PIEDMONT REBAR, INC., d/b/a
CAROLINA REBAR,
Plaintiff,
v
.
Randolph County
No. 98-CVS-1754
SUN CONSTRUCTION, INC. and
EAST COAST HOSPITALITY, L.L.C.,
Defendants.
No brief filed for plaintiff appellee.
Stubbs & Perdue, P.A., by Trawick H. Stubbs, Jr., and John W.
King, Jr., for defendant appellant East Coast Hospitality,
L.L.C.
TIMMONS-GOODSON, Judge.
East Coast Hospitality, L.L.C. (East Coast) appeals from an
order of the trial court denying its motions seeking relief from a
default judgment granting Piedmont Rebar, Inc. (Piedmont) a lien
against certain real property owned by East Coast. For the reasons
stated herein, we affirm the order of the trial court.
On 6 October 1998, Piedmont filed a complaint in Randolph
County Superior Court against East Coast and Sun Construction, Inc.
(Sun Construction) for breach of contract. The complaint allegedthat Sun Construction and East Coast entered into a contract for
Sun Construction to build a motel on certain property owned by East
Coast. Piedmont thereafter entered into a subcontract with Sun
Construction to provide reinforcing rod for the Project.
According to the complaint, Piedmont provided the contracted
materials but was never reimbursed for such supplies, resulting in
a loss to Piedmont of over ten thousand dollars. Piedmont asserted
recovery based upon quantum meruit and breach of its contract with
Sun Construction, and it requested a lien upon any funds owed by
East Coast to Sun Construction, as well as a subrogation lien on
the property owned by East Coast.
Neither Sun Construction nor East Coast responded to the
complaint, and Piedmont subsequently obtained a default judgment
against both of them. On 8 February 1999, the trial court entered
an order and judgment awarding Piedmont judgment against Sun
Construction for the principal sum of $10,568.20, plus interest in
the amount of $1,426.70. The trial court also decreed Piedmont to
have a lien against any funds owed to Sun Construction by East
Coast, as well as a lien against the real property owned by East
Coast.
On 29 January 2001, East Coast filed a motion in the cause
requesting that the 8 February 1999 judgment be amended to reflect
that East Coast Hospitality, LLC did not violate the Notice of
Claim of Lien of the Plaintiff and that any claim against the
real estate owned by [East Coast] be vacated. On 8 February 2001,
East Coast filed a motion seeking relief from the default judgmentunder Rule 60(b)(6) of the Rules of Civil Procedure. The trial
court heard the matter on 19 February 2001. Upon review of the
relevant materials and argument by counsel, the trial court
concluded that East Coast had failed to demonstrate sufficient
grounds to support its Motions and therefore denied such motions.
East Coast filed a timely notice of appeal to this Court.
____________________________________________________
East Coast contends that the trial court erred by denying its
motion to set aside the default judgment on the grounds that the
judgment was void for lack of jurisdiction. East Coast also
submits that the court erred in denying its motion in the cause.
Under section 1A-1, Rule 60(b)(6) of our Rules of Civil
Procedure, a judgment may be set aside for any reason justifying
relief from the operation of the judgment. N.C. Gen. Stat. § 1A-
1, Rule 60(b)(6) (2001). A motion to set aside a judgment based on
lack of personal service is proper under this section. See Nye,
Mitchell, Jarvis & Bugg v. Oates, 109 N.C. App. 289, 291-92, 426
S.E.2d 291, 293 (1993). Rule 60(b)(6) is equitable in nature and
permits a trial judge to exercise his discretion in granting or
withholding the desired relief. See State ex. rel. Envir. Mgmt.
Comm. v. House of Raeford Farms, 101 N.C. App. 433, 448, 400 S.E.2d
107, 117, disc. review denied, 328 N.C. 576, 403 S.E.2d 521 (1991).
As such, the trial judge's ruling may be reversed on appeal only
upon a showing that the decision results in a substantial
miscarriage of justice. See id.
East Coast argues that the default judgment is void for lackof process. East Coast notes that, although it received proper and
timely notice of Piedmont's complaint, Sun Construction was not
served with notice until thirty-three days after the issuance of
the summons. East Coast asserts that the lack of proper service to
Sun Construction rendered the default judgment void. This argument
has no merit.
When Piedmont filed its complaint, it had thirty days
(See footnote 1)
after
the date of the issuance of the summons in which to effect personal
service of summons. See N.C. Gen. Stat. § 1A-1, Rule 4(c) (1999).
Where personal service is not effected within the time specified,
the action is discontinued as to any defendant not theretofore
served with summons within the time allowed. N.C. Gen. Stat. §
1A-1, Rule 4(e) (2001) (emphasis added). As East Coast was
properly served within the time specified by statute, the action
clearly did not discontinue as to East Coast. Moreover, where an
action is brought against two or more defendants who are jointly or
severally liable, and the summons is served on one or more, but not
all of them, the plaintiff may proceed against the defendants
served, and if the plaintiff recovers judgment, such judgment may
be entered against all the defendants who are jointly indebted, and
enforced against the joint property of all and the separate
property of the defendants served. See N.C. Gen. Stat. § 1-113
(2001); Hancock v. Southgate, 186 N.C. 278, 282, 119 S.E. 364, 366(1923).
East Coast contends, however, that the monetary portion of the
judgment concerned Sun Construction and not East Coast. East Coast
asserts that, because service to Sun Construction was defective,
that portion of the judgment as to Sun Construction is void, and if
the monetary portion of the judgment is void, then the lien against
the real property cannot be enforced. We disagree.
The 8 February 1999 order and judgment of the trial court
decrees that Plaintiff has a lien on the Property in the full
amount of this judgment. The lien has an effective date of
February 20th, 1998. Pursuant to N.C.G.S. 44A-13(b), the Property
shall be sold to satisfy the lien[.] The amount of the lien filed
by Piedmont was $10,568.20. The amount of the lien against the
real property awarded by the trial court in favor of Piedmont
arises from the lien itself, and not from the monetary damages
assessed against Sun Construction.
We conclude that the trial court did not abuse its discretion
in denying East Coast's motion for relief from the default
judgment. The judgment against East Coast was not void, and the
record reveals no extraordinary circumstances or other showing by
East Coast that would warrant relief from the judgment. See Howell
v. Howell, 321 N.C. 87, 91, 361 S.E.2d 585, 588 (1987) (noting that
relief under Rule 60(b)(6) is properly granted only if
extraordinary circumstances exist and the movant makes a showing
that justice demands the granting of such relief). East Coast
argues that, as a subcontractor, Piedmont had no right to the lienunless the general contractor could enforce the lien, and that
Piedmont failed to show that Sun Construction had any rights
against East Coast. East Coast failed to assert this defense at
trial, however, and did not appeal the default judgment. East
Coast is therefore precluded from seeking relief under Rule
60(b)(6) on this basis. See Concrete Supply Co. v. Ramseur Baptist
Church, 95 N.C. App. 658, 660, 383 S.E.2d 222, 223 (1989) (holding
that, where the defendant property owner failed to appeal from
judgment against it in favor of a subcontractor, it was not
entitled to relief under Rule 60(b)(6) on the grounds that it had
already paid the general contractor all that was due under the
contract). We therefore overrule East Coast's first assignment of
error.
By its second assignment of error, East Coast argues that the
trial court erred in denying its motion in the cause to determine
the extent to which it violated the notice of claim of lien served
by Piedmont. East Coast points to that portion of the default
judgment which states that, Plaintiff [has] a lien on the Property
to the extent it is determined that East Coast violated the Notice
of Claim of Lien[.] Because the default judgment makes no
findings regarding the extent to which East Coast violated the
notice of claim of lien, East Coast asserts that the lien cannot be
enforced. We do not agree with this argument.
East Coast concedes that the above-stated language represents
only a portion of the default judgment. As noted supra, the
default judgment clearly orders that, Plaintiff has a lien againstthe Property in the full amount of this judgment. This language
fully supports the enforcement of Piedmont's lien against the real
property. Moreover, East Coast did not appeal from the default
judgment. In fact, the record shows that East Coast took no steps
in this matter whatsoever until 29 January 2001, nearly two years
after the default judgment was entered against it, and nearly four
years after it was served notice of Piedmont's claim of lien. We
conclude that the trial court properly denied the motion in the
cause, and we overrule East Coast's second assignment of error.
In conclusion, we hold that the trial court properly denied
the motions brought by East Coast. The order of the trial court is
therefore
Affirmed.
Judge WYNN concurs.
Judge TYSON concurs in the result.
TYSON, Judge, concurring in the result.
I concur in the result of the majority's opinion. N.C.G.S. §
44A-23 provides first, second, and third tier subcontractors a
right of subrogation to the lien of the contractor who dealt with
the owner, regardless of any lien upon the funds. Electric Supply
Co. of Durham, Inc. v. Swain Elec. Co., Inc., 328 N.C. 651, 654,
403 S.E.2d 291, 293 (1991).
Plaintiff was a first tier subcontractor. Article 2, Part 2
of Chapter 44A of the General Statutes provides for perfection of
liens by subcontractors. A lien in favor of a subcontractor mayarise either: (1) directly under N.C.G.S. § 44A-18 and N.C.G.S. §
44A-20; or (2) by subrogation under N.C.G.S. § 44A-23. Mace v.
Bryant Constr. Corp., 48 N.C. App. 297, 304, 269 S.E.2d 191, 195
(1980).
N.C.G.S. § 44A-23 provides that:
a first, second, or third tier subcontractor,
who gives notice as provided in this Article,
may, to the extent of his claim, enforce the
lien of the contractor created by Part 1 of
Article 2 of this Chapter. The manner of such
enforcement shall be as provided by G.S. 44A-7
through 44A-16. The lien is perfected as of
the time set forth in G.S. 44A-10 upon filing
of claim of lien pursuant to G.S. 44A-12.
Upon the filing of the notice and claim of
lien and the commencement of the action, no
action of the contractor shall be effective to
prejudice the rights of the subcontractor
without his written consent.
N.C. Gen. Stat. § 44A-23(a), (b) (2001) (Emphasis supplied). Under
this provision, a claim of lien against real property is perfected,
or enforceable, upon the filing and service of both a notice of
claim of lien pursuant to N.C.G.S. § 44A-19 and a claim of lien
pursuant to N.C.G.S. § 44A-12. Universal Mechanical, Inc. v. Hunt,
114 N.C. App. 484, 486, 442 S.E.2d 130, 131-32 (1994).
Entry of default against a defendant results in all
allegations of plaintiff's complaint being deemed admitted against
that defendant, and thereafter, defendant is prohibited from
defending on the merits of the case. Spartan Leasing, Inc. v.
Pollard, 101 N.C. App. 450, 460, 400 S.E.2d 476, 482 (1991). While
defendant East Coast may have had a meritorious defense had it
answered the complaint, because of its failure to appear or file an
appeal from the default judgment, defendant East Coast is bound bythe judgment validly entered. Waters v. Qualified Personnel, Inc.,
32 N.C. App. 548, 233 S.E.2d 76 (1977).
*** Converted from WordPerfect ***