 N.C. 623, 374 S.E.2d 584 (1988). The evidence
presented is viewed in the light most favorable to the non-
movant. Bruce-Terminex Co. v. Zurich Ins. Co., 130 N.C. App.
729, 733, 504 S.E.2d 574, 577 (1998).
The deed in the instant case was created in 1955 and granted
PSNC an easement for the purpose of laying, constructing,
maintaining, operating, repairing, altering, replacing and
removing pipelines, for the transportation of natural gas, andother substances. Although the right-of-way agreement did not
distinctly specify the width of the easement, the agreement
provided that PSNC shall have all other rights and benefits
necessary or convenient for the full enjoyment or use of the
rights herein granted including the right from time to time, to
lay, construct, maintain, alter, repair, remove, change the size
of, and replace one or more additional lines of pipe
approximately parallel with the first pipe line laid by PSNC.
We begin by noting that an easement deed, such as the one
disputed in the instant case, is a contract. See Cochran v.
Keller, 84 N.C. App. 205, 211, 352 S.E.2d 458, 462 (1987), disc.
review denied, 322 N.C. 605, 370 S.E.2d 244 (1988). In North
Carolina, it is an established principle that the possessor of an
easement has all rights that are necessary to the reasonable and
proper enjoyment of that easement. Keller v. Cochran, 108 N.C.
App. 783, 784, 425 S.E.2d 432, 434 (1993). Deeds of easement are
construed according to the rules of construction of contract so
as to ascertain the intention of the parties as gathered from the
entire instrument at the time it was created. See Higdon v.
Davis, 315 N.C. 208, 216, 337 S.E.2d 543, 547 (1985). This
court has held that [w]hen an easement is created by express
conveyance and the conveyance is 'perfectly precise' as to the
extent of the easement, the terms of the conveyance control. Williams v. Abernethy, 102 N.C. App. 462, 464-65, 402 S.E.2d 438,
440 (1991) (citation omitted). 'If the conveyance is silent as
to the scope of the easement, extrinsic evidence is inadmissible
as to the scope or extent of the easement.' Swaim v. Simpson,
120 N.C. App. 863, 864, 463 S.E.2d 785, 786-87 (1995)(quoting
Patrick K. Hetrick & James B. McLaughlin, Jr., Webster's Real
Estate Law in North Carolina, § 15-21 (4th ed. 1994)), affirmed,
343 N.C. 298, 469 S.E.2d 553 (1996). However, in this situation,
a reasonable use is implied. Id. In such cases, '[a]n
easement in general terms is limited to a use which is reasonably
necessary and convenient . . . for the use contemplated.'
Shingleton v. State, 260 N.C. 451, 457, 133 S.E.2d 183, 188
(1963)(quoting 12A Am. Jur., Easements, § 113, pp. 720, 721); see
also Keller, 108 N.C. App. at 784-85, 425 S.E.2d at 434.
Whether a specific use of an easement constitutes a reasonable
use is a question of fact and is not a matter of law. Id.
In the instant case, Intermount maintains that the width of
the right-of-way became fixed when the original pipeline was
installed. Therefore, the width of the easement is only the
width of the pipe itself and the minimal amount necessary for he
maintenance of its pipelines. Contrary to Intermount's
assertions, PSNC contends that the owner of a pipeline right-of-
way is entitled to reasonable access to the land for the purposeof maintaining and making repairs. In support of this
proposition, PSNC relies on a line of cases that have held that a
fifty-foot wide easement is reasonable and necessary for the
safety and maintenance of gas pipelines. See Columbia Gas
Transmission Corp. v. Tarbuck, 62 F.3d. 538, 544 (3rd Cir. 1995)
(holding that fifty feet is a reasonable and necessary width
needed to operate a twenty-inch gas pipeline); Columbia Gas
Transmission Corp. v. Savage, 863 F.Supp. 198, 202 (M.D.Pa. 1994)
(finding fifty feet necessary for an easement in order to safely
maintain a 14-inch pipeline); and Crane Hollow, Inc. v. Marathon
Ashland Pipe Line LLC, 138 Ohio App. 3d. 57, 69, 740 N.E.2d 328,
336 (2000) (holding that evidence supported a finding that use
and acquiescence of the easement established a fifty-foot width
for pipeline easement).
Although not specifically addressed in North Carolina, we
find guidance in other jurisdictions that have held that when the
width of an easement is not specifically defined in the grant,
such as the one in the instant case, then the previously
undefined width is then established by the rule of reasonable
enjoyment. Sunnyside Valley Irrigation District v. Dickie, ____
Wash. Ct. App. ____, 43 P.3d 1277, 1281 (2002). Under the
doctrine of reasonable enjoyment, the width of an undefined
easement is determined by considering the purpose of the easementand establishing a width necessary to effectuate that purpose.
Id. Where an easement is granted without limitations on its use,
the grantee may partake in other reasonable uses that develop
over time if such uses significantly relate to the object for
which the easement was granted. 61 Am. Jur. 2d, Pipelines, §
31 (2002). Determination of the necessary width under the
doctrine of reasonable enjoyment [presents] a question of fact.
Sunnyside Valley Irrigation District, ____ Wash Ct. App. at
_____, 43 P.3d. at 1281. Although the extent of an easement is
limited to that which has been granted, courts have also
consistently permitted express easements to accommodate modern
developments, so long as the use remains consistent with the
purpose of which the right was originally granted. Savage, 863
F.Supp. at 202. This is based upon a presumption that advances
in technology are contemplated in the grant of the easement.
Id.
In the instant case, the original deed as granted in 1955,
expressly stated the purpose of the grant, which was the right
from time to time, to lay, construct, maintain, operate, . . .
change the size of and replace one or more additional lines of
pipe[.] Clearly, the reasonableness of the amount of space
needed to operate and maintain PSNC's pipelines raises a question
of fact that precludes summary judgment. We therefore concludethat the trial court erred in concluding as a matter of law that
the width of the easement was eight inches and remand this case
for a factual finding regarding the reasonableness of the amount
of space needed to operate PSNC's gas pipelines.
Reversed and remanded.
Judges HUDSON and TYSON concur.
*** Converted from WordPerfect ***