Link to original WordPerfect file
How to access the above link?
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the
print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
EASTWAY WRECKER SERVICE, INC., Plaintiff-Appellant, v. CITY OF
CHARLOTTE, Defendant-Appellee
NO. COA03-399
Filed: 3 August 2004
1. Civil Procedure_failure to state a claim_consideration of complaint's exhibits_not
transformed into summary judgment
A Rule 12(b)(6) motion was not transformed into a summary judgment motion by
consideration of exhibits to the complaint which were expressly incorporated by reference.
2. Quantum Meruit_government contract_sovereign immunity
The trial court did not err by dismissing a quantum meruit claim against the City of
Charlotte for failure to state a claim arising from the provision of towing services. Although the
trial court erred by dismissing the claim on the ground that it was precluded by express contract
where plaintiff had alleged that the contract was invalid (plaintiff's claims are taken as true when
ruling on a Rule 12(b)(6) motion), the dismissal was still appropriate because sovereign
immunity bars quantum meruit claims against the State. Any suggestion in prior cases that
sovereign immunity only bars quantum meruit claims arising from ultra vires contracts has been
overruled.
3. Fraud_negligent misrepresentation_failure to state a claim
A claim for negligent misrepresentation against the City of Charlotte for a towing
contract was properly dismissed for failure to state a claim where plaintiff did not allege that it
was denied the opportunity to investigate or that it could not have learned the facts by reasonable
diligence. Moreover, the complaint establishes that any reliance by plaintiff on representations
by employees of the City other than the City Manager was unjustified.
Judge MCGEE dissenting.
Appeal by plaintiff from order entered 6 January 2003 by Judge
Albert Diaz in Superior Court, Mecklenburg County. Heard in the
Court of Appeals 14 January 2004.
The Odom Firm, P.L.L.C., by T. LaFontine Odom, Sr. and Thomas
L. Odom, Jr., for plaintiff-appellant.
City Attorney's Office, by Senior Assistant City Attorney
Cynthia White, for defendant-appellee.
GEER, Judge.
Plaintiff Eastway Wrecker Service, Inc. ("Eastway") appeals
from an order dismissing its claims against defendant City ofCharlotte based on quantum meruit and negligent misrepresentation.
We hold that the quantum meruit cause of action is barred by
sovereign immunity while the negligent misrepresentation cause of
action failed to include all the allegations necessary to state a
claim for relief. We, therefore, affirm.
Factual Background
Plaintiff entered into an agreement with defendant providing
that plaintiff would tow, store, and dispose of motor vehicles, as
directed by the police, for a specified geographical area known as
Zone C. Plaintiff was to pay defendant $2,000.00 annually for the
right to service Zone C and agreed to various specifications and
conditions regarding documentation, service hours, and storage
facilities, as well as a fee schedule for services rendered and the
sale of unclaimed motor vehicles.
In a complaint filed 28 March 2002 and amended in August 2002,
plaintiff alleged that defendant breached the agreement by failing
to pay plaintiff for services provided under the agreement. In its
amended complaint, plaintiff added alternative claims for (1)
damages in quantum meruit for labor and materials supplied; (2) for
negligent misrepresentation by defendant in connection with the
agreement; and (3) breach of the covenant of good faith and fair
dealing. Defendant filed a motion to dismiss the alternative
claims pursuant to Rule 12(b)(6). Following a hearing, the trial
court entered an order on 6 January 2003 granting defendant's
motion to dismiss as to plaintiff's quantum meruit and negligent
misrepresentation claims, but denying it as to the claim for breach
of the implied covenant of good faith and fair dealing. As aresult, plaintiff's claims for breach of contract and breach of the
implied covenant of good faith and fair dealing remain pending.
Plaintiff appeals from the 6 January 2003 order.
Discussion
Because the trial court's order granting defendant's motion to
dismiss did not dispose of all of plaintiff's claims against
defendant, the order is interlocutory. DKH Corp. v. Rankin-
Patterson Oil Co., 348 N.C. 583, 584, 500 S.E.2d 666, 667 (1998).
The trial court, however, included a certification that the
dismissal of plaintiff's claims for quantum meruit and negligent
misrepresentation was a "final judgment[] and dispositive as to
these claims and there is no reason to delay an appeal." In an
action with multiple parties or multiple claims, Rule 54(b)
provides that "if the trial court enters a final judgment as to a
party or a claim and certifies there is no just reason for delay,
the judgment is immediately appealable." Id. at 585, 500 S.E.2d at
668. We agree with the trial court that the dismissal order was
properly certified under Rule 54(b) and, therefore, address the
merits of plaintiff's appeal.
[1] To determine if a complaint is sufficient to withstand a
Rule 12(b)(6) motion to dismiss, the trial court must "ascertain
'whether, as a matter of law, the allegations of the complaint,
treated as true, are sufficient to state a claim upon which relief
may be granted under some legal theory.'" Plummer v. Community
Gen. Hosp. of Thomasville, Inc., 155 N.C. App. 574, 576, 573 S.E.2d
596, 598 (2002) (quoting Shell Island Homeowners Ass'n v.
Tomlinson, 134 N.C. App. 217, 225, 517 S.E.2d 406, 413 (1999)),disc. review denied, 357 N.C. 63, 579 S.E.2d 392 (2003). As an
initial matter, we address the dissent's conclusion that the trial
court considered matters outside the pleadings, thereby converting
the motion to dismiss into a motion for summary judgment under Rule
12(b): "If, on a motion asserting the defense numbered (6), to
dismiss for failure of the pleading to state a claim upon which
relief can be granted, matters outside the pleading are presented
to and not excluded by the court, the motion shall be treated as
one for summary judgment and disposed of as provided in Rule 56,
and all parties shall be given reasonable opportunity to present
all material made pertinent to such a motion by Rule 56."
After carefully reviewing the record, it appears that the only
documents other than the pleadings that were before the trial court
in connection with the motion to dismiss were the plaintiff's
exhibits to the complaint. Since the exhibits to the complaint
were expressly incorporated by reference in the complaint, they
were properly considered in connection with the motion to dismiss
as part of the pleadings. See Oberlin Capital, L.P. v. Slavin, 147
N.C. App. 52, 60-61, 554 S.E.2d 840, 847 (2001) ("Here, the loan
agreement is the subject of [plaintiff's] complaint and is
specifically referred to in the complaint. Therefore, the trial
court did not err in reviewing the loan agreement when ruling on
the Rule 12(b)(6) motions.").
Quantum Meruit
[2] Plaintiff first contends that the trial court erred in
dismissing its alternative claim for recovery in quantum meruit on
the grounds that such recovery was precluded by the existence of anexpress contract between the parties. While it is true that an
express contract precludes recovery in quantum meruit, Paul L.
Whitfield, P.A. v. Gilchrist, 348 N.C. 39, 42, 497 S.E.2d 412, 414
(1998), it was improper for the trial court to assume the presence
of an express contract in this case. Under Rule 8(a)(2) of the
North Carolina Rules of Civil Procedure, plaintiff is entitled to
seek alternative forms of relief. N.C. Gen. Stat. § 1A-1, Rule
8(a)(2) (2003) ("Relief in the alternative or of several different
types may be demanded."). Here, plaintiff's alternative claim for
relief in quantum meruit does not allege that a contract exists,
but rather that the parties' contract is invalid because of defects
in its formation and performance. When ruling on a Rule 12(b)(6)
motion to dismiss, the trial court must only determine whether the
plaintiff's allegations, if taken as true, support a claim upon
which relief may be granted. Sutton v. Duke, 277 N.C. 94, 98-99,
176 S.E.2d 161, 163 (1970); N.C. Gen. Stat. § 1A-1, Rule 12(b)(6)
(2003). If plaintiff's allegations in its alternative claim are
accepted as true, no contract exists and quantum meruit is not
precluded as a remedy per se. Accordingly, it was error for the
trial court to dismiss plaintiff's alternative claim for recovery
in quantum meruit on the ground that it was precluded by an express
contract between the parties.
Nonetheless, dismissal of the quantum meruit claim was still
appropriate because such a claim when brought against an arm of the
State is barred by sovereign immunity. In North Carolina, the
State waives sovereign immunity when it expressly enters into a
valid contract. Smith v. State, 289 N.C. 303, 320, 222 S.E.2d 412,423-24 (1976). Sovereign immunity bars quantum meruit actions
against the State, however, because the remedy of quantum meruit is
based on an implied contract and an implied contract cannot support
the inference of an express waiver. Whitfield, 348 N.C. at 42, 497
S.E.2d at 415. Our Supreme Court held in Whitfield that "[a]
contract implied in law - as opposed to an express valid contract
- simply will not form a sufficient basis for a court to make a
reasonable inference that the State has intended to waive its
sovereign immunity." Id. at 45, 497 S.E.2d at 416.
This Court has since applied Whitfield and held: "[O]ur
Supreme Court declined to imply a contract in law in derogation of
sovereign immunity to allow a party to recover under a theory of
quantum meruit, and we decline to do so here." Data Gen. Corp. v.
County of Durham, 143 N.C. App. 97, 103, 545 S.E.2d 243, 248
(2001). See also Moore v. N.C. Coop. Extension Serv., 146 N.C.
App. 89, 93, 552 S.E.2d 662, 665 (citation omitted) ("In Whitfield,
the Supreme Court held that the State's waiver of sovereign
immunity only applies to express contracts and that contracts
implied in law, such as a claim in quantum meruit, are insufficient
to constitute a waiver of the State's sovereign immunity."), disc.
review denied, 354 N.C. 574, 559 S.E.2d 180 (2001). Archer v.
Rockingham County, 144 N.C. App. 550, 557, 548 S.E.2d 788, 792
(2001), disc. review denied, 355 N.C. 210, 559 S.E.2d 796 (2002),
relied upon by plaintiff, did not address a claim based on quantum
meruit, but rather a claim arising out of a valid employment
contract. It, therefore, did not _ indeed could not _ overrule
Whitfield. Plaintiff argues, however, that Whitfield's sovereign immunity
bar only applies in cases where a contract fails because it is
ultra vires. Plaintiff urges that if a contract fails for some
other reason, such as a defect in formation, then sovereign
immunity does not protect the State from quantum meruit claims.
Indeed, certain cases decided prior to Whitfield support
plaintiff's argument. See, e.g., Hawkins v. Town of Dallas, 229
N.C. 561, 564, 50 S.E.2d 561, 563 (1948); Rockingham Square
Shopping Center, Inc. v. Town of Madison, 45 N.C. App. 249, 254,
262 S.E.2d 705, 708 (1980). Further, Whitfield itself involved a
contract that was invalid because it was ulta vires. Whitfield,
348 N.C. at 43-44, 497 S.E.2d at 415-16.
The language and reasoning of Whitfield does not, however,
support the continuing validity of such a distinction. The Supreme
Court specifically held:
[W]e will not first imply a contract in law
where none exists in fact, then use that
implication to support the further implication
that the State has intentionally waived its
sovereign immunity and consented to be sued
for damages for breach of the contract it
never entered in fact. Only when the State
has implicitly waived sovereign immunity by
expressly entering into a valid contract
through an agent of the State expressly
authorized by law to enter into such contract
may a plaintiff proceed with a claim against
the State upon the State's breach.
Id. at 42-43, 497 S.E.2d at 415 (emphasis original). Without both
an express contract and a valid contract, the State has not waived
its sovereign immunity. This dual requirement necessarily
precludes any recovery in quantum meruit against the State
regardless of the reason why the alleged contract fails. To theextent prior cases suggested that sovereign immunity only bars
quantum meruit claims where the alleged contract is ulta vires,
they were overruled by Whitfield.
Plaintiff's complaint also alleges that the City was engaged
in a proprietary or ministerial act when entering into the contract
at issue, arguably a basis for avoiding the sovereign immunity
defense. The plaintiff has not, however, argued this theory on
appeal and, therefore, we do not reach that question. Plaintiff's
claim based on quantum meruit is barred by sovereign immunity and
dismissal was, for that reason, proper.
Negligent Misrepresentation
[3] Plaintiff has also appealed from the dismissal of its
claim for negligent misrepresentation. Plaintiff based its claim
on (1) misrepresentations "in Item 4 of the Contract and Amendments
that Eastway Wrecker shall be compensated per the attached fee
schedule upon completion of the Contract[,]" (2) the City's payment
of some towing and storage charges, (3) statements by employees
within the course and scope of their employment regarding payment,
and (4) the failure of the City to "respond with any denial that
charges had not accrued or there were no amounts owing."
The Supreme Court has held that "[t]he tort of negligent
misrepresentation occurs when a party justifiably relies to his
detriment on information prepared without reasonable care by one
who owed the relying party a duty of care."
Raritan River Steel
Co. v. Cherry, Bekaert & Holland, 322 N.C. 200, 206, 367 S.E.2d
609, 612 (1988). Plaintiff's claim could properly be dismissed by
the trial court pursuant to Rule 12(b)(6) if no law exists tosupport the claim, if the complaint fails to allege sufficient
facts to assert a viable claim, or if the complaint alleges facts
that will necessarily defeat the claim.
Oberlin Capital, 147 N.C.
App. at 61, 554 S.E.2d at 847. Here, the trial court properly
dismissed the negligent misrepresentation claim for failure to
allege all the required facts and because the complaint includes
facts that necessarily defeat the claim.
Plaintiff alleged in its complaint that "[d]efendant owed a
duty of care to Eastway Wrecker to provide accurate information in
the Contract and Amendments and other actions and omissions set
forth above." Plaintiff further alleged that it "reasonably and
justifiably relied upon the above misrepresentations to its
detriment by entering into the Contract and Amendments to tow,
store and dispose of vehicles for the Defendant from July 5, 1994
until October 31, 2001 and by actually towing, storing and
disposing of the vehicles."
It appears that plaintiff is at least in part alleging that
the City failed to disclose the legal import of the contract or to
properly memorialize the parties' agreement. While it is
questionable that such a contention, standing alone, could form a
basis for a negligent misrepresentation claim,
see International
Harvester Credit Corp. v. Bowman, 69 N.C. App. 217, 220, 316 S.E.2d
619, 621 (internal citations omitted) ("[a] person who executes a
written instrument is ordinarily charged with knowledge of its
contents, and may not base an action for fraud on ignorance of the
legal effect of its provisions"),
disc. review denied, 312 N.C.
493, 322 S.E.2d 556 (1984), the Court need not reach that question. This Court has held that if "the complaint fails to allege that
[the plaintiff] was denied the opportunity to investigate or that
[the plaintiff] could not have learned the true facts by exercise
of reasonable diligence, the complaint fails to state causes of
action for fraudulent concealment and negligent misrepresentation."
Oberlin Capital, 147 N.C. App. at 60, 554 S.E.2d at 847.
See also
Hudson-Cole Dev. Corp. v. Beemer, 132 N.C. App. 341, 346, 511
S.E.2d 309, 313 (1999) ("[W]hen the party relying on the false or
misleading representation could have discovered the truth upon
inquiry, the complaint must allege that he was denied the
opportunity to investigate or that he could not have learned the
true facts by exercise of reasonable diligence."). Because
plaintiff's complaint fails to include this required allegation, it
fails to state a claim for negligent misrepresentation.
Further, to the extent the complaint based its cause of action
on representations by employees of the City regarding the contract
and the amendments, the complaint establishes that any reliance by
plaintiff was unjustified. The original contract states:
This contract together with the Invitation to
Bid and, Instructions to Bidder, and the Bid
Continuation Sheet-Specifications and Special
Conditions constitutes the entire agreement
between the City and the Contractor on this
subject and its acceptance by the City Manager
of the City,
and no one is authorized to vary
same unless the proposed substitution or
variations are brought before the City
Manager.
(Emphasis added.) Each of the amendments to the contract,
extending the term of the agreement, specifically provided that the
terms of the original contract "shall remain in force and effect."
As a result of these provisions, plaintiff was not entitled to relyupon statements of City personnel, other than the City Manager,
regarding a variation of the terms of the contract. Since the
contract and the amendments were incorporated by reference in the
complaint, the complaint discloses facts that necessarily defeat
plaintiff's claim.
See Oberlin Capital, 147 N.C. App. at 61, 554
S.E.2d at 847 (language of loan agreement established that any
reliance was not reasonable and, therefore, "the trial court did
not err in dismissing the claim for negligence"). The trial court
thus properly granted the motion to dismiss the negligent
misrepresentation claim.
Affirmed.
Judge HUNTER concurs.
Judge McGEE dissents in a separate opinion.
McGEE, Judge, dissenting.
I respectfully dissent from the majority opinion for the
following reasons. To determine if a complaint is sufficient to
withstand a motion to dismiss pursuant to N.C. Gen. Stat. § 1A-1,
Rule 12(b)(6) (2003), the trial court must "ascertain 'whether, as
a matter of law, the allegations of the complaint, treated as true,
are sufficient to state a claim upon which relief may be granted
under some legal theory.'"
Plummer v. Community Gen. Hosp. of
Thomasville, Inc., 155 N.C. App. 574, 576, 573 S.E.2d 596, 598
(2002) (citation omitted),
disc. review denied, 357 N.C. 63, 579
S.E.2d 392 (2003). "When considering a 12(b)(6) motion to dismiss,
the trial court need only look to
the face of the complaint to
determine whether it reveals an insurmountable bar to plaintiff'srecovery."
Locus v. Fayetteville State University, 102 N.C. App.
522, 527, 402 S.E.2d 862, 866 (1991).
The sole purpose of a motion pursuant to N.C.G.S. § 1A-1, Rule
12(b)(6) is "to test the legal sufficiency of
the pleading against
which [the motion] is directed."
Azzolino v. Dingfelder, 71 N.C.
App. 289, 295, 322 S.E.2d 567, 573 (1984),
rev'd. in part and
aff'd. in part, 315 N.C. 103, 377 S.E.2d 528 (1985),
cert. denied,
479 U.S. 835, 93 L. Ed. 2d 75 (1986). Where a defendant asserts,
pursuant to Rule 12(b)(6), that a plaintiff's complaint has failed
to state a claim for which relief is available and where the trial
court considers
matters outside the pleading . . . [which
were] not excluded by the court, the motion
shall be treated as one for summary judgment
and disposed of as provided by Rule 56, and
all parties shall be given reasonable
opportunity to present all material made
pertinent to such a motion by Rule 56.
N.C.G.S. § 1A-1, Rule 12(b).
In the case before this Court, the trial court stated in its
order dismissing plaintiff's claims under Rule 12(b)(6), that it
"considered the pleadings, the Motion to Dismiss, the Motion to
Reconsider And/Or Amend, Plaintiff's Request to Certify, the
arguments of the parties and the applicable law." Defendant's
motion was directed solely at plaintiff's complaint and for the
trial court to consider other pleadings is contrary to the function
of Rule 12(b)(6). Based on the trial court's order, I conclude the
trial court considered matters in addition to the allegations in
the complaint and defendant's motion to dismiss was therebyconverted
into one for summary judgment. N.C.G.S. § 1A-1, Rule
12(b).
Plaintiff was not provided, upon conversion of the motion from
a 12(b)(6) motion to a summary judgment motion, a "reasonable
opportunity to present all material made pertinent to such a motion
by Rule 56." N.C.G.S. § 1A-1, Rule 12(b). Because plaintiff was
not afforded a reasonable opportunity to oppose the summary
judgment motion, as in
Locus, I would remand the case to the trial
court in order that plaintiff be permitted to present evidence in
opposition to the motion for summary judgment.
Locus, 102 N.C.
App. at 528, 402 S.E.2d at 866.
*** Converted from WordPerfect ***