Link to original WordPerfect file
How to access the above link?
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the
print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
WATSON ELECTRICAL CONSTRUCTION CO., Plaintiff, v. SUMMIT
COMPANIES, LLC, JAMES L. HODGIN; and NANCY T. HODGIN, Defendants
NO. COA02-1366
Filed: 21 October 2003
1. Construction Claims_by subcontractor against owners_breach of contract
The trial court did not err by granting summary judgment for property owners (the
Hodgins) on a subcontractor's breach of contract claim. Plaintiff-subcontractor did not claim that
it had a direct contract with the Hodgins, and did not produce evidence that the Hodgins ratified
the contract between plaintiff and the general contractor.
2. Liens_by subcontractor against property owners_claims of general contractor
dismissed_no funds available
Summary judgment was properly granted for the property owners on a subcontractor's
lien claims against the property owners. The lien on real property was properly dismissed
because an arbitrator had determined that the general contractor (Summit) had breached the
contract and dismissed its lien, and the subcontractor is bound by any defense available against
the contractor. The lien on funds owed to the general contractor was properly dismissed because
the arbitrator determined that, after a set-off, the general contractor was indebted to the property
owners.
3. Construction Claims_quantum meruit_summary judgment
Summary judgment was correctly granted for property owners on a quantum meruit claim
by a subcontractor where the owners made monthly payments to the general contractor until the
general contractor abandoned the project.
4. Construction Claims_oral guaranty_main purpose rule_issue of fact
There was a genuine issue of fact as whether an oral guaranty was given to a
subcontractor by the property owners and whether application of the main purpose rule was
warranted in a construction case in which the general contractor had abandoned the project.
5. Construction Claims_by subcontractor against property owners_third-party
beneficiary
The trial court correctly granted summary judgment for property owners on a
subcontractor's claim for damages as a third-party beneficiary. Even assuming that the property
owners (the Hodgins) agreed to pay the general contractor an amount for the subcontractors,
there was no new consideration to the property owners. Moreover, an arbitration proceeding
resulted in an award in full settlement of all claims.
6. Construction Claims_by subcontractor against property owners_false
representation
Summary judgment was correctly granted for the property owners (the Hodgins) on a
claim for false representation by a subcontractor seeking payment under an alleged guarantee by
the property owners. The evidence indicates that the Hodgins paid the general contractor in a
timely fashion and issued two party checks to resolve subcontractor's liens, as promised.
7. Construction Claims_by subcontractor against property owners_unfair trade
practice
Summary judgment was properly granted for property owners on an unfair and deceptive
trade practice claim by a subcontractor. The claim was based on allegedly fraudulent conduct, but
summary judgment was properly granted for the property owners on a fraud claim, and plaintiff
did not show substantial aggravating circumstances in any breach of contract.
Appeal by plaintiff from order entered 14 June 2002 by Judge
Wade Barber, Superior Court, Orange County. Heard in the Court of
Appeals 19 August 2003.
Stark Law Group, by Thomas H. Stark, for plaintiff.
Burns, Day & Presnell, P.A., by Daniel C. Higgins and Daniel
T. Tower, for defendants James L. Hodgin and Nancy T. Hodgin.
WYNN, Judge.
Under
Mace v. Bryant Construction Corporation, 48 N.C. App.
297, 303, 269 S.E.2d 191, 194-95 (1980), this Court held, because
the subcontractor is entitled to a lien under G.S. 44A-23 only by
way of subrogation, his lien rights are dependent upon the lien
rights of the general contractor. In this case, because the the
general contractor did not have any lien rights against the owner,
the first-tier subcontractor, likewise, had no rights. However, we
hold that the evidence creates an issue of fact as to whether the
owners gave the subcontractor an oral guaranty, and if so, whether
the main purpose rule should be applied in this case.
Accordingly, we affirm in part and reverse in part the trial
court's grant of summary judgment.
The underlying facts tend to show that the owners, James andNancy T. Hodgins, contracted with Summit Companies, LLC
(See footnote 1)
to serve
as the general contractor in the construction of the Rockhaven
Dialysis Center in Orange County, North Carolina. In September
1999, Summit hired Watson Electrical Construction Company to
replace Port Beacon Electric, the original electrical
subcontractor. On 1 December 1999, the Hodgins made their last
payment to Summit; in return, Summit waived its lien rights for all
labor and materials furnished through 30 November 1999.
In the meantime, after not receiving payment for work
performed, Watson Electrical ceased work on the site on 30 November
1999. On 19 January 2000, Watson Electrical filed a Claim of Lien
and Lien of Funds for $100,932.10 and initiated an action to
perfect the lien on 21 January 2000.
In February 2000, the Hodgins declared Summit in default,
terminated Summit as the general contractor on the project, and
contracted with another general contractor to complete the project.
On 1 March 2000, Summit filed a claim of lien on the project for
$495,617.60, and thereafter, filed a complaint against the Hodgins
on 8 August 2000. Pursuant to their contract, the parties
submitted their disagreement to arbitration which resulted in (1)
a determination that since the Hodgins owed Summit $294,000 and
Summit owed the Hodgins $575,000, Summit should pay $281,000 to the
Hodgins; (2) the dismissal of Summit's claim of lien with
prejudice; and (3) a determination that the award was in full
settlement of all claims and counterclaims submitted toarbitration. After the arbitration award in the Summit litigation,
the trial court for the subject litigation entered summary judgment
favoring the Hodgins. Watson Electrical appealed from the summary
judgment.
(See footnote 2)
______________________________________________________
[1] Upon reviewing this appeal by Watson Electrical, we
summarily reject its first argument that the trial court erred by
granting summary judgment on its claim for breach of contract
because Watson Electrical neither claimed that it had a direct
contract with the Hodgins nor produced evidence tending to show
that the Hodgins ratified the contract between Summit and Watson.
See Simmons v. Morton, 1 N.C. App. 308, 310, 161 S.E.2d 222, 223
(1968). Accordingly, we uphold the trial court's grant of summary
judgment on Watson Electrical's breach of contract claim.
[2] Next, Watson Electrical argues that the trial court erred
by granting summary judgment against its claims for enforcement of
lien and a lien on funds. Regarding the claim for enforcement oflien, this Court has long recognized that a lien in favor of a
subcontractor may arise either directly under G. S. 44A-18 and G.S.
44A-20 or by subrogation under G. S. 44A-23" Con Co. v. Wilson
Acres Apartments, Ltd., 56 N.C. App. 661, 664, 289 S.E.2d 633, 635
(1982). Under Chapter 44, Watson Electrical filed and served a
Lien and Notice of Claim of Lien by First-Tier Subcontractor on the
Hodgins' real property on 19 January 2000 and filed suit to perfect
the lien on 31 January 2000. G. S. 44A-23 provides in pertinent
part as follows:
A first tier subcontractor, who gives notice
as provided in this Article, may, to the
extent of his claim, enforce the lien of the
contractor created by Part 1 of Article 2 of
this Chapter. . . . Upon the filing of the
notice and claim of lien and the commencement
of the action, no action of the contractor
shall be effective to prejudice the rights of
the subcontractor without his written consent.
This statute grants to a first tier subcontractor a lien upon real
property based upon a right of subrogation to the direct lien of
the general contractor on the improved real property as provided in
G. S. 44A-8. Because the subcontractor is entitled to a lien under
G.S. 44A-23 only by way of subrogation, his lien rights are
dependent upon the lien rights of the general contractor. Thus, if
the general contractor has no right to a lien, the first tier
subcontractor likewise has no such right. Mace v. Bryant
Construction Corp., 48 N.C. App. 297, 303, 269 S.E.2d 191, 194-95
(1980). The subcontractor is bound by any defenses available
against the contractor. Con Co. v. Wilson Acres Apartments, Ltd.,
56 N.C. App. 661, 664, 289 S.E.2d 633, 635 (1982). Moreover, the
subcontractor . . . [can] acquire no better right by subrogationthan that of the principal. . . . They may assert only the lien
rights which the general contractor has in the project. The
general contractor can enforce the lien only for the amount due on
the contract, and therefore, [the subcontractor is] similarly
limited. Vulcan Materials Co. v. Fowler Contracting Corp., 111
N.C. App. 919, 921-22, 433 S.E.2d 462, 464 (1993).
In this case, after Watson Electrical filed its action to
enforce its claim of lien, Summit filed a claim of lien against the
real property and sought enforcement of its lien. The Hodgins
filed a demand for arbitration and asserted claims against Summit
for breach of contract, breach of warranty, negligence and fraud.
The arbitrator determined that the Hodgins owed Summit $294,000.00
for work performed and materials provided through 16 February 2000,
and Summit owed the Hodgins $575,000.00 for corrected work and
uncompleted work; accordingly, the arbitrator ordered Summit to pay
the Hodgins the sum of $281,000.00. Thus, the arbitrator
ultimately determined that Summit breached the contract, awarded
the Hodgins damages, and dismissed Summit's claim of lien. Since
the subcontractor is bound by any defenses available against the
contractor, see Con Co. v. Wilson Acres Apartments, Ltd., 56 N.C.
App. 661, 664, 289 S.E.2d 633, 635 (1982), we uphold the trial
court's grant of summary judgment in favor of the Hodgins on Watson
Electrical's claim of lien on the real property.
However, a subcontractor's lien on funds does not arise by
subrogation; rather, under G.S. 44A-18(1), a lien in favor of [the
subcontractor can] attach only to funds owed by owner to
contractor. Lewis-Brady Builders Supply, Inc. v. Bedros, 32 N.C.App. 209, 231 S.E.2d 199, 200 (1977). In Mr. Hodgin's supplemental
affidavit in support of his motion for summary judgment, he stated
that the Hodgins had not paid Summit any money in connection with
the project since 1 December 1999. Watson's last day on the
project was 30 November 1999. Moreover, the amount owed by owner
to the contractor at any particular time must be determined in the
light of the existing circumstances and the contract between owner
and contractor. Id. at 212, 231 S.E.2d at 201. Due to Summit's
breach, the Hodgins were entitled to set off any amount [they] may
have owed [Summit] against the damages caused by [Summit's] breach
of contract. Only after these developments could it be determined
what amount, if any, [the Hodgins] owed [Summit]. Id. As stated,
the arbitrator determined that after the set-off, Summit was
indebted to the Hodgins. Accordingly, the trial court properly
granted summary judgment in favor of the Hodgins on Watson
Electrical's lien on funds.
[3] In Watson Electrical's fourth cause of action, it seeks to
recover damages from the Hodgins under the theory of quantum
meruit. Quantum meruit is a measure of recovery for the
reasonable value of services rendered in order to prevent unjust
enrichment. It operates as an equitable remedy based upon a quasi
contract or a contract implied in law. . .. An implied contract is
not based on an actual agreement, and quantum meruit is not an
appropriate remedy when there is an actual agreement between the
parties. Only in the absence of an express agreement of the
parties will courts impose a quasi contract or a contract implied
in law in order to prevent an unjust enrichment. Paul L.Whitfield, P.A. v. Gilchrist, 348 N.C. 39, 42, 497 S.E.2d 412, 414-
15 (1998). Unjust enrichment has been described as:
the result or effect of a failure to make
restitution of, or for, property or benefits
received under such circumstances as to give
rise to a legal or equitable obligation to
account therefor. It is a general principle
underlying various legal doctrines and
remedies, that one person should not be
permitted unjustly to enrich himself [or
herself] at the expense of another.
Furthermore, the mere fact that one party was enriched, even at the
expense of the other, does not bring the doctrine of unjust
enrichment into play. There must be some added ingredients to
invoke the unjust enrichment doctrine. Peace River Electric
Cooperative, Inc. v. Ward Transformer Company, Inc., 116 N.C. App.
493, 509, 449 S.E.2d 202, 213 (1994); see also Collins v. Davis, 68
N.C. App. 588, 591, 315 S.E.2d 759, 761 (1984)(stating recovery
under quantum meruit based upon contract implied-in-law is only
proper in circumstances such that it would be unfair for the
recipient to retain the benefit of the claimant's services).
In this case, the Hodgins contracted with Summit for the
construction of a dialysis center for $1,000,000. Until Summit
abandoned the project, the Hodgins paid Summit in monthly progress
payments. Even though the Hodgins were enriched by the work
performed by Watson Electrical, based upon these facts, a genuine
issue of material fact does not exist as to whether any such
enrichment was unjust because the Hodgins made regular payments to
Summit. Accordingly, we uphold the trial court's grant of summary
judgment on this claim.
[4] In its fifth cause of action, Watson Electrical allegesthe Hodgins, as guarantors of payment, are liable to Watson
Electrical for sums due under the contract and their failure to pay
constitutes a breach of the guaranty of payment. In the Hodgins'
forecast of evidence in support of summary judgment, Mr. Hodgin
denies agreeing to guarantee payment in his affidavit. However, in
opposition to defendants' motion for summary judgment, Watson
Electrical presented the deposition testimony of Dennis Cole,
Watson Electrical's field supervisor, and Keith Clifford, a Watson
Electrical project manager. Mr. Cole and Mr. Clifford stated that
during their work site visit on 21 September 1999, they had a
conversation with Mr. Hodgin in which Mr. Hodgin assured them
Watson Electrical would be paid and that Mr. Hodgin would issue a
two-party check if necessary. Ikey Huffman, Watson's Burlington
Division Manager, stated that Mr. Cole and Mr. Clifford relayed
that assurance to him upon their return from the work site.
However, Watson Electrical neither obtained nor received a signed
writing from the Hodgins guaranteeing payment.
A suretyship promise must be in writing. Under the North
Carolina Statute of Frauds,
No action shall be brought . . . to charge any
defendant upon a special promise to answer the
debt, default or miscarriage of another
person, unless the agreement upon which such
action shall be brought, or some memorandum or
note thereof, shall be in writing, and signed
by the party charged therewith or some other
person thereunto by him lawfully authorized.
N.C. Gen. Stat. § 22-1 (2001). Thus, pursuant to the Statute of
Frauds, enforcement of the alleged oral guaranty would be barred.
Nevertheless, Watson Electrical contends the oral guaranty is
enforceable pursuant to the main purpose rule. North Carolina haslong recognized the rule that the promise to pay the debt of
another is outside the statute and enforceable if the promise is
supported by an independent and sufficient consideration running to
the promisor. This rule is generally referred to as the 'main
purpose rule' or the 'leading object rule.' McKenzie Supply
Company v. Motel Development Unit 2, Inc., 32 N.C. App. 199, 202-
03, 231 S.E.2d 201, 204 (1977); see also Burlington Industries,
Inc. v. Foil, 284 N.C. 740, 202 S.E.2d 591 (1974) (Generally, if
it is concluded that the promisor had the requisite personal,
immediate, and pecuniary interest in the transaction in which a
third party is the primary obligor, then the promise is said to be
original rather than collateral and therefore need not be in
writing to be binding.).
Watson Electrical contends there is a genuine issue of
material fact as to (1) whether the oral guaranty was given and (2)
whether the main purpose rule is applicable. Watson Electrical
contends that the Rockhaven project was behind schedule and over
budget, the relationship between the owners and the general
contractor was deteriorating and the Hodgins wanted the project
completed without delay. According to Watson Electrical, the
prospect of having another electrical contractor walk off the job
invoked images of further delays and increased costs that induced
Mr. Hodgin to make assurances to Watson Electrical that regardless
of the circumstances, Watson Electrical would be paid. However,
the Hodgins contend that they did not have a personal, immediate,
and pecuniary interest in seeing that Summit hired Watson to do the
electrical work because they had a fixed price contract withSummit to construct the project for an amount not to exceed
$1,000,000. Nonetheless, in Mr. Hodgin's deposition, he stated he
had concerns about Summit's ability to finish the project and that
the delays, additional interest cost and the loss of income was
killing him. Mr. Hodgin further stated that he had several
conversations with Summit about finishing the building because you
know, . . . we had hundreds of thousands of dollars invested in
this thing, plus the interest on our loans. And, yes, there was a
lot of conversation with Adams, not particularly to the electrical,
but the project total. He was under pressure to get the project
done.
Whether a promise is an original one not coming within the
statute of frauds, or a collateral one required by the statute to
be in writing, is to be determined from the circumstances of its
making, the situation of the parties, and the objects to be
accomplished. Where the intent is doubtful, the solution usually
lies in summoning the aid of a jury. . . . However, [if] there is
insufficient evidence as a matter of law to bring the main purpose
rule into play, the case should not be allowed to go to the jury
under the theory of the main purpose rule. Burlington Industries,
284 N.C. 740, 752, 202 S.E.2d 591, 599 (1974). After carefully
reviewing the pleadings, affidavits, and depositions, we find a
genuine issue of material fact exists as to (1) whether an oral
guaranty was given, and (2) whether an application of the main
purpose rule is warranted on the facts of this case. Accordingly,
we find summary judgment was improvidently granted on Watson
Electrical's claim for breach of guaranty. [5] In its sixth cause of action, Watson Electrical contends
it should recover damages because it was a third-party beneficiary
to an alleged February 2000 contract entered into between the
Hodgins and Summit for $250,000. To establish a claim based on
the third party beneficiary contract doctrine, a complaint's
allegations must show: (1) the existence of a contract between two
other persons; (2) that the contract was valid and enforceable; and
(3) that the contract was entered into for his direct, and not
incidental, benefit. LSB Financial Services, Inc. v. Harrison,
144 N.C. App. 542, 548, 548 S.E.2d 574, 578 (2001). Watson
Electrical relies on deposition testimony from Mr. Hodgin and
Thomas Adams, owner of Summit Corporation, which he contends
demonstrates a genuine issue of material fact as to the existence
of a February 2000 contract for the benefit of the subcontractors.
From the evidence presented by both parties, it is clear that an
agreement was never reached between the parties regarding a
$250,000 payment. According to Mr. Hodgin, between 30 November
1999 and 16 February 2000, the date Summit was terminated from the
project, there were discussions between Summit and the Hodgins
regarding change orders and several lien claimants. Mr. Hodgin
stated that Summit threatened to abandon the job if it was not paid
$250,000 within several days. Mr. Hodgin never agreed to pay
$250,000. However, Mr. Adams stated an agreement was reached where
the Hodgins agreed to pay an additional $250,000, that based upon
this agreement, he called several subcontractors and told them
they would receive payment in a few days and that after notifying
the subcontractors, Mr. Hodgin repudiated the deal. Nonetheless,these facts do not create a genuine issue of material fact as to
whether an enforceable contract was entered into by the parties.
An enforceable contract is one supported by consideration.
Moreover, where a contract has been partially performed, as is the
case here, a modification of its terms is treated as any other
contract and must also be supported by consideration. It is well
established that consideration sufficient to support a contract or
a modification of its terms consists of any benefit, right, or
interest bestowed upon the promisor, or any forbearance, detriment,
or loss undertaken by the promisee. Consideration is the glue that
binds parties together, and a mere promise, without more, is
unenforceable. Lee v. Paragon Group Contractors, Inc., 78 N.C.
App. 334, 337, 337 S.E.2d 132, 134 (1985).
In this case, even assuming the Hodgins agreed to pay Summit
$250,000 in order to pay various subcontractors, no new
consideration flowed to the Hodgins. Under the original contract
between Summit and the Hodgins, Summit agreed to construct the
dialysis center for the fixed price of $1,000,000. Any additional
money above the $1,000,000 would constitute a contractual
modification requiring new consideration. Moreover, the record
shows that all claims, including the alleged $250,000 contract,
were determined in the arbitration proceeding. Under that
proceeding, the arbitrator held that the award was in full
settlement of all claims and counterclaims submitted.
Accordingly, we hold the trial court properly granted summary
judgment on this claim.
[6] In its seventh cause of action, Watson Electrical contendsit reasonably relied to its detriment upon Mr. Hodgin's allegedly
false representation that he would guarantee payment to Watson
Electrical and, therefore, the Hodgins should pay damages in the
amount of $100,932.10 plus interest.
To make out a case of actionable fraud, plaintiffs must show:
(a) that defendant made a representation relating to some material
past or existing fact; (b) that the representation was false; (c)
that defendant knew the representation was false when it was made
or made it recklessly without any knowledge of its truth and as a
positive assertion; (d) that defendant made the false
representation with the intention that it should be relied upon by
plaintiff; (e) that plaintiffs reasonably relied upon the
representation and acted upon it; and (f) that plaintiffs suffered
injury. Johnson v. Phoenix Mutual Life Insurance Company, 300
N.C. 247, 253, 266 S.E.2d 610, 615 (1980), overruled on other
grounds by Myers & Chapman, Inc. v. Thomas G. Evans, Inc., 323 N.C.
559, 374 S.E.2d 385 (1988), Boyd v. Drum, 129 N.C. App. 586, 501
S.E.2d 91 (1998), and Symons Corp. v. Insurance Co. of North
America, 94 N.C. App. 541, 380 S.E.2d 550 (1989).
The facts, viewed in the light most favorable to Watson
Electrical, indicate that Watson Electrical's representatives and
Mr. Hodgin had a conversation in the parking lot after Watson
Electrical's work site visit. During this conversation, Mr. Hodgin
allegedly stated Watson Electrical would be paid for their services
and he would issue a two-party check if necessary. After
nonpayment, Watson Electrical contacted Mr. Hodgin and Mr. Hodgin
informed them there was money remaining on the contract. The factsalso indicate Mr. Hodgin issued several two-party checks to
subcontractors in order to resolve claims of lien and that he paid
Summit in a timely fashion which tends to negate any allegation
that Mr. Hodgin made a false statement regarding the issuance of
two party checks. Accordingly, on these facts, a genuine issue of
material fact does not exist regarding whether Mr. Hodgin made a
false statement or misrepresentation about guaranteeing payment.
[7] In its final cause of action, Watson Electrical contends
it is entitled to treble damages because Mr. Hodgin's conduct was
unfair and/or deceptive within the meaning of Chapter 75 of the
North Carolina General Statutes. In its brief, Watson Electrical
indicates Mr. Hodgin's allegedly fraudulent conduct is the conduct
upon which this cause of action is based. As stated, summary
judgment was properly granted on Watson Electrical's fraud claim
and therefore, summary judgment was properly granted on Watson
Electrical's unfair and deceptive trade practices cause of action.
Furthermore, it is well recognized . . . that actions for unfair
or deceptive trade practices are distinct from actions for breach
of contract, and that a mere breach of contract, even if
intentional, is not sufficiently unfair or deceptive to sustain an
action under N.C.G.S. § 75-1.1" Eastover Ridge, L.L.C. v. Metric
Constructors, Inc., 139 N.C. App. 360, 367-68, 533 S.E.2d 827, 832-
33 (2000). Thus, plaintiff must show substantial aggravating
circumstances attending the breach to recover under the Act. Id.
Watson Electrical has not met this showing in this case;
accordingly, summary judgment was properly granted on this issue.
In summation, we hold summary judgment was properly grantedon all causes of action with the exception of the breach of oral
guaranty claim. Accordingly the order below is,
Affirmed in part, reversed in part.
Judges HUDSON and CALABRIA concur.
Footnote: 1 Defendant Summit Companies, L.L.C., is not a party to
this appeal.
Footnote: 2 Summary judgment is appropriate only if the pleadings,
depositions, answers to interrogatories, and admissions on file,
together with the affidavits, if any, show that there is no
genuine issue as to any material fact and that any party is
entitled to judgment as a matter of law.
Martin Architectural
Products v. Meridian Construction, 155 N.C. App. 176, 180, 574
S.E.2d 189, 191 (2002). An issue is material if the facts
alleged would constitute a legal defense, or would affect the
result of the action, or if its resolution would prevent the
party against whom it is resolved from prevailing in the action.
Koontz v. Winston-Salem, 280 N.C. 513, 518, 186 S.E.2d 897, 901
(1972). An issue is genuine if it can be proven by substantial
evidence.
Lowe v. Bradford, 305 N.C. 366, 369, 289 S.E.2d 363,
366 (1982). The movant has the burden of showing that summary
judgment is appropriate. Furthermore, in considering summary
judgment motions, we review the record in the light most
favorable to the nonmovant.
Hayes v. Turner, 98 N.C. App. 451,
456, 391 S.E.2d 513, 516 (1990).
*** Converted from WordPerfect ***