Link to original WordPerfect file
How to access the above link?
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the
print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
NO. COA01-1146
NORTH CAROLINA COURT OF APPEALS
Filed: 15 October 2002
RPR & ASSOCIATES, INC., a South Carolina Corporation,
Plaintiff,
v
.
THE UNIVERSITY OF NORTH CAROLINA-CHAPEL HILL and THE NORTH
CAROLINA DEPARTMENT OF ADMINISTRATION,
Defendants.
Appeal by plaintiff and defendant University of North Carolina
at Chapel Hill from judgment entered 1 May 2000 by Judge Donald W.
Stephens in Wake County Superior Court. Heard in the Court of
Appeals 11 June 2002.
Brian E. Upchurch for plaintiff appellant-appellee.
Attorney General Roy Cooper, by Special Deputy Attorney
General Thomas J. Ziko, for defendant appellant-appellee.
TIMMONS-GOODSON, Judge.
RPR & Associates, Inc. (plaintiff) and the University of
North Carolina at Chapel Hill (defendant) appeal from judgment in
favor of plaintiff for breach of contract by defendant. For the
reasons set forth herein, we affirm in part and reverse in part the
judgment of the trial court.
The procedural and factual history of this appeal is a lengthy
one: On 15 January 1998, plaintiff filed a complaint in Wake County
Superior Court against defendant, the State of North Carolina (the
State), and the North Carolina Department of Administration (the
DOA). The complaint alleged that plaintiff, a South Carolina
corporation, entered into a contract with the State, by and throughdefendant and the DOA, for the purpose of constructing the George
Watts Hill Alumni Center (Alumni Center), located on the campus
of the University of North Carolina at Chapel Hill. The complaint
set forth claims for breaches of contract and of warranty.
All three defendants thereafter filed motions to dismiss
plaintiff's complaint pursuant to Rules 12(b)(1), (2), (4), (5) and
(6) of the North Carolina Rules of Civil Procedure. After a
hearing on the motions, the trial court entered an order granting
the State's motion to dismiss pursuant to Rule 12(b)(5) for
insufficient service of process. The trial court denied, however,
the motions to dismiss filed by defendant and the DOA, which
denials defendant and the DOA appealed to this Court on 12 August
1998.
Despite the appeal filed by defendant and the DOA, plaintiff
continued to pursue its claims in the superior court. Defendant
and the DOA resisted such proceedings, contending that their notice
of appeal removed jurisdiction from the trial court pending
resolution of the appeal. Plaintiff rejoined that, as the orders
from which defendant and the DOA appealed were interlocutory and
nonappealable, the notice of appeal did not deprive the trial court
of jurisdiction or otherwise stay proceedings at the trial level.
On 8 September 1998, the trial court denied defendant's motion
to stay proceedings pending resolution of the appeal. Defendant
thereafter filed a petition for writs of certiorari and supersedeas
with the Court of Appeals, and moved for a temporary stay of the
trial court proceedings. Although this Court initially granteddefendant's motion for a temporary stay, it dissolved the stay on
23 September 1998. The Court also denied defendant's petition for
writ of supersedeas and dismissed the petition for writ of
certiorari. On 30 September 1998, this Court denied a second
motion filed by defendant for a temporary stay.
Defendant then filed petitions for writ of supersedeas and
writ of certiorari with the Supreme Court, which petitions were
denied. By order dated 12 October 1998, the Supreme Court also
denied defendant's motion for temporary stay of the judgment of the
Court of Appeals. On 15 October 1998, the Court of Appeals denied
defendant's petition for writ of prohibition.
Defendant moved the trial court once more for a stay of
proceedings, which motion was heard on 3 May 1999. Upon reviewing
the repeated denials of defendant's motions by the appellate
courts, as well as the 8 September 1998 order by the trial court
denying a stay of proceedings, the trial court once again denied
defendant's motion to stay proceedings. On 2 June 1999, the Court
of Appeals denied further petitions by defendant for writ of
supersedeas and prohibition.
On 6 October 1999, this Court heard the appeal by defendant
and the DOA from the trial court's denial of their motions to
dismiss plaintiff's complaint. See RPR & Assocs. v. State, 139
N.C. App. 525, 534 S.E.2d 247 (2000), affirmed per curiam, 353 N.C.
362, 543 S.E.2d 480 (2001) (hereinafter RPR I). The first issue
addressed by the RPR I Court was the interlocutory nature of the
appeal. The Court concluded that, because the motion to dismisswas based in part on the doctrine of sovereign immunity, the denial
of such motion affected a substantial right, thus rendering the
decision of the trial court immediately appealable. See id. at
527, 534 S.E.2d at 250. Having determined that the appeal was
properly before the Court, the Court proceeded to address the
substantive issues of the case. Concluding that plaintiff had
complied with all applicable statutory procedures, the Court held
that defendant had waived its claim to sovereign immunity from suit
by entering into the contract with plaintiff. The Court thus held
that the trial court properly denied defendant's motion to dismiss.
The Court filed its opinion on 15 August 2000.
On 22 November 1999 and 21 February 2000, after defendant's
appeal had been heard in this Court, but before a decision had been
filed, the merits of plaintiff's case came before the trial court.
The parties presented evidence for more than two weeks, upon the
conclusion of which the trial court entered a judgment one hundred
and twenty pages in length. In its judgment, filed 1 May 2000, the
trial court concluded that defendant had breached its contract with
plaintiff, causing substantial monetary injury. The trial court
assessed such damages against defendant as $851,058.38, with
interest accrued in the amount of $748,931.37. It is from this
judgment that defendant and plaintiff now appeal.
___________________________________________________
Defendant presents three issues on appeal, arguing that the
trial court erred by (1) continuing to assert jurisdiction over the
case after defendant filed its notice of appeal; (2) assessinginterest in the judgment against defendant; and (3) awarding
excessive monetary damages. Plaintiff also argues three issues on
appeal, contending that the trial court erred in (1) failing to
award damages on its masonry claim; (2) failing to award damages
based on plaintiff's excessive punchlist claim; and (3) failing
to make findings regarding an offset against the judgment granted
to defendant. We first examine defendant's assignments of error.
I. Defendant's Appeal
Defendant argues that the trial court erred by (1) exercising
jurisdiction over the case; (2) awarding interest; and (3) awarding
damages in amounts unsupported by the evidence. We address these
issues in turn.
A. Functus Officio
By its first assignment of error, defendant argues that the
trial court had no jurisdiction over the case after defendant
perfected its appeal, and that therefore, the trial court erred in
entering judgment against defendant.
As a general rule, once a party gives notice of appeal, such
appeal divests the trial court of its jurisdiction, and the trial
judge becomes functus officio. See Bowen v. Motor Co., 292 N.C.
633, 635, 234 S.E.2d 748, 749 (1977); Sink v. Easter, 288 N.C. 183,
197, 217 S.E.2d 532, 541 (1975). Functus officio, which translates
from Latin as having performed his of her office, is defined as
being without further authority or legal competence because the
duties and functions of the original commission have been fully
accomplished. Black's Law Dictionary 682 (7th ed. 1999). Thus,when a court is functus officio, it has completed its duties
pending the decision of the appellate court. The principle of
functus officio stems from the general rule that two courts cannot
ordinarily have jurisdiction of the same case at the same time.
See Wiggins v. Bunch, 280 N.C. 106, 110, 184 S.E.2d 879, 881
(1971).
It follows from the principle of functus officio that if a
party appeals an immediately appealable interlocutory order, the
trial court has no authority, pending the appeal, to proceed with
the trial of the matter. See Patrick v. Hurdle, 7 N.C. App. 44,
45-46, 171 S.E.2d 58, 59 (1969). Where a party appeals from a
nonappealable interlocutory order, however, such appeal does not
deprive the trial court of jurisdiction, and thus the court may
properly proceed with the case. See Veazey v. Durham, 231 N.C.
357, 364, 57 S.E.2d 377, 382-83 (1950); T & T Development Co. v.
Southern Nat. Bank of S.C., 125 N.C. App. 600, 603, 481 S.E.2d 347,
349, disc. review denied, 346 N.C. 185, 486 S.E.2d 219 (1997).
[A] litigant cannot deprive the trial court of jurisdiction to
determine a case on its merits by appealing from a nonappealable
interlocutory order of the trial court. Velez v. Dick Keffer
Pontiac-GMC Truck, Inc., 144 N.C. App. 589, 591, 551 S.E.2d 873,
875 (2001).
An interlocutory order is immediately appealable if such order
affects a substantial right of the parties involved. See N.C. Gen.
Stat. §§ 1-277(a), 7A-27(d) (2001). A right is substantial when it
will clearly be lost or irremediably and adversely affected if theorder is not reviewed before final judgment. See Cagle v. Teachy,
111 N.C. App. 244, 246, 431 S.E.2d 801, 802 (1993).
Admittedly the 'substantial right' test for
appealability of interlocutory orders is more
easily stated than applied. It is usually
necessary to resolve the question in each case
by considering the particular facts of that
case and the procedural context in which the
order from which appeal is sought was entered.
Waters v. Personnel, Inc., 294 N.C. 200, 208, 240 S.E.2d 338, 343
(1978); see also Cagle, 111 N.C. App. at 246, 431 S.E.2d at 802
(noting that there are [n]o hard and fast rules . . . for
determining which appeals affect a substantial right). The trial
court has the authority, however, to determine whether or not its
order affects a substantial right of the parties or is otherwise
immediately appealable. See Utilities Comm. v. Edmisten, Attorney
General, 291 N.C. 361, 365, 230 S.E.2d 671, 674 (1976); Veazey, 231
N.C. at 364, 57 S.E.2d at 382-83; T & T Development Co., 125 N.C.
App. at 603, 481 S.E.2d at 349; Benfield v. Benfield, 89 N.C. App.
415, 420, 366 S.E.2d 500, 503 (1988). Pursuant to Appellate Rule
8, a party may apply to the appellate courts for a stay when the
trial court chooses to proceed with the matter. See N.C.R. App. P.
8 (2002).
In the instant case, defendant appealed from the trial court's
order denying defendant's motion to dismiss. Defendant argues that
this order was immediately appealable because it affected a
substantial right. The substantial right at issue was based on the
doctrine of sovereign immunity which, defendant asserted, barred
plaintiff's suit. Defendant contends that, as the order wasimmediately appealable, the trial court had no jurisdiction over
the case once defendant perfected its appeal.
Although this Court eventually held that defendant's appeal
affected a substantial right, and was thus immediately appealable,
such a holding was not a foregone conclusion. The Court noted in
its opinion that the Supreme Court has never specifically
addressed the issue. RPR & Assocs., 139 N.C. App. at 527, 534
S.E.2d at 250. There is moreover substantial authority for the
proposition that, once the State enters into a contract, it waives
its rights to sovereign immunity. See, e.g., N.C. Gen. Stat. §
143-135.3 (2001); Smith v. State, 289 N.C. 303, 320, 222 S.E.2d
412, 423-24 (1976); Stahl-Rider v. State, 48 N.C. App. 380, 384,
269 S.E.2d 217, 219 (1980). As noted supra, the trial court had
the authority to determine whether or not its order was immediately
appealable. See Veazey, 231 N.C. at 364, 57 S.E.2d at 382-83; T &
T Development Co., 125 N.C. App. at 603, 481 S.E.2d at 349. Given
the fact that plaintiff's claim against defendant was based upon a
contract, the trial court's decision that defendant had waived all
claims to sovereign immunity, and that therefore the appeal did not
affect defendant's substantial rights, was a reasonable one. The
reasonableness of the trial court's decision to proceed with trial
is underscored by the fact that both this Court and the Supreme
Court repeatedly rejected defendant's attempts to stay the lower
court proceedings or otherwise remove jurisdiction from the trial
court. Defendant does not contend that the proceeding before the
trial court was otherwise flawed or resulted in prejudice todefendant.
Because the trial court had the authority to determine whether
its order affected defendant's substantial rights or was otherwise
immediately appealable, the trial court did not err in continuing
to exercise jurisdiction over this case after defendant filed its
notice of appeal. The trial court's determination that the order
was nonappealable was reasonable in light of established precedent
and the repeated denials by the appellate courts of this State to
stay proceedings. Although this Court ultimately held that
defendant's appeal affected a substantial right, it also held that
defendant was not immune to suit. Defendant states no grounds, nor
has it produced any evidence to demonstrate how it was prejudiced
by the trial court's exercise of jurisdiction over this case. We
therefore overrule defendant's first assignment of error.
B. Prejudgment and Postjudgment Interest
By its second assignment of error, defendant contends that the
trial court erred when it included prejudgment and postjudgment
interest in the award entered for plaintiff. Citing the well-
established rule that interest is not recoverable against the State
absent express authorization by a statute or contract, see, e.g.,
Faulkenbury v. Teachers' and State Employees' Ret. Sys., 132 N.C.
App. 137, 149, 510 S.E.2d 675, 683, disc. review denied, 350 N.C.
379, 536 S.E.2d 620, cert. denied, 352 N.C. 102, 540 S.E.2d 358
(1999), defendant argues that the award of interest was improper
and must be reversed. On this point, we agree with defendant.
In its award to plaintiff, the trial court ordered that (2) G.S. 143-134.1, which is incorporated in
Article 17 of the general conditions of this
contract governs the issue of interest.
Interest accrues at the rate of one percent
(1%) beginning on the 46th day after
substantial completion as to all monies due
and unpaid a contractor. RPR completed its
work on November 16, 1992 and is entitled to
interest on sums awarded by this court to run
from January 1, 1993 until paid. Therefore,
RPR is entitled to prejudgment interest at the
contract and the statutory rate (1% per month)
from January 1, 1993 which has accrued in the
amount of $748,931.37 as of May 1, 2000.
(3) Interest on the principal sum from and
after the date of this judgment at the
contract and statutory rate of 1% per month.
As noted in the trial court's order, the parties agreed in their
contract that payments to subcontractors shall be made in
accordance with the provisions of G.S. 143-134.1 entitled Interest
on final payments due to prime contractors: payments to
subcontractors. Section 143-134.1 of the North Carolina General
Statutes provides in pertinent part that:
On all public construction contracts which are
let by a board or governing body of the State
government or any political subdivision
thereof . . . the balance due prime
contractors shall be paid in full within 45
days after respective prime contracts of the
project have been accepted by the owner,
certified by the architect, engineer or
designer to be completed in accordance with
terms of the plans and specifications, or
occupied by the owner and used for the purpose
for which the project was constructed,
whichever occurs first. Provided, however,
that whenever the architect or consulting
engineer in charge of the project determines
that delay in completion of the project in
accordance with terms of the plans and
specifications is the fault of the contractor,
the project may be occupied and used for the
purposes for which it was constructed without
payment of any interest on amounts withheldpast the 45 day limit. . . . Should final
payment to any prime contractor beyond the
date such contracts have been certified to be
completed by the designer or architect,
accepted by the owner, or occupied by the
owner and used for the purposes for which the
project was constructed, be delayed by more
than 45 days, said prime contractor shall be
paid interest, beginning on the 46th day, at
the rate of one percent (1%) per month or
fraction thereof unless a lower rate is agreed
upon on such unpaid balance as may be due.
N.C. Gen. Stat. § 143-134.1(a) (2001) (emphasis added). Under the
plain terms of section 143-134.1, a prime contractor may recover
interest of one percent on any unpaid balance due under a public
construction contract beginning on the forty-sixth day after such
balance was due.
In the instant case, plaintiff filed suit against defendant
for breach of contract and for breach of warranty. Plaintiff did
not allege, however, nor did the trial court find, that defendant
failed to pay plaintiff the amount due under the contract for
completion of the construction project. Instead, plaintiff
asserted that defendant's conduct rendered performance of the
contract more difficult, resulting in unforeseen extra-contractual
expense and damages to plaintiff. The trial court agreed, finding
and concluding that defendant's breach of contract injured
plaintiff in the amount of $851,058.38 in damages. The trial court
then ordered that plaintiff was entitled to interest on sums
awarded by this court. Such a conclusion was in error.
The case of Davidson and Jones, Inc. v. N.C. Dept. of
Administration, 69 N.C. App. 563, 317 S.E.2d 718 (1984), reversed
in part on other grounds, 315 N.C. 144, 337 S.E.2d 463 (1985), isstrikingly similar to the facts of the instant case and instructive
on the issue of interest awarded against the State on damages for
a breach of contract action. In Davidson, the plaintiff-contractor
entered into a contract with the defendants, the University of
North Carolina at Chapel Hill (UNC-CH) and the North Carolina
Department of Administration, for the construction by plaintiff of
new stacks for books for the Wilson Library on the [UNC-CH]
campus. Id. at 564, 317 S.E.2d at 719. During the course of
construction, the plaintiff incurred unforeseen expenses for rock
excavation and removal. After the plaintiff's request for
additional compensation was rejected by the defendants, the
plaintiff filed claims for equitable adjustment, requesting
'$262,551.00 for the extra costs, duration expenses, inefficiency
and interest costs' allegedly incurred because of the overrun in
rock excavation. Id. at 567, 317 S.E.2d at 721. The trial court
agreed with the plaintiff, concluding that it was 'entitled to
recover from the State as an equitable adjustment under the
Contract.' Id. at 569, 317 S.E.2d at 722. The trial court also
ruled that the plaintiff was entitled to interest on such recovery.
On appeal, this Court held that, although the trial court
correctly awarded damages to the plaintiff for expenses it incurred
as a result of the rock excavation, the plaintiff was not entitled
to interest on such damages. See id. at 574-75, 317 S.E.2d at 725.
In so holding, the Court specifically rejected section 143-134.1 as
a basis for awarding interest. See id. at 575, 317 S.E.2d at 725.
Noting that it was unaware of any statute authorizing the recoveryof any interest against the State on breach of contract on the
facts of this case[,] the Court reversed the award of interest by
the trial court.
As did the Davidson Court, we conclude that on the face of
its textual language[,] section 143-134.1 is inapplicable to the
facts of the instant case. Id. at 575, 317 S.E.2d at 725.
Plaintiff's recovery was based on damages it incurred as a result
of defendant's breaches of contract and of warranty, and not for
any unpaid balance due under the contract. As noted supra, the
State is not required to pay interest on its obligations unless it
is required to do so by contract or by statute. Faulkenbury, 132
N.C. App. at 149, 510 S.E.2d at 683. Because defendant was not
obligated under the contract or section 143-134.1 to pay interest
on damages suffered by plaintiff as a result of defendant's breach
of contract, the trial court erred in awarding prejudgment and
postjudgment interest. We therefore reverse the trial court's
award of interest against defendant and turn to defendant's third
assignment of error.
C. Sufficiency of Evidence
By its final assignment of error, defendant argues that the
trial court erred in awarding excessive damages to plaintiff.
Defendant contends that there was insufficient evidence to support
the award by the trial court. We disagree.
Upon review of judgment by the trial court, we must determine
whether there was competent evidence before the court to support
its findings of fact, and whether those findings of fact, in turn,support its conclusions of law. See Lemmerman v. Williams Oil Co.,
318 N.C. 577, 580-81, 350 S.E.2d 83, 86 (1986). On appeal, the
findings of fact made below are binding on the Court of Appeals if
supported by the evidence, even when there may be evidence to the
contrary. Barnhardt v. City of Kannapolis, 116 N.C. App. 215,
217, 447 S.E.2d 471, 473, disc. review denied, 338 N.C. 514, 452
S.E.2d 807 (1994).
Defendant first contends that there was insufficient evidence
to support the trial court's award of direct costs of $86,214.12
for damages plaintiff incurred under its rock excavation claim.
Defendant asserts that plaintiff submitted a damage claim for rock
excavation totaling only $82,961.62. Our review of the transcript
in this case reveals that defendant's argument is without merit.
James E. Anderson (Anderson), a civil engineer, testified
extensively regarding plaintiff's damages on the rock excavation
claim. Anderson testified that plaintiff suffered damages
amounting to $2,214.03 for additional open rock excavation[,]
$1,038.47 for additional utility trench rock excavation[,] and
$82,961.62 for additional footings trench rock excavation[,] the
total of which is $86,214.12. Thus, the figure of $82,961.62
represented only a portion of plaintiff's claim, rather than the
entire figure as defendant asserted. The trial court's findings
accurately and properly reflect Anderson's testimony. Because
there was substantial evidence to support the trial court's
findings, we conclude that the trial court properly found that
plaintiff's damages for rock excavation totaled $86,214.12. Defendant next argues that the finding by the trial court that
plaintiff suffered damages totaling $138,800.00 due to a delay on
the project of 347 days is unsupported by the evidence. Defendant
asserts that the trial court neglected to deduct from its total of
347 days a time extension of forty-eight days granted to plaintiff
by a series of change orders, as well as a time period of eighty
days previously awarded to plaintiff by the State Office of
Construction. We disagree.
Plaintiff presented extensive evidence at trial on the cause
and effect of construction delay. Mr. William W. Gurry (Gurry),
an expert in the analysis of construction delay and critical path
methodology of construction scheduling, testified in detail
concerning the construction delays caused by defendant. Gurry
testified that, according to his calculations, the project was 391
days late beyond contract completion[,] a figure which include[d]
a 44 day time extension. Thus, contrary to defendant's
assertions, the evidence before the trial court, and the trial
court's findings concerning the delay, took into account the time
extensions granted to plaintiff. Moreover, the trial court
explicitly recognized that the State Office of Construction had
previously awarded plaintiff damages, but found that defendant
refused to pay any portion of that award of the State Office of
Construction. The trial court therefore included these time
extensions in its award. We conclude that the trial court's award
to plaintiff of damages suffered due to delay of the project is
supported by the evidence and does not constitute a double recoveryfor plaintiff. We therefore overrule defendant's final assignment
of error. We now examine the issues presented by plaintiff on
appeal.
II. Plaintiff's Appeal
Plaintiff assigns as error three issues on appeal, arguing
that the trial court erred in failing to award plaintiff damages on
its (1) masonry claim and (2) its excessive punchlist claim.
Plaintiff also asserts that the trial court erred by (3) making no
findings regarding its conclusion that an offset against the
judgment was proper for sums paid to plaintiff in settlement of a
lawsuit against the project architect.
In addressing plaintiff's claims, we note again the proper
standard of review for this Court. Findings of fact made by the
trial court are binding if supported by competent evidence, see
Barnhardt, 116 N.C. App. at 217, 447 S.E.2d at 473, while we review
de novo the trial court's conclusions of law. See Lemmerman, 318
N.C. at 581, 350 S.E.2d at 86.
A. Masonry Claim
Plaintiff asserts that the trial court erred in concluding
that plaintiff had presented insufficient evidence of the specific
damages it incurred in connection with the masonry phase of
construction. In its judgment, the trial court found that
RPR's budget for the masonry work, including
materials and subcontract labor to install the
masonry and appurtenances, was $669,064.00,
which is found to be reasonable. RPR's actual
cost for this work was $1,280,268.00. RPR's
budget amount is found to be reasonable. RPR
has been unable to prove to the court by the
greater weight of the evidence how much ofthis additional masonry expense which was
actually incurred by RPR was due to the
conduct of UNC. Some, but not all of these
additional costs, likely arose out of
estimating errors. Although it is clear on
this masonry claim that RPR suffered damages
through owner caused inefficiencies, the
amount of such actual damages has not been
proven with the degree of specificity required
by law. Therefore, the court rules that the
Plaintiff cannot receive any monetary recovery
for this claim.
Plaintiff argues that the trial court's failure to award damages on
its masonry claim arises from the trial court's misapprehension of
the law concerning speculative damages. Plaintiff correctly notes
that, 'where the plaintiff can prove the fact of damage, but not
the extent of it, the reasonable certainty rule as it is now
applied in most courts does not require proof of damages with
mathematical precision.' Bolton Corp. v. T.A. Loving Co., 94 N.C.
App. 392, 405, 380 S.E.2d 796, 805 (1989) (quoting Dobbs, Remedies
§ 3.3 (1973)), disc. review denied, 325 N.C. 545, 385 S.E.2d 496
(1989). Plaintiff contends that it produced sufficient evidence to
support an award for damages on the masonry claim, and that the
trial court erred in failing to make such an award. We disagree.
Contrary to plaintiff's assertions, it is clear that the trial
court's denial of its masonry claim was based on plaintiff's
failure to present sufficient evidence as to the cause of the
damages rather than the extent of such damages. As recited above,
the trial court found that
RPR has been unable to prove to the court by
the greater weight of the evidence how much of
this additional masonry expense which was
actually incurred by RPR was due to the
conduct of UNC. Some, but not all of theseadditional costs, likely arose out of
estimating errors.
It is well established that, for breach of an executory
contract, the plaintiff has the burden of presenting sufficient
evidence of damages as can be ascertained and measured with
reasonable certainty. Biemann & Rowell Co. v. Donohoe Cos., 147
N.C. App. 239, 245, 556 S.E.2d 1, 5 (2001). Moreover, where both
parties contribute to the delay, neither can recover damages,
unless there is proof of clear apportionment of the delay and
expense attributable to each party. Id. In the instant case, the
trial court found that plaintiff had failed to sustain its burden
on the issue of apportionment of damages on the masonry claim and
declined to award any monetary damages for such. The trial court's
findings were based on competent evidence, and we conclude that the
trial court did not err in failing to award damages for plaintiff's
masonry claim. See Biemann, 147 N.C. App. at 246, 556 S.E.2d at 6
(holding that the trial court did not err in failing to award the
plaintiff damages for its construction claim where the plaintiff
failed to properly establish responsibility for its additional
costs). We therefore overrule this assignment of error.
B. Excessive Punchlist Claim
Plaintiff further assigns error to the trial court's failure
to award plaintiff damages for the direct expenses it incurred on
its excessive punchlist claim. After reviewing the evidence
connected with this claim, the trial court found that [a]s a
direct and proximate result of the unreasonable means and methods
employed by UNC in performing pre-final and final inspections andof the imposition of excessively high standards on RPR's finished
work, RPR incurred . . . additional costs[.] Although the trial
court awarded plaintiff damages for costs it incurred in connection
with additional labor by subcontractors, the trial court made no
findings and no award based on plaintiff's direct costs, for which
plaintiff submitted substantial evidence. Plaintiff argues that
the trial court's failure to make findings regarding the direct
costs constitutes error. We agree.
In all actions tried upon the facts without a jury . . . the
court shall find the facts specially and state separately its
conclusions of law thereon . . . . N.C. Gen. Stat. § 1A-1, Rule
52(a)(1) (2001). Our Supreme Court has noted that
while Rule 52(a) does not require a recitation
of the evidentiary and subsidiary facts
required to prove the ultimate facts, it does
require specific findings of the ultimate
facts established by the evidence, admissions
and stipulations which are determinative of
the questions involved in the action and
essential to support the conclusions of law
reached.
Quick v. Quick, 305 N.C. 446, 452, 290 S.E.2d 653, 658 (1982)
(alteration in original). Such specific findings are necessary for
appropriate appellate review. See Mann Contr'rs, Inc. v. Flair
With Goldsmith Consultants-II, Inc., 135 N.C. App. 772, 775, 522
S.E.2d 118, 121 (1999)(holding that the trial court's award of
damages was not supported by the findings).
In the instant case, plaintiff submitted substantial evidence
of the direct costs it incurred as a result of defendant's
unreasonable behavior in its inspection of plaintiff's work. Specifically, plaintiff produced evidence of costs totaling
$38,221.00 in clean up expense[;] $273,334.00 in additional
payroll expense; and $264.00 in travel expenses. Further,
Anderson testified at trial that plaintiff incurred $311,000.00 in
direct costs as a result of defendant's behavior in connection
with this claim. Although the trial court found that, [a]s a
result of the unreasonable and excessive punchlist process, RPR was
required to expend an extraordinary sum of money for punchlist work
above and beyond that reasonably anticipated and included in RPR's
bid and awarded costs related to subcontractor expenses, the trial
court made no findings in connection with the direct costs expended
by plaintiff. As a result, we are unable to determine whether or
not the trial court properly considered the evidence of
plaintiff's direct costs. We therefore remand the case for
additional findings of fact regarding this evidence. We now
examine plaintiff's final assignment of error.
C. Offset
By its final assignment of error, plaintiff argues that the
trial court erred in allowing an offset against monies plaintiff
received from a settlement of claims against the architect on the
project. In its judgment, the trial court ordered that
UNC shall receive a credit to be applied to
this judgment for monies received by Plaintiff
resulting from the settlement of similar
claims made by RPR in a separate lawsuit
against the Architect, O'Brien/Atkins
Associates, P.A. in the amount of $200,000.00,
plus interest at one percent per month (1%)
running from the date of such settlement
payment to RPR.
Plaintiff contends that the trial court erred in ordering the
credit without making findings of fact and conclusions of law
regarding the necessity of this offset. We disagree.
In a breach of contract action, a defendant is entitled to
produce evidence of payment of compensation by a third party to a
plaintiff for damages resulting from a similar claim regarding the
same subject matter.
See Markham v. Nationwide Mut. Fire Ins. Co.,
125 N.C. App. 443, 455, 481 S.E.2d 349, 357,
disc. review denied,
346 N.C. 281, 487 S.E.2d 551 (1997).
Simply put, although plaintiff is entitled to
full recovery for its damages, plaintiff is
nevertheless not entitled to double recovery
for the same loss or injury. As stated by our
Supreme Court, any amount paid by anybody . .
. for and on account of any injury or damage
should be held for a credit on the total
recovery . . . .
Id. (quoting
Holland v. Utilities Co., 208 N.C. 289, 292, 180 S.E.
592, 593-94 (1935)) (citations omitted).
In the case at bar, plaintiff asserted that it incurred
expenses as a result of delay of the project caused by the State
of North Carolina through its agent architect. Plaintiff conceded
that it had sued the architect over such delay and had settled its
case for the amount of $200,000.00. Thus, in bringing the present
breach of contract action, plaintiff sought compensation for
injuries for which it had already in part received some monies. In
its judgment, the trial court found that plaintiff was entitled to
expenses it incurred as a result of the project delay. It is clear
that defendant was entitled to a reduction of damages for monies
plaintiff received for identical injuries resulting from anidentical delay.
See Ryals v. Hall-Lane Moving and Storage Co.,
122 N.C. App. 134, 141-42, 468 S.E.2d 69, 74-75 (1996). Because
the facts regarding the settlement were not in dispute, and because
defendant was entitled to the credit as a matter of law, the trial
court was not required to make findings regarding the offset. We
therefore overrule plaintiff's final assignment of error.
In conclusion, we hold that the trial court did not err by
continuing to exercise jurisdiction over this case after defendant
perfected its appeal. We further hold that the trial court erred
when it awarded prejudgment and postjudgment interest against
defendant, and by neglecting to make findings of fact concerning
the evidence of direct costs plaintiff incurred in connection with
its excessive punchlist claim. We otherwise affirm the judgment
of the trial court.
The judgment of the trial court is hereby
Affirmed in part, reversed in part, and remanded.
Judges GREENE and HUNTER concur.
*** Converted from WordPerfect ***