Link to original WordPerfect file
How to access the above link?
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the
print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
POMPANO MASONRY CORPORATION, Plaintiff, v. HDR ARCHITECTURE,
INC., Defendant
NO. COA03-43
Filed: 20 July 2004
1. Construction Claims--breach of duty--negligent performance as project expediter--
economic loss
The trial court erred in a negligence action by granting summary judgment in favor of
defendant, a separate prime contractor also serving as project expediter, based on N.C.G.S. §
143-128 or lack of privity of contract with plaintiff subcontractor, because: (1) although a
subcontractor is allowed to submit to its own prime contractor its claims against a separate prime
contractor, the subcontractor is not required to follow such a procedure; (2) defendant may be
held liable for the foreseeable economic injury resulting from its alleged negligent performance
of its duties as project expediter; and (3) while no privity of contract exists between defendant
and plaintiff, a working relationship and community of interests exists allowing plaintiff to sue
defendant for the economic loss resulting from defendant's alleged breach of its common law
duty of care.
2. Statutes of Limitation and Repose--statute of limitation--negligence
The trial court erred in a negligence action by granting summary judgment in favor of
defendant, a separate prime contractor also serving as project expediter, on the grounds that
plaintiff subcontractor's claim was barred by the statute of limitations, because: (1) N.C.G.S. § 1-
52 imposes a three-year statute of limitations for negligence actions and the action accrues at the
time plaintiff discovers or reasonably should have discovered the injury or damage as long as it is
within ten years of defendant's negligence; (2) plaintiff filed its negligence action within three
years of its discovery of defendant's alleged negligence during the June 1998 coordination
meetings; and (3) it cannot be concluded as a matter of law that plaintiff reasonably should have
discovered the damages or negligence prior to the coordination meetings.
3. Negligence--contributory negligence--participation in planning and approval of
project schedule--proximate cause
The trial court erred in a negligence action by granting summary judgment in favor of
defendant, a separate prime contractor also serving as project expediter, on the ground that
plaintiff subcontractor's claim was barred by plaintiff's own contributory negligence, because:
(1) whether plaintiff had a duty as a subcontractor to participate in the project planning and
scheduling as early as February 1998 is a question for the jury; and (2) assuming arguendo that
plaintiff was negligent in not participating in the planning and approval of the project schedule,
there was no clear indication in the record that such negligence was the proximate cause of
plaintiff's injury and damages.
4. Contracts--assumption of risk--lack of privity of contract
The trial court erred in a negligence action by granting summary judgment in favor of
defendant, a separate prime contractor also serving as project expediter, on the ground that
plaintiff subcontractor assumed the risk of injury by entering into its subcontract with another
prime contractor, because: (1) defendant failed to allege any contractual relationship between
itself and plaintiff, and defendant also challenged plaintiff's right to sue defendant based on lack
of contractual privity; and (2) assumption of risk is not available as a defense to one not in acontractual relationship to plaintiff.
5. Damages and Remedies--failure to mitigate damages--summary judgment
The trial court erred in a negligence action by granting summary judgment in favor of
defendant, a separate prime contractor also serving as project expediter, on the ground that
plaintiff subcontractor failed to mitigate damages, because failure to mitigate damages is not an
absolute bar to all recovery even though a plaintiff is barred from recovering for those losses
which could have been prevented through plaintiff's reasonable efforts.
6. Damages and Remedies--home office expenses--summary judgment
The trial court erred in a negligence action by granting summary judgment in favor of
defendant, a separate prime contractor also serving as project expediter, on the ground that
plaintiff subcontractor is prevented from recovering home office expenses, because: (1) although
a plaintiff is not entitled to recover any home office expenses not contemplated in their contract
with a defendant, no such contract or privity exists between plaintiff and defendant in the instant
case; and (2) assuming arguendo that plaintiff is in fact prevented from recovering home office
expenses, the trial court is authorized only to dismiss plaintiff's claims to those particular
damages and not plaintiff's entire claim.
Appeal by plaintiff from judgment entered 30 August 2002 by
Judge Robert P. Johnston in Mecklenburg County Superior Court.
Heard in the Court of Appeals 12 November 2003.
SMITH, CURRIE & HANCOCK LLP, by Harry R. Bivens and David Hill
Bashford, for plaintiff-appellant.
MOORE & VAN ALLEN, PLLC, by George V. Hanna, III, and Robert
C. Bowers, for defendant-appellee.
TIMMONS-GOODSON, Judge.
Pompano Masonry Corporation (plaintiff) appeals the trial
court order granting summary judgment in favor of HDR Architecture,
Inc. (defendant). For the reasons discussed herein, we reverse
the trial court's order.
The evidence presented upon the motion for summary judgment
tends to show the following: In 1995, the University of North
Carolina (UNC) entered into a public construction project
contract with defendant, whereby defendant was to oversee theproject design work related to the construction of the Biological
Science Research Center at the University of North Carolina at
Chapel Hill (the project). In 1997, UNC and defendant entered
into a contract that named defendant project expediter. As
project expediter, defendant was responsible for preparing the
project schedule and overseeing and coordinating the work between
various prime contractors and subcontractors. Metric Constructors,
Inc. (Metric) served as the prime contractor for the general
construction work of the project. In early 1998, Metric entered
into a subcontract with plaintiff, whereby plaintiff agreed to
perform the masonry work for the project.
On 10 February 1998, defendant prepared the first Project
Schedule (10 February Project Schedule) for the project. The 10
February Project Schedule provided that concrete masonry work would
begin on 22 June 1998, after the initiation of the mechanical,
electrical, and plumbing (MEP) work. The 10 February Project
Schedule also provided that plaintiff's masonry work would be
completed on 25 March 1999.
On 16 June 1998, plaintiff's representatives attended a
coordination meeting at the project site. At the coordination
meeting, plaintiff criticized the scheduling and sequencing of the
MEP work in the 10 February Project Schedule. Plaintiff provided
defendant with input as to the scheduling and sequencing of the MEP
work and requested that plaintiff's masonry work be rescheduled
ahead of the MEP work for efficiency reasons. The prime
contractors, plaintiff, and defendant each agreed to reschedule
plaintiff's work prior to the MEP work but after completion ofMetric's concrete work. The subcontract between Metric and
plaintiff remained unsigned.
In July 1998, plaintiff was notified that Metric's concrete
work had progressed to the point where masonry work could begin.
However, plaintiff refused to sign the subcontract with Metric, and
in plaintiff's absence, the MEP work began. On 13 July 1998,
plaintiff notified Metric that plaintiff would incur $127,924 in
additional costs in order to perform masonry work after the MEP
work. On the same day, plaintiff began its masonry work on the
project, and on 15 July 1998, plaintiff signed the subcontract with
Metric.
Plaintiff completed its masonry work on the project on 10
November 1999, eight months after the original completion date
indicated by the 10 February Project Schedule, and fifteen months
after the actual start date of the masonry work. On 31 May 2001,
plaintiff filed a Complaint alleging that defendant
fail[ed] . . . to properly schedule and coordinate the work on the
[p]roject, and that as a result, [plaintiff] was forced to
perform out-of-sequence work and incurred significant disruptions
to its work, substantially impairing [plaintiff's] ability to
efficiently perform its work. . . . thereby increasing
[plaintiff's] costs to perform its work. Defendant filed an
Answer asserting that plaintiff was responsible, through its own
action or omissions, for some or all of the acts and omissions
alleged to have been committed by [defendant], and that plaintiff
knowingly and voluntarily assumed the risk of any delays or other
problems that were in existence or were reasonably foreseeable atthe time [p]laintiff undertook its [work on the project].
On 10 July 2002, defendant moved the trial court for summary
judgment, stating, inter alia, the following:
Plaintiff's claim is barred by the applicable
statute of limitations, the economic loss
doctrine, the lack of any contractual or
statutory relationship between [p]laintiff and
[defendant], and [p]laintiff's failure to
pursue its alleged damages through the claims
of its prime contractor. . . . Additionally,
[p]laintiff's claim is barred by its own
contributory negligence, by its assumption of
risk, and by its failure to mitigate its
alleged damages.
On 30 August 2002, the trial court granted summary judgment in
favor of defendant. Plaintiff appeals.
The dispositive issue on appeal is whether the trial court
erred in granting summary judgment in favor of defendant. Because
we conclude defendant was not entitled to judgment as a matter of
law, we hold that the trial court erred in granting summary
judgment in favor of defendant.
[T]he standard of review on appeal from summary judgment is
whether there is any genuine issue of material fact and whether the
moving party is entitled to a judgment as a matter of law.
Bruce-Terminix Co. v. Zurich Ins. Co., 130 N.C. App. 729, 733, 504
S.E.2d 574, 577 (1998). Summary judgment is appropriate when,
viewed in the light most favorable to the non-movant[,]
Id., the
pleadings, depositions, answers to interrogatories, and admissions
on file, together with the affidavits, if any, show that there is
no genuine issue as to any material fact and that any party is
entitled to a judgment as a matter of law. N.C. Gen. Stat. §1A-1, Rule 56(c) (2003). The party moving for summary judgment
must establish that no triable issue of material fact exists 'by
proving that an essential element of the opposing party's claim is
non-existent, or by showing through discovery that the opposing
party cannot produce evidence to support an essential element of
his claim or cannot surmount an affirmative defense which would bar
the claim.'
DeWitt v. Eveready Battery Co., 355 N.C. 672, 681,
565 S.E.2d 140, 146 (2002) (quoting
Collingwood v. General Elec.
Real Estate Equities, Inc., 324 N.C. 63, 66, 376 S.E.2d 425, 427
(1989)).
Statutory and Contractual Bars to Recovery of Economic Loss
[1] Defendant contends that plaintiff's negligence action was
barred by the lack of any contractual or statutory relationship
between defendant and plaintiff. According to defendant, N.C. Gen.
Stat. § 143-128 (2003) and the cases interpreting it require that
plaintiff first submit its claims against defendant to Metric, its
prime contractor. We disagree.
N.C. Gen. Stat. § 143-128(a1) (2003) provides as follows:
Construction methods. -- The State, a county,
municipality, or other public body shall award
contracts to erect, construct, alter, or
repair buildings pursuant to any of the
following methods:
(1) Separate-prime bidding.
(2) Single-prime bidding.
(3) Dual prime bidding pursuant to
subsection (d1) of this
section.
(4) Construction management at risk
contracts pursuant to G.S. 143-
128.1.
(5) Alternative contracting methods
authorized pursuant to G.S.
143-135.26(9).
N.C. Gen. Stat. § 143-128(b) (2003) provides further that
where the State chooses to award contracts to multiple contractors:
Each separate contractor shall be directly
liable to the State of North Carolina, or to
the county, municipality, or other public body
and to the other separate contractors for the
full performance of the separate contracts and
in accordance with the plans and
specifications, which shall specifically set
forth the duties and obligations of each
separate contractor.
The statute defines a separate contractor as any person, firm or
corporation who shall enter into a contract with the State, or with
any county, municipality, or other public entity to erect,
construct, alter or repair any building or buildings, or parts of
any building or buildings. Id. Thus, under N.C. Gen. Stat. §
143-128, a prime contractor may be sued by another prime
contractor working on a construction project for economic loss
foreseeably resulting from the first prime contractor's failure to
fully perform 'all duties and obligations due respectively under
the terms of the separate contracts.' Bolton Corp. v. T.A. Loving
Co., 94 N.C. App. 392, 396, 380 S.E.2d 796, 800, disc. review
denied, 325 N.C. 545, 385 S.E.2d 496 (1989). However, the statute
does not provide an express remedy for the circumstances of the
instant case, where a subcontractor has sued a separate prime
contractor that also served as project expediter.
In Bolton, a heating and ventilating prime contractor sued a
project expediter for the project expediter's breach of its
contract with the State. The prime contractor claimed that the
project expediter's breach caused the prime contractor and its
subcontractor undue delay and damages. This Court recognizedinitially that the suit was based not in tort, but upon the
provisions of N.C. Gen. Stat. § 143-128. Id. at 396, 380 S.E.2d at
799. We concluded that the subcontractor's claims against the
project expediter were properly brought by the prime contractor
because [a] contractor may recover from an owner its
subcontractor's 'extra costs and services wrongfully demanded' when
the subcontractor is not in privity with the owner and could not
recover directly. Id. at 407, 380 S.E.2d at 806 (quoting United
States v. Blair, 321 U.S. 730, 737 (1944)). Interpreting the terms
of the contract between the project expediter and the State, we
concluded the following:
There is no privity of contract between the
subcontractor and the [State], nor the
subcontractor and the other primes. The
subcontractor is viewed under the contract as
a mere employee or agent of the prime
contractor.
Id. at 408, 380 S.E.2d at 806.
In the instant case, defendant contends that because no
privity exists between it and plaintiff, Bolton requires plaintiff
to first submit its claims up the chain to Metric rather than
directly against defendant. However, we note that Bolton merely
allows a subcontractor to submit to its own prime contractor its
claims against a separate prime contractor -- the decision does not
require the subcontractor to follow such a procedure. Furthermore,
we also note that this Court's decision in Bolton does not overrule
our previous decision in Davidson and Jones, Inc. v. County of New
Hanover, 41 N.C. App. 661, 255 S.E.2d 580, disc. review denied, 298
N.C. 295, 259 S.E.2d 911 (1979).
In Davidson, a general contractor and its subcontractors sued an architect for the architect's failure to reasonably conduct its
examinations and inspections of the soil conditions and foundations
adjoining a county building site. The trial court dismissed the
subcontractor's complaints for failure to state a claim upon which
relief may have been granted. On appeal, this Court reversed the
trial court and held that in the absence of privity of contract[,]
an architect may be held liable to a general contractor and his
subcontractors for economic loss resulting from breach of a common
law duty of care. Id. at 666, 255 S.E.2d at 583-84. We noted
that a complete binding contract between the parties is not a
prerequisite to a duty to use due care in one's actions in
connection with an economic relationship, nor is it a prerequisite
to suit by a contractor against an architect. Id. at 666, 255
S.E.2d at 584. We further concluded that
[a]n architect, in the performance of his
contract with his employer, is required to
exercise the ability, skill, and care
customarily used by architects upon such
projects. 5 Am. Jur. 2d, Architects, § 8, pp.
669-70. Where breach of such contract results
in foreseeable injury, economic or otherwise,
to persons so situated by their economic
relations, and community of interests as to
impose a duty of due care, we know of no
reason why an architect cannot be held liable
for such injury.
Id. at 667, 255 S.E.2d at 584.
In the instant case, we conclude defendant may be held liable
for the foreseeable economic injury resulting from its alleged
negligent performance of its duties as project expediter. As we
recognized in Davidson, [l]iability arises from the negligent
breach of a common law duty of care flowing from the parties'
working relationships. Id. In the instant case, while no privityof contract exists between defendant and plaintiff, a working
relationship and community of interests clearly exists. Thus,
while plaintiff could not maintain a cause of action against
defendant grounded upon defendant's negligent performance of its
contract with the State, Davidson authorizes plaintiff to sue
defendant for the economic loss resulting from defendant's alleged
breach of its common law duty of care, despite the fact that no
privity exists between plaintiff and defendant. Id.
The project expediter is charged with using proper procedures
to obtain information to evaluate the progress of the project.
Bolton, 94 N.C. App. at 398, 380 S.E.2d at 801 (citing Goldberg,
The Owner's Duty to Coordinate Multi-Prime Construction
Contractors, A Condition of Cooperation, 28 Emory L.J. 377, 385-87
(1979)). Plaintiff's Complaint recognizes this duty and claims
that defendant breached its duty as project expediter by failing to
properly schedule the work, failing to maintain a reasonable and
workable project schedule, failing to give adequate and reasonable
notice to the subcontractors regarding the sequencing of work to
ensure efficient coordination of all phases of the work, and
failing to properly incorporate into the schedule the
subcontractors' input regarding the sequencing of work. Based upon
our holding in Davidson, we conclude plaintiff stated a proper
cause of action for negligence in the instant case. Therefore, we
hold that summary judgment was improper on the grounds that
plaintiff's claim was barred by N.C. Gen. Stat. § 143-128 or the
absence of privity of contract.
Statute of Limitations
[2] Defendant also contends that plaintiff's claim is barred
by the applicable statute of limitations. We disagree.
N.C. Gen. Stat. § 1-52 (2003) imposes a three-year statute of
limitations for negligence actions. The negligence action accrues
at the time the plaintiff discovers, or reasonably should have
discovered, the injury or damage, as long as it is within ten years
of the defendant's negligence. N.C. Gen. Stat. § 1-52(16) (2003).
In the instant case, plaintiff filed its negligence action
within three years of its discovery of defendant's alleged
negligence during the June 1998 coordination meetings.
Furthermore, we cannot conclude as a matter of law that plaintiff
reasonably should have discovered the damages or negligence prior
to the coordination meetings. Therefore, we hold that summary
judgment was improper on the grounds that plaintiff's claim was
barred by the statute of limitations.
Contributory Negligence
A trial court may grant summary judgment in a negligence case
where the uncontroverted evidence establishes that the defendant
failed to use ordinary care and that want of ordinary care was at
least one of the proximate causes of injury. DiOrio v. Penny, 331
N.C. 726, 728, 417 S.E.2d 457, 459 (1992). A trial court may also
grant summary judgement in a negligence action where the evidence
fails to show negligence on the part of defendant, or where
contributory negligence on the part of plaintiff is established.
Hale v. Power Co., 40 N.C. App. 202, 203, 252 S.E.2d 265, 267,
disc. review denied, 297 N.C. 452, 256 S.E.2d 805 (1979). However,
[t]he existence of contributory negligence is ordinarily aquestion for the jury; such an issue is rarely appropriate for
summary judgment, and only where the evidence establishes a
plaintiff's negligence so clearly that no other reasonable
conclusion may be reached. Martishius v. Carolco Studios, Inc.,
355 N.C. 465, 479, 562 S.E.2d 887, 896 (2002).
Our Supreme Court has held that [a] plaintiff is
contributorily negligent when he fails to exercise such care as an
ordinarily prudent person would exercise under the circumstances in
order to avoid injury. Newton v. New Hanover County Bd. of
Education, 342 N.C. 554, 564, 467 S.E.2d 58, 65 (1996). This Court
has previously held that
contributory negligence . . . may arise where
a plaintiff knowingly exposes himself to a
known danger when he had a reasonable choice
or option to avoid that danger, or when a
plaintiff heedlessly or carelessly exposes
himself to a danger or risk of which he knew
or should have known.
Lashlee v. White Consol. Indus., Inc., 144 N.C. App. 684, 690-91,
548 S.E.2d 821, 825-26, disc. review denied, 354 N.C. 574, 559
S.E.2d 179 (2001)(citations omitted).
[3] In the instant case, defendant contends that plaintiff
chose to ignore a clear invitation contained in its subcontract
with Metric to participate in the project planning and scheduling.
According to defendant, plaintiff thus aggravated and contributed
to its own injury despite a reasonable opportunity to avoid the
injury. We disagree.
Angelo Antenucci (Antenucci), one of plaintiff's officers in
1998, stated in his deposition that there had been no conversations
between plaintiff and defendant regarding the scheduling orsequencing of the project prior to the June 1998 coordination
meeting. Antenucci also stated that plaintiff would ordinarily
participate in those meetings in other projects. However,
Antenucci further stated that plaintiff would not participate in
coordination meetings too far early into the project . . . if
masonry wouldn't start, you know, for three months down the road.
We conclude a genuine issue as to a material fact remained
regarding plaintiff's contributory negligence. Whether plaintiff
had a duty as a subcontractor to participate in the project
planning and scheduling as early as February 1998 is a question for
the jury. Furthermore, assuming arguendo that plaintiff was
negligent in not participating in the planning and approval of the
project schedule, there is no clear indication in the record that
such negligence was the proximate cause of plaintiff's injury and
damages. Thus, a genuine issue of fact exists in the instant case
regarding not only whether plaintiff was negligent but also whether
plaintiff's failure was the proximate cause of plaintiff's injury.
Therefore, we hold that summary judgment was improper on the
grounds that plaintiff's claim was barred by plaintiff's own
contributory negligence.
Assumption of Risk
[4] Defendant also contends that summary judgment was proper
in the instant case because plaintiff assumed the risk of its
alleged injury by entering into its subcontract with Metric. We
disagree.
In the instant case, defendant failed to allege any
contractual relationship between it and plaintiff in its pleadings,and on appeal to this Court defendant challenges plaintiff's right
to sue defendant because of the lack of contractual privity between
the parties. It is well established in this jurisdiction that
assumption of risk is not available as a defense to one not in a
contractual relationship to the plaintiff. McWilliams v. Parham,
269 N.C. 162, 166, 152 S.E.2d 117, 120 (1967) (citations omitted).
Therefore, we hold that summary judgment was improper on the
grounds that plaintiff assumed the risk of its injury.
Damages
[5] Defendant also contends that summary judgment was proper
in the instant case because plaintiff failed to mitigate its
damages and is barred from recovering its extended home office
overhead damages. We disagree.
In a negligence action, it is well settled the party wronged
must use due care to minimize the loss occasioned by defendant's
negligence. Smith v. Childs, 112 N.C. App. 672, 682-83, 437
S.E.2d 500, 507 (1993). However, the failure to mitigate damages
is not an absolute bar to all recovery; rather, a plaintiff is
barred from recovering for those losses which could have been
prevented through the plaintiff's reasonable efforts. Id. at 683,
437 S.E.2d at 507. Thus, in the instant case, plaintiff's alleged
failure to mitigate damages does not serve as an absolute bar to
its claim. Therefore, we hold that summary judgment was improper
on the grounds that plaintiff failed to mitigate its damages.
[6] Defendant maintains that plaintiff is prevented from
recovering home office expenses in its negligence claim, and that
therefore summary judgment is proper in the instant case. Wedisagree.
Home office expenses are those expenses incurred by the
plaintiff indirect of the damages proximately caused by the
defendant. In Construction Co. v. Crain and Denbo, Inc., 256 N.C.
110, 123-26, 123 S.E.2d 590, 600-01 (1962), our Supreme Court
concluded that the plaintiffs were not entitled to recover any home
office expenses not contemplated in their contract with defendant.
However, as discussed above, no such contract or privity exists
between plaintiff and defendant in the instant case. Furthermore,
assuming arguendo that plaintiff is in fact prevented from
recovering its home office expenses, the trial court is authorized
only to dismiss plaintiff's claims to those particular damages, not
plaintiff's entire claim. Therefore, we hold that summary judgment
was improper on the grounds that plaintiff's action contained
improper claims for damages.
Conclusion
Summary judgment is a drastic measure, and it should be used
with caution.
Williams v. Power & Light Co., 296 N.C. 400, 402,
250 S.E.2d 255, 257 (1979).
[I]t is seldom appropriate to grant
summary judgment in a negligence action, [and] it is [only] proper
if there are no genuine issues of material fact, and the plaintiff
fails to demonstrate one of the essential elements of the claim.
Parish v. Hill, 350 N.C. 231, 236, 513 S.E.2d 547, 550 (1999). As
detailed above, we conclude that plaintiff is not barred from
bringing the action in the instant case, and we also conclude that
genuine issues of material fact remain in the action. Therefore,
we hold that the trial court erred in granting summary judgment infavor of defendant.
Reversed.
Judges WYNN and ELMORE concur.
*** Converted from WordPerfect ***