COASTAL CAISSON CORP.
a Delaware corporation,
Plaintiff,
v
.
Wake County
No. 00 CVS 658
KLINE IRON and STEEL CO., INC.
a South Carolina corporation
and CAPITOL BROADCASTING COMPANY
INCORPORATED a North Carolina
corporation,
Defendants.
Womble Carlyle Sandridge & Rice, PLLC, by Pressly M. Millen
for plaintiff-appellant.
The Law Office of John T. Benjamin, Jr., by John T. Benjamin,
Jr. and William E. Hubbard for defendant-appellee Kline Iron
and Steel Co., Inc.
STEELMAN, Judge.
Plaintiff, Coastal Caisson Corporation, appeals an order
allowing defendant Kline Iron and Steel Company's motion for
partial summary judgment. For the reasons discussed herein, we
affirm. Capitol Broadcasting contracted with Kline to construct a
television tower on 14 August 1997. On 7 December 1998, Kline
solicited a bid from plaintiff, an underground construction
subcontractor, to install the foundations for the television tower.
In soliciting the bid, Kline provided plaintiff with a subsurface
report about the quality and competency of subsurface rock and
soil. The report noted that the rock found at the tower base and
other locations was very competent and that blasting would be
necessary. In preparing its bid, plaintiff relied on the report in
determining construction schedules, equipment and costs. Based on
experience with rock formation as described in the report,
plaintiff selected a pre-excavation drilling and blasting
technique, caisson drilling equipment and estimated seven to eight
weeks to complete the work.
Plaintiff submitted a bid for $547,210. Its proposal
specifically stated that [s]oil conditions which are different
from those represented in the soils report may cause design changes
and/or extra charges. Plaintiff reserved the right to make a
claim for addition compensation or time. Kline requested a requote
on 29 December 1998. Plaintiff submitted a second bid at $486,990.
On 14 January 1999, Kline forwarded to plaintiff a purchase order
which stated:
Foundation Contract for the WRAL-TV 1989 Ft.Tower in Auburn, N.C. per Foundation Contract
Agreement to be forwarded upon completion and
per your quote dated December 29, 1998 in the
amount of $486,990.00 plus $7,304.85 for
Performance and Payment Bond for a total of
$494,294.85 as noted in Article Four, Price
and Payment.
Work to begin approx. February 26, 1999.
Plaintiff and Kline entered into a written contract for the
project, dated 1 February 1999, which was designated as the
Foundation Contract.
From February to May 1999, plaintiff discovered that
subsurface conditions were materially different from the conditions
described in the report. Because of the differences, plaintiff was
unable to use the blasting technique and certain equipment as
planned. On 3 June 1999, Kline authorized plaintiff to use a
different technique and equipment to install the foundations. On
9 August 1999, plaintiff submitted a claim for additional
compensation due to increased time and effort, with the use of
special equipment and extra personnel. Plaintiff requested a total
of $698,245 plus interest.
On 19 January 2000, plaintiff filed a complaint against Kline
and Capitol Broadcasting, alleging breach of contract and quantum
meruit and seeking to enforce its lien against funds owed to Kline
by Capitol Broadcasting or to enforce its lien against Capitol
Broadcasting's real property. Plaintiff had previously filed aclaim of lien by a first tier subcontractor. On 18 February 2000,
Capitol Broadcasting filed an answer, motion to dismiss and a
crossclaim against Kline for indemnity. On 24 March 2000, Kline
filed an answer asserting six affirmative defenses: express terms
of the contract, waiver, estoppel, void lien, and assumption of
risk. Kline's answer also included a motion to dismiss and
crossclaims against Capitol Broadcasting for indemnity,
contribution, breach of contract and unjust enrichment. Kline
further asserted a counterclaim against plaintiff for breach of
contract.
On 24 August 2001, Kline filed a motion for partial summary
judgment on the breach of contract and equitable claims raised
against it by plaintiff. On 11 October 2001, the trial court
granted Kline's motion for partial summary judgment. Plaintiff
appeals.
Following the trial court's entry of summary judgment, all
parties entered into a consent order resolving all issues between
them with the exception of those in this appeal.
Summary judgment is proper when the pleadings, depositions,
answers to interrogatories, and admissions on file, together with
the affidavits, if any, show that there is no genuine issue as to
any material fact and that any party is entitled to a judgment as
a matter of law. N.C. Gen. Stat. § 1A-1, Rule 56(c) (2001). Themoving party bears the burden of demonstrating the lack of triable
issues of fact. Koontz v. City of Winston-Salem, 280 N.C. 513, 518,
186 S.E.2d 897, 901 (1972). Once the movant satisfies its burden
of proof, the burden then shifts to the non-movant to present
specific facts showing triable issues of material fact. Lowe v.
Bradford, 305 N.C. 366, 369-70, 289 S.E.2d 363, 366 (1982). On
appeal from summary judgment, we review the record in the light
most favorable to the non-moving party. Bradley v. Hidden Valley
Transp., Inc., 148 N.C. App. 163, 165, 557 S.E.2d 610, 612 (2001),
aff'd, 355 N.C. 485, 562 S.E.2d 422 (2002) (citing Caldwell v.
Deese, 288 N.C. 375, 378, 218 S.E.2d 379, 381 (1975)).
In its first assignment of error, plaintiff argues that the
trial court erred in granting Kline's motion for partial summary
judgment on the breach of contract claim. Plaintiff contends that
material issues of fact remain on the question of whether the terms
of the Foundation Contract allow plaintiff to make claims for
additional compensation based on unexpected expenses. We disagree.
It is a well-settled rule of contract construction that
[i]ndividual clauses in an agreement and particular words must be
considered in connection with the rest of the agreement, and all
parts of the writing, and every word in it, will, if possible, be
given effect. Robbins v. C. W. Myers Trading Post, Inc., 253 N.C.
474, 477, 117 S.E.2d 438, 440 (1960). Plaintiff contends that the provisions of its proposal, which
allow it to make a claim for additional compensation should actual
conditions vary from those represented were accepted by Kline and
were not superceded by the terms of the Foundation Contract.
The purchase order sent by Kline to plaintiff clearly stated
that the Foundation Contract would be forwarded upon
completion[.] It was clearly contemplated that the agreement
between Kline and plaintiff would be reduced to writing in the
Foundation Contract. This was the final and only agreement between
the parties. There was no interim agreement based upon plaintiff's
bid and Kline's purchase order.
Paragraph 4.1(f) of the Foundation Contract provides that:
It is further agreed that the Contractor
prior to entering into this contract has
investigated the site and has satisfied itself
that the price it has quoted is sufficient to
perform the work and that the ground
conditions and underground conditions are
suitable for the performance of the work
intended, so accordingly no claims shall be
submitted by the Contractor for conditions
existing at the surface or underneath the
surface of the ground.
The Foundation Contract also contains clause 9.7, designated as
Interpretation of Contract. Section (a) of paragraph 9.7
provides that:
*** Converted from WordPerfect ***