ROBERT W. NUDELMAN
and EMILY S. NUDELMAN,
Plaintiffs,
v
.
Guilford County
No. 00 CvS 6363
J.A. BOOE BUILDING
CONTRACTOR, INC., JAMES
A. BOOE, JR., and MILTON W.
GRENFELL, A.I.A., d/b/a
GRENFELL ARCHITECTURE,
Defendants,
and
J.A. BOOE BUILDING CONTRACTOR,
INC.,
Third-Party Plaintiff,
v.
VEGA INDUSTRIES, INC., d/b/a
CRAFTLINE DISTRIBUTION CENTER;
STO CORP., SCIULLO INTERIOR
SYSTEMS COMPANY, INC.; and
SCAN AM DESIGNS, INC.,
Third-Party Defendants.
Carruthers & Roth, P.A., by Jack B. Bayliss, Jr., for
plaintiff appellants.
Dean & Gibson, L.L.P., by Christopher J. Culp, for James A.
Booe, Jr., defendant appellee.
McCULLOUGH, Judge.
This case arises out of a construction agreement betweenplaintiffs Robert and Emily Nudelman and defendants J.A. Booe
Building Contractor, Inc., and its President, Mr. James A. Booe,
Jr. The pertinent facts are as follows: In 1992, plaintiffs
contracted with architect Milton Grenfell to design and oversee the
construction of a custom built residence for them in Greensboro,
North Carolina. J.A. Booe Building Contractor, Inc. (Booe
Building) successfully bid for the construction job and entered
into a construction contract with plaintiffs on 26 October 1992.
Booe Building's President, Mr. James A. Booe, Jr. (Booe), executed
the construction contract on behalf of Booe Building. Throughout
the construction contract, the contractor was defined as Booe
Building, rather than Booe individually.
As the qualifying agent for Booe Building, Booe completed and
signed a permit application for construction of the house and
submitted it to the City of Greensboro. Booe Building was listed
as both the applicant and the contractor, and Booe Building's
contractor license number also appeared on the permit application.
The City of Greensboro issued a building permit card allowing the
proposed construction, and the permit card was posted on the
building site. However, because the City's computers were not
working when the permit was issued, the permit card was
handwritten. The contractor signature line on the permit card was
never signed; instead, it bore a notation from the City that read
computer down.
After the litigation commenced, Booe realized the permit card
had been issued to him in his individual capacity and in hispersonal contractor code. Booe never signed the permit card and
had no explanation for why the permit was in his name, other than
the fact that the city's computers were not working and perhaps a
clerical error had been made. Despite the confusion in the
issuance of the permit, the construction contract itself clearly
identified Booe Building as the contractor for plaintiffs' house.
When deposed, Mr. Nudelman admitted he never entered into a
contract with Booe individually. All payments required under the
construction contract were made payable to Booe Building, rather
than to Booe individually.
After construction was completed, plaintiffs discovered
problems with the EIFS (exterior insulation and finishing system),
a synthetic stucco product applied and installed on the outside of
the house. Over time, plaintiffs learned their home had elevated
moisture readings, which indicated that the synthetic stucco had
not been properly installed. On 27 April 2000, plaintiffs sued
both Booe Building and Booe individually, as well as their
architect, Mr. Grenfell, for what they believed was a defective
installation of the EIFS. Plaintiffs' complaint asserted that
Booe, in his individual capacity, breached his duty to plaintiffs
and was careless and negligent . . . in conducting and supervising
the construction of plaintiffs' house. On 6 June 2000, Booe
Building and Booe answered plaintiffs' complaint and included a
number of affirmative defenses and a cross-claim against Mr.
Grenfell alleging breach of contract and negligence.
Plaintiffs' case was set for trial at the 5 November 2001Civil Session of Guilford County Superior Court. On 25 October
2001, defendants Booe Building and Booe filed separate motions for
summary judgment. On 29 October 2001, plaintiffs filed a cross-
motion for partial summary judgment on liability as to both
defendants. Before calling the case for trial, the trial court
heard arguments and considered the documents and discovery
submitted on the motions for summary judgment. On 5 November 2001,
the trial court informed the parties that it would grant summary
judgment for Booe. Thereafter, on 13 November 2001, the trial
court entered a written judgment granting Booe's motion for summary
judgment and specifically stated that its judgment was final under
N.C. Gen. Stat. § 1A-1, Rule 54(b) (2001), thus rendering it
subject to appeal and review by this Court. The trial court denied
Booe Building's motion for summary judgment on 21 November 2001.
On the same date, plaintiffs filed a voluntary dismissal without
prejudice as to Booe Building, pursuant to N.C. Gen. Stat. § 1A-1,
Rule 41(a)(1) (2001). Thereafter, on 3 December 2001, plaintiffs
appealed from the trial court's grant of summary judgment for
defendant Booe.
On appeal, plaintiffs argue the trial court erred by (I)
granting summary judgment for Booe in his individual capacity; and
(II) failing to grant their motion for partial summary judgment on
liability as to Booe in his individual capacity. For the reasons
stated herein, we disagree with plaintiffs' arguments and affirm
the judgment of the trial court.
Summary judgment is appropriate if the pleadings,depositions, answers to interrogatories, and admissions on file,
together with the affidavits, if any, show that there is no genuine
issue as to any material fact and that any party is entitled to a
judgment as a matter of law. N.C. Gen. Stat. § 1A-1, Rule 56(c)
(2001). [T]he standard of review on appeal from summary judgment
is whether there is any genuine issue of material fact and whether
the moving party is entitled to a judgment as a matter of law.
Further, the evidence presented by the parties must be viewed in
the light most favorable to the non-movant. Bruce-Terminix Co. v.
Zurich Ins. Co., 130 N.C. App. 729, 733, 504 S.E.2d 574, 577 (1998)
(citation omitted).
Plaintiffs contend summary judgment for defendant Booe was
improper because he did not fulfill his duty to exercise his best
efforts and comply with the North Carolina State Building Code,
N.C. Gen. Stat. § 143-138 (2001). Though they acknowledge that
they entered into a contract with Booe Building (rather than
defendant individually), plaintiffs nonetheless argue defendant was
actively involved in the day-to-day construction of their house and
was therefore responsible for the defective installation of the
EIFS. They further contend the EIFS defects constituted Building
Code violations and note that the [Building] Code imposes
liability on any person who constructs, supervises construction, or
designs a building or alteration thereto, and violates the Code
such that the violation proximately causes injury or damage.
Olympic Products Co. v. Roof Systems, Inc., 88 N.C. App. 315, 329,
363 S.E.2d 367, 375, disc. reviews denied, 321 N.C. 744, 366 S.E.2d862, 863 (1988). Plaintiffs argue a duty of care arose out of the
contract agreement between themselves and Booe Building (and with
defendant, based upon his position with respect to Booe Building),
the theory being that accompanying every contract is a common-law
duty to perform with ordinary care the thing agreed to be done, and
that a negligent performance constitutes a tort as well as a breach
of contract. Pinnix v. Toomey, 242 N.C. 358, 362, 87 S.E.2d 893,
898 (1955). Plaintiffs seek to pierce Booe Building's corporate
veil and hold defendant personally liable for the alleged defects
in their home, and believe their tort claim should have proceeded
to trial.
North Carolina courts will disregard the corporate form or
'pierce the corporate veil,' and extend liability for corporate
obligations beyond the confines of a corporation's separate entity,
whenever necessary to prevent fraud or to achieve equity. Glenn
v. Wagner, 313 N.C. 450, 454, 329 S.E.2d 326, 330 (1985). The
instrumentality rule operates in the following situation:
[When a] corporation is so operated that it is
a mere instrumentality or alter ego of the
sole or dominant shareholder and a shield for
his activities in violation of declared public
policy or statute of the State, the corporate
entity will be disregarded and the corporation
and the shareholder treated as one and the
same person, it being immaterial whether the
sole or dominant shareholder is an individual
or another corporation.
Henderson v. Finance Co., 273 N.C. 253, 260, 160 S.E.2d 39, 44
(1968).
In Statesville Stained Glass v. T.E. Lane Construction &Supply, 110 N.C. App. 592, 430 S.E.2d 437 (1993), the plaintiff
furnished stained glass to defendant Lane Construction Company,
which used the glass in a number of structures it built. Id. at
593, 430 S.E.2d at 438. Upon receiving only a partial payment,
the plaintiff sued Lane Construction Company, Terrence Lane, and
Lane's other construction company for money it was owed and sought
to hold Terrence Lane personally liable for the debt of his
corporation because he was the chief executive officer, sole
shareholder, and controller of the corporation. Id. at 593-94, 430
S.E.2d at 438. At trial, the plaintiff presented evidence that
Lane Construction Company owed it over $15,000.00 and that while
still indebted to plaintiff, defendant Terrence Lane dissolved Lane
Construction Company and organized another construction company.
Id. at 594-95, 430 S.E.2d at 438-39. The Statesville Court made
the following observations about the propriety of piercing the
corporate veil:
[I]n a close corporation, the principal or
sole stockholder [is] permitted by law to play
an active role in management, [and] may deal
with third parties without incurring personal
liability, as long as the separate corporate
identity is maintained. 18 Am. Jur. 2d
Corporations § 45 (1985). In cases arising
out of contracts with a close corporation,
where another party has voluntarily dealt with
the corporation, corporate separateness is
usually respected. 1 F. Hodge O'Neal and
Robert B. Thompson, O'Neal's Close
Corporations § 1.10, at 49 (3d ed. 1992).
This is so because [i]f the other contracting
party has agreed to look to the corporation,
and thus only to the assets that have been
contributed to it, courts understandably are
reluctant to remake the bargain by permitting
the other party to pierce the corporate veiland pursue the shareholders' noncorporate
assets. Id.
Id. at 597, 430 S.E.2d at 440. In ruling that defendant Terrence
Lane was not individually liable to plaintiff, the Statesville
Court stated:
[P]laintiff presented no evidence that Lane
used Lane Construction to conduct personal
business or for personal benefit.
Furthermore, plaintiff's bare assertion that
Lane used Lane Construction to defraud
plaintiff, without supporting evidence, does
not support the court's conclusion that Lane
exercised excessive control on [Lane
Construction], at least partially, in order to
escape liability in violation of plaintiff's
rights. To the contrary, the evidence
presented by plaintiff shows only that Lane
and the other members of the board of
directors agreed to dissolve Lane Construction
due to the financial condition of the
corporation, and that its assets were
liquidated to help pay off company debts. Our
review of the evidence reveals that the trial
court erred in concluding that the corporate
entity of Lane Construction should be
disregarded.
Id. at 598, 430 S.E.2d at 441 (citation omitted).
In the present case, plaintiffs seek to hold defendant
individually liable for the alleged construction defects in their
home, even though defendant, individually, was not a party to the
construction contract. The contract itself imposed no obligations
on defendant Booe individually. Throughout construction, defendant
served as an officer, employee, and agent of Booe Building and
acted within the scope and course of his employment. The fact that
defendant had an ownership interest in Booe Building and exercised
control over the corporation does not, without more, subject him topersonal liability for the liabilities incurred by Booe Building.
Under Statesville, plaintiffs could maintain a negligence action
against defendant in his individual capacity only if they showed
(1) that defendant acted outside the course and scope of his
employment; or (2) that the corporation was a sham (thereby
justifying the piercing of the corporate veil). Upon review, we
discern no such showing by plaintiffs.
In affirming the trial court's judgment, we also note that
plaintiffs could not maintain an action against defendant in tort
even if he was the contractor. Plaintiffs were the original owners
of the house in question and were the promisees in the construction
contract. Our Supreme Court has stated that [o]rdinarily, a
breach of contract does not give rise to a tort action by the
promisee against the promisor. Ports Authority v. Roofing Co.,
294 N.C. 73, 81, 240 S.E.2d 345, 350 (1978), rejected on other
grounds by Trustees of Rowan Tech. v. Hammond Assoc., 313 N.C. 230,
328 S.E.2d 274 (1985). Although exceptions to the general rule
exist, none of the exceptions are applicable to the case before us.
See Ports Authority, 294 N.C. at 82, 240 S.E.2d at 350.
In Spillman v. American Homes, 108 N.C. App. 63, 422 S.E.2d
740 (1992), this Court applied the reasoning of Ports Authority to
construction cases. The plaintiffs in Spillman asserted a tort
claim based upon their allegation that the defendant failed to
perform the terms of their contract and improperly constructed and
installed the plaintiffs' mobile home. Id. at 64, 422 S.E.2d at
741. In reversing the denial of the defendant's motion for adirected verdict, the Spillman Court stated:
Absent the existence of a public policy
exception, as in the case of contracts
involving a common carrier, innkeeper or other
bailee, see Ports Authority v. Roofing Co.,
294 N.C. 73, 82, 240 S.E.2d 345, 350-51
(1978), a tort action does not lie against a
party to a contract who simply fails to
properly perform the terms of the contract,
even if that failure to properly perform was
due to the negligent or intentional conduct of
that party, when the injury resulting from the
breach is damage to the subject matter of the
contract. It is the law of contract and not
the law of negligence which defines the
obligations and remedies of the parties in
such a situation.
Id. at 65, 422 S.E.2d at 741-42. See also Mason v. Yontz, 102 N.C.
App. 817, 403 S.E.2d 536 (1991) (Plaintiffs could not recover
damages based on a negligence method of recovery against the
builder for the alleged improper construction of their swimming
pool.).
Plaintiffs argue that defendant's work resulted in Building
Code violations which constituted violations of a duty imposed as
a matter of public policy and were, therefore, sufficient to impose
tort liability. However, we do not believe this argument is
persuasive. See Ports Authority, 294 N.C. at 82-83, 240 S.E.2d at
350-51; and Warfield v. Hicks, 91 N.C. App. 1, 9-10, 370 S.E.2d
689, 694, disc. review denied, 323 N.C. 629, 374 S.E.2d 602 (1988).
Prior cases from this Court limit the remedy for original owners to
contractual theories rather than tort. Finally, we note that the
economic loss doctrine precludes recovery for plaintiffs on their
tort claim. North Carolina has adopted the economic loss rule,which prohibits recovery for economic loss in tort. Instead, such
claims are governed by contract law[.] The courts have construed
the term 'economic losses' to include damages to the product
itself. Moore v. Coachmen Industries, Inc., 129 N.C. App. 389,
401, 499 S.E.2d 772, 780 (1998). See also Ports Authority, 294
N.C. 73, 240 S.E.2d 345. As such, plaintiffs' sole remedy, if one
is deemed proper, is for breach of contract and breach of warranty
against Booe Building.
In light of the foregoing, we hold that plaintiffs cannot
assert a negligence claim against defendant Booe in his individual
capacity, and that summary judgment in favor of Booe was therefore
proper. Accordingly, plaintiffs' first assignment of error is
overruled.
Plaintiffs also argue that the trial court erred by denying
their motion for partial summary judgment against defendant Booe in
his individual capacity. Although the trial court did not enter a
written order as to plaintiffs' motion for partial summary
judgment, the trial court's 13 November 2001 judgment granting
summary judgment in favor of defendant rendered plaintiffs' motion
moot. It is clear that the trial court did not find plaintiffs'
motion persuasive, and for the same reasons it granted defendant's
motion for summary judgment, the trial court implicitly denied
plaintiffs' motion for partial summary judgment. Plaintiffs'
second assignment of error is meritless and is therefore overruled.
Upon careful review of the record and the arguments presented
by the parties, we conclude the trial court acted properly in allrespects. The trial court's judgment in favor of defendant Booe is
hereby
Affirmed.
Chief Judge EAGLES and Judge ELMORE concur.
Report per Rule 30(e).
*** Converted from WordPerfect ***