Link to original WordPerfect file
How to access the above link?
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the
print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
TOWN OF WALLACE, Petitioner v. NORTH CAROLINA DEPARTMENT OF
ENVIRONMENT AND NATURAL RESOURCES, DIVISION OF WATER QUALITY,
Respondent
NO. COA02-1119
Filed: 19 August 2003
1. Administrative Law; Environmental Law_review of agency final decision_whole
record test
There was substantial evidence in the record to support the Environmental Management
Commission's findings and conclusions that a town permitted or caused a break to occur in its
sewer line by not inspecting or maintaining the line properly. The trial court improperly applied
the whole record test by weighing the evidence and substituting its own evaluation for the
agency's.
2. Administrative Law_superior court review of agency decision_burden of proof
The trial court did not erroneously place the burden of proof on the agency in reviewing
an agency decision in a sewer discharge case by finding that there was an absence of competent
evidence that petitioner caused or permitted the discharge and by concluding that respondent
failed to present substantial credible evidence that petitioner caused or permitted the break in the
sewer line. The court's judgment does not relieve petitioner of its burden of pleading sufficient
facts to demonstrate respondent's actions violated State law under N.C.G.S. § 150B-23(a).
3. Injunction; Environmental Law_remedy at law_sufficient
The trial court erred by permanently restraining and enjoining respondent from imposing
a civil penalty upon or investigating petitioner for water quality violations. There was a complete
and adequate remedy at law under N.C.G.S. Ch. 150B, Article 4.
Appeal by respondent from judgment entered 11 March 2002 by
Judge Gary E. Trawick in Duplin County Superior Court. Heard in
the Court of Appeals 14 May 2003.
Burrows & Hall, by Richard L. Burrows, for petitioner-
appellee.
Attorney General Roy Cooper, by Special Deputy Attorney
General Francis W. Crawley and Assistant Attorney General
Anita LeVeaux, for respondent-appellant.
STEELMAN, Judge.
The Town of Wallace (petitioner or Wallace) operates a
wastewater treatment plant under a national pollutant dischargeelimination system (NPDES) permit issued by the North Carolina
Department of Environment and Natural Resources (DENR) and the
Division of Water Quality (DWQ). One of the main trunk lines
into the plant runs along Little Rockfish Creek in Wallace.
On 16 June 1999, plant operator Doug Mears (Mears) arrived
at 7:00 a.m. to discover that little or no sewage was flowing into
the treatment plant. Mears informed Paul Parker (Parker),
Director of Public Works in Wallace, of the problem around 7:30
a.m. He also telephoned the DWQ office in Wilmington, North
Carolina, where he left a message that the treatment plant was not
receiving flow and that petitioner was investigating the problem to
determine the cause.
About 8:30 a.m. on 16 June 1999, DWQ environmental chemist
George Colby (Colby) received Mears' message and telephoned
Mears, who again stated that the plant was not receiving any flow
of sewage. At 12:30 p.m., Colby telephoned Parker who informed him
that a broken pipe had been discovered on the main trunk line
running along Little Rockfish Creek. This pipe was 18 inches in
diameter, was one and one-half to two inches thick and was
constructed of reinforced concrete.
Colby arrived at the site of the break at approximately 1:15
p.m. and observed that Wallace employees had removed the section of
the pipe where the break had occurred. He estimated the break
caused one million gallons of untreated sewage to spill into Little
Rockfish Creek. Colby sampled the waters of the creek near the
sewage entry point, upstream and downstream on 16 June 1999 and for
several subsequent days. During a discussion about the break and subsequent spill,
Parker told Colby that the trees and bushes surrounding the section
of broken pipe had been cut for right-of-way maintenance three to
four years prior to June 1999. However, petitioner had not
inspected the interior of the pipes in that section by TVing them
with a special camera or any other method before the break
occurred.
On 17 June 1999, Parker filed an initial written report in
which he stated the break and sewage spill were caused by
[d]ecayed tree stump roots [that] grew into pipe joints and...high
rainfall.... This report also stated that tree stumps were
removed from the area surrounding the broken pipe and that a
temporary, sleeved channel was constructed with steel and plywood
until a new section of pipe could be installed.
Parker later testified that during the excavation of the
broken pipe, he observed a small, decayed tree stump on the ground
above the break. He further testified that none of the roots had
intruded any section of the pipe and that an inspection of the
adjacent pipe sections revealed no roots growing into the pipe or
other defects.
Petitioner had been under a Special Order of Consent (SOC)
with DENR to investigate and repair sections of its sewage
collection system identified by engineers as needing repairs.
However, the section of pipe which broke and caused the spill was
not part of the SOC.
A laboratory analysis of the water samples collected by Colby
showed violations of the State water quality standards fordissolved oxygen levels and fecal coliform bacteria. DWQ Director
Kerr T. Stevens (Stevens) investigated the incident and issued a
decision assessing petitioner a $4,000.00 civil penalty for its
violations of N.C. Gen. Stat. § 143-215.1(a)(6) (2001) plus
investigation costs of $530.82.
On 13 March 2000, Wallace filed a contested case petition
pursuant to N.C. Gen. Stat. § 150B-23 (2001) to challenge DWQ's
assessment. After an administrative hearing, the administrative
law judge (ALJ) issued a recommended decision finding that the
civil penalties had been assessed improperly. On 26 April 2001,
the Environmental Management Commission (EMC) issued the final
agency decision in which it rejected the ALJ's recommendation but
reduced the civil penalty to $2,000.00 plus investigation costs of
$530.82.
Wallace petitioned for judicial review on 10 May 2001, seeking
to have the EMC's final agency decision declared null and void. On
11 March 2002, the trial court filed its judgment reversing the
EMC's final agency decision and permanently restraining and
enjoining DENR from imposing any civil penalty or costs on
petitioner. Respondent appeals the trial court's reversal of the
EMC decision.
I.
[1] Respondent contends the trial court erred in reversing the
EMC's final agency decision. Specifically, it argues the trial
court erred in concluding there was insufficient credible evidence
that petitioner caused or permitted the break in the sewer line to
occur by failing to maintain or inspect it properly. Our review of the trial court's reversal of a final agency
decision involves two inquiries: (1) whether the trial court
exercised the appropriate standard of review; and (2) whether the
trial court properly applied the standard of review. Kea v. Dep't
of Health and Human Servs., 153 N.C. App. 595, 570 S.E.2d 919
(2002), appeal dismissed, 356 N.C. 673, 577 S.E.2d 120 (2003).
This Court's scope of review is the same as that employed by the
trial court. Wallace v. Bd. of Trs., 145 N.C. App. 264, 550 S.E.2d
552, disc. review denied, 354 N.C. 580, 559 S.E.2d 553 (2001).
The trial court may reverse or modify an agency's final
decision or adopt the ALJ's decision
if the substantial rights of the petitioners
may have been prejudiced because the agency's
findings, inferences, conclusions, or
decisions are:
(1) In violation of constitutional provisions;
(2) In excess of the statutory authority or
jurisdiction of the agency;
(3) Made upon unlawful procedure;
(4) Affected by other error of law;
(5) Unsupported by substantial evidence
admissible under G.S. 150B-29(a), 150B-30, or
150B-31 in view of the entire record as
submitted; or
(6) Arbitrary, capricious, or an abuse of
discretion.
N.C. Gen. Stat. § 150B-51(b). Alleged errors of law, including
questions of statutory interpretation by the agency, are reviewed
de novo by the trial court. Friends of Hatteras Island Nat'l
Historic Maritime Forest Land Trust for Preservation v. Coastal
Resources Comm'n, 117 N.C. App. 556, 452 S.E.2d 337 (1995). Wherean allegation is made that a final agency decision is not supported
by competent evidence or is arbitrary and capricious, the trial
court must review the decision under the whole record test. Walker
v. North Carolina Dep't of Human Resources, 100 N.C. App. 498, 397
S.E.2d 350 (1990), cert. denied, 328 N.C. 98, 402 S.E.2d 430
(1991).
In this case, the petition for judicial review of the EMC's
final agency decision alleged that its findings and conclusions
were unsupported by substantial competent evidence. The EMC's
decision contained the following pertinent findings of fact:
6. ...Upon uncovering the section of sewer
collection line in question, the Town [of
Wallace] discovered that the bell (joint)
portion of one section of pipe had broken off
at the bottom. An old tree stump with roots
was removed by the Town in uncovering the
section of broken pipe. According to the
Town, the pipeline break was the result of
decayed tree stump roots which grew into pipe
joints and along with the high rainfall (5
in.) creek water caused a break in the pipe.
14. The Town of Wallace had never inspected
or performed maintenance to the
interior of
the main collection line where the break
occurred[,] but it had recently performed
inspections and maintenance of other sewer
collection lines in the Town's collection
system as mandated by DWQ in a Special Order
of Consent, (SOC).
15. The Town of Wallace did not possess a
valid permit for the discharge of waste water
to the creek that resulted from the broken
pipe.
(emphasis added). The EMC then concluded:
8. The Town of Wallace permitted the
discharge, spillage and leakage of
approximately 1.0 million gallons of municipal
sewage into Little Rockfish Creek on 16 June1999 as a result of its failure to perform any
inspection or maintenance of the pipes in the
affected portion of the sewer collection line
where the rupture or break occurred.
When reviewing the agency's decision to determine whether
there was substantial evidence to support the findings and
conclusions, the trial court must employ the whole record test and
examine all evidence presented to the agency. N.C. Gen. Stat. §
150B-51(b)(5). The trial court's order recites that it conducted
both a
de novo review as well as a whole record test of the final
decision. Thus, we conclude the trial court exercised the proper
standard of review on the question of substantial competent
evidence to support the EMC's findings and conclusions.
See Kea,
supra, 153 N.C. App. at 603, 570 S.E.2d at 924. We now must
determine whether it properly applied the whole record test.
The whole record test requires the trial court to examine all
evidence before the agency and to determine whether the decision
has a rational basis in the evidence.
In re Rogers, 297 N.C. 48,
253 S.E.2d 912 (1979). If the trial court concludes that there is
substantial competent evidence in the record to support the
findings, the agency decision must stand.
Little v. North Carolina
State Bd. of Dental Examiners, 64 N.C. App. 67, 306 S.E.2d 534
(1983). 'Substantial evidence is such relevant evidence as a
reasonable mind might accept as adequate to support a conclusion.'
It is more than a scintilla or a permissible inference.
Lackey v.
North Carolina Dep't of Human Resources, 306 N.C. 231, 238, 293
S.E.2d 171, 176 (1982) (citations omitted). The trial court may
not weigh the evidence presented to the agency or substitute its
own judgment for that of the agency.
King v. North Carolina Envtl.Management Comm'n, 112 N.C. App. 813, 436 S.E.2d 865 (1993).
(See footnote 1)
The trial court found that there was no competent evidence of
record to support the EMC's conclusion that the break occurred
because petitioner failed to maintain or inspect the sewer lines
properly. It then concluded that [t]he Respondent has failed to
present substantial credible evidence that the Petitioner either
caused or permitted the break in the sewer line to occur, by either
failing to properly or reasonably maintain or inspect the sewer
line in question.
We first note that the trial court made independent findings
of fact in its order. However, findings contained in the final
agency decision which are not objected to by the petitioner are
binding on the trial court.
Walker,
supra. Since petitioner
objected only to finding of fact 14, all of the EMC's other
findings were binding, and the trial court did not have the
discretion to make its own findings of fact.
Further, after reviewing the record before us, we conclude
there was substantial competent evidence to support the agency's
findings and conclusions that petitioner permitted the break to
occur by failing to properly inspect or maintain the pipe. The
initial report submitted by Parker identified the cause of the
break in the pipe as decayed tree stump roots. Testimony fromColby indicated petitioner had not inspected the pipe's interior
and that it had performed maintenance right-of-way around the pipe
to clear away trees and bushes three to four years prior to the
break. The assessment by DWQ Director Kerr T. Stevens stated that
[t]he violations are not considered willful or intentional but
were due to inadequate maintenance. Field samples taken by Colby
established violations of water quality standards in Little
Rockfish Creek following the spill. The foregoing provided the EMC
with substantial competent evidence upon which it based its final
agency decision.
Petitioner presented contrary evidence regarding the cause of
the break and the necessity of inspecting the interior of the pipes
primarily through Parker's testimony. This testimony conflicted
with the initial information provided in Parker's report to
respondent. Conflicts in testimony and witness credibility are
issues to be determined by the agency, not the reviewing court.
Yates Constr. Co. v. Commissioner of Labor, 126 N.C. App. 147, 484
S.E.2d 430 (1997). 'The whole record test does not allow the
reviewing court to replace the [agency's] judgment as between two
reasonably conflicting views, even though the court could
justifiably have reached a different result had the matter been
before it
de novo[.]'
Wilkie v. North Carolina Wildlife Resources
Comm'n, 118 N.C. App. 475, 483, 455 S.E.2d 871, 876 (1995)
(citation omitted). Thus, the trial court improperly weighed the
evidence and substituted its own evaluation for the EMC's.
We hold the trial court incorrectly applied the standard of
review required under N.C. Gen. Stat. § 150B-51(b) and erred inconcluding that the EMC's findings and conclusions were not
supported by substantial competent evidence of record.
II.
[2] Respondent next argues the trial court erred in placing
the burden of proof on DENR to show that petitioner caused the
sewage discharge. Respondent particularly assigns as error (1) the
trial court's finding that there was an absence of any competent
evidence that the Petitioner either caused or permitted the waste
to go into the stream; and (2) its conclusion that respondent
failed to present substantial credible evidence that the
Petitioner either caused or permitted the break in the sewer line
to occur, by either failing to properly or reasonably maintain or
inspect the sewer line in question. As a result, respondent
contends the trial court erroneously placed the burden of proof
upon it, rather than petitioner.
In a contested case filed pursuant to N.C. Gen. Stat. Chapter
150B, the petitioner must state facts tending to establish that
the agency named as the respondent has...substantially prejudiced
the petitioner's rights and that the agency:...(2) Acted
erroneously;...(4) Acted arbitrarily or capriciously; or (5) Failed
to act as required by law or rule. N.C. Gen. Stat. § 150B-23(a).
The party having the burden of proof must establish the required
facts by a preponderance of the evidence. N.C. Gen. Stat. § 150B-
29(a). Chapter 150B, Article 3 is otherwise silent as to the
burden of proof in demonstrating error by the agency. Similarly,
N.C. Gen. Stat. § 143-215.1 does not specify which party bears the
burden of proving an alleged violation of subsection (a)(6) forcausing or permitting waste to be discharged into State waters
without a permit.
The trial court's judgment does not relieve petitioner of its
burden of pleading sufficient facts to demonstrate respondent's
actions violated State law under N.C. Gen. Stat. § 150B-23(a).
Thus, we disagree with respondent's argument that the trial court's
finding of fact and conclusion of law at issue in this assignment
of error erroneously placed the burden of proof on respondent. The
conclusion that respondent failed to present substantial credible
evidence that petitioner caused or permitted the discharge by
improper maintenance or inspection has been addressed in Part I of
this opinion.
III.
[3] Finally, respondent contends the trial court erred in
permanently restraining and enjoining respondent from imposing any
civil penalty or investigative costs on petitioner.
Generally, the trial court may not impose an equitable remedy
when there is an adequate and complete remedy at law.
Embree
Constr. Group, Inc. v. Rafcor, Inc., 330 N.C. 487, 411 S.E.2d 916
(1992). A party to a contested case may appeal a final agency
decision through the procedures set forth in N.C. Gen. Stat.
Chapter 150B, Article 4. This section governs the scope of the
trial court's review and the actions it may take. None of the
statues in this section authorize a trial court to enjoin an agency
from executing its statutory duties.
We conclude that N.C. Gen. Stat. Chapter 150B, Article 4
provides petitioner a complete and adequate remedy at law and,therefore, hold the trial court erred in permanently restraining
and enjoining respondent from imposing a civil penalty upon or
investigating petitioner for water quality violations.
Because we reverse the trial court's decision on the grounds
that it improperly applied the standard of review in determining
whether substantial competent evidence supported the EMC's findings
and conclusions that petitioner permitted the break by failing to
properly inspect or maintain the sewer line, we do not address
respondent's remaining assignments of error. We remand this matter
to the trial court for entry of judgment consistent with this
decision.
Reversed and remanded.
Judges TIMMONS-GOODSON and HUDSON concur.
Footnote: 1 Subsection (c) of N.C. Gen. Stat. § 150B-51 requires the
reviewing court to engage in a
de novo review of a final agency
decision where the agency did not adopt the ALJ recommendation.
This subsection was enacted in 2000 and is applicable to
contested cases commenced on or after 1 January 2001. Because
the contested case petition in the instant case was filed on 13
March 2000, the standard of review articulated in subsection (c)
does not apply.
*** Converted from WordPerfect ***