Appeal by plaintiff from amended order entered 21 April 2003
by Judge Ripley E. Rand in Wake County Superior Court. Heard in
the Court of Appeals 17 March 2004.
Moore & Van Allen, P.L.L.C., by Kevin M. Capalbo for the
plaintiff-appellant.
Robert A. Brady for the defendant-appellee.
ELMORE, Judge.
Poythress Commercial Contractors, Inc. (Poythress) was the
general contractor on the Cary Fire Station No. 6 project
(project), and American National Electric Corporation (ANE) was an
electrical subcontractor. In September 1999, Poythress and ANE
executed a subcontract (subcontract) by which ANE would supply all
material and labor to perform certain electrical work on the
project. Pursuant to the subcontract, Poythress prepared and
delivered to ANE a Project CPM Schedule which provided that ANE
would have 144 days in which to perform its electrical work underthe subcontract. ANE agreed to perform its work pursuant to the
Project CPM Schedule prepared by Poythress. Article 5 of the
subcontract's Terms and Conditions provided that Poythress was
obligated to direct both the timing and sequence of ANE's work.
During the course of ANE's work on the project, Poythress made
certain alterations to the schedule and sequence of ANE's work.
ANE asserted that as a result, ANE was denied sufficient access to
the project to perform the work it intended to perform, in the
sequence in which ANE had agreed to perform it, such that ANE ended
up being on the project for over 200 days.
In April 2000, ANE's president, Ron Thoreson (Thoreson), gave
verbal notice to Poythress's project superintendent, Tom Seymour
(Seymour), that ANE's work was being adversely impacted due to
schedule and sequence changes. As soon as ANE's work on the
project was completed, ANE provided Poythress with written notice
of the amount of ANE's claim for damages, the basis for the claim,
and documentation supporting the claim. ANE claims Poythress'
changes to the scheduling and sequencing of ANE's work on the
project caused labor inefficiencies and loss of productivity
which damaged ANE in an amount not less than $52,025.00.
ANE filed a complaint against Poythress and Brown & Jones
Architects, Inc., seeking damages for breach of contract.
Poythress moved for summary judgment as to all counts in ANE's
complaint against it. The trial court granted summary judgment in
favor of Poythress. ANE appeals from that order granting summary
judgment.
I.
Summary judgment is appropriate when the pleadings,
depositions, answers to interrogatories, and admissions on file,
together with the affidavits . . . show that there is no genuine
issue as to any material fact and that any party is entitled to a
judgment as a matter of law. N.C. Gen. Stat. § 1A-1, Rule 56(c)
(2003). On appeal, the standard of review is (1) whether there is
a genuine issue of material fact and (2) whether the movant is
entitled to judgment as a matter of law.
See Kessing v. Mortgage
Corp., 278 N.C. 523, 180 S.E.2d 823 (1971). The evidence presented
is viewed in the light most favorable to the non-movant.
See
Caldwell v. Deese, 288 N.C. 375, 218 S.E.2d 379 (1975).
A defendant who moves for summary judgment
assumes the burden of positively and clearly
showing that there is no genuine issue as to
any material fact and that he or she is
entitled to judgment as a matter of law. 'A
defendant may meet this burden by: (1) proving
that an essential element of the plaintiff's
case is nonexistent, or (2) showing through
discovery that the plaintiff cannot produce
evidence to support an essential element of
his or her claim, or (3) showing that the
plaintiff cannot surmount an affirmative
defense which would bar the claim.'
James v. Clark, 118 N.C. App. 178, 180-81, 454 S.E.2d 826, 828
(1995) (quoting
Watts v. Cumberland County Hosp. System, 75 N.C.
App. 1, 6, 330 S.E.2d 242, 247 (1985),
reversed on other grounds,
317 N.C. 321, 345 S.E.2d 201 (1986)). In the present case, it
appears the trial court granted summary judgment in Poythress's
favor because it concluded ANE could not surmount Poythress's
affirmative defense that ANE's claims were barred by ANE's failureto comply with the notice provisions of the General Contract, which
provisions that were incorporated into the subcontract by Articles
7 and 23 of the subcontract.
Article 7 of the subcontract states, in relevant part, as
follows:
The Subcontractor agrees to be bound to the
Contractor by the terms of the General
Contract to the extent that it is applicable
to this Contract and to assume toward the
Contract all of the obligations and
responsibilities that the Contractor by that
document assumes toward the Owner insofar as
applicable to this Contract.
Article 23 of the subcontract states, in relevant part, as
follows:
Claims for extra or altered work, changes,
modifications, changed conditions, subsurface
conditions or obstructions at the site, any
Act of God, the elements, delays, equitable
adjustments, and the damages resulting from
requirements, acts or omission of the Owner or
any third party, or from any cause beyond the
control of the Contractor shall be governed by
the provisions of the General Contract and the
Contractor shall make payments to the
Subcontractor on account of such claims only
to the extent that the Contractor is paid
thereof by the Owner.
Poythress contends that Articles 7 and 23 incorporate into the
subcontract the notice provisions of Paragraph 8.3.2 of the general
conditions of the General Contract between Poythress and the
project's owner, the Town of Cary. Paragraph 8.3.2 in turn
requires that claims for delay compensation must be made in
accordance with Paragraph 4.3 of the General Contract. Paragraph
4.3 states that claims for delay must be made, in writing, to theproject architect and owner within 21 days after the occurrence of
any event giving rise to the claim or within 21 days after the
claimant first recognizes the condition giving rise to the claim.
ANE's president, Thoreson, admitted in his deposition testimony
that ANE was aware that its work was being delayed in April 2000,
but did not notify Poythress of its delay claim in writing until a
letter dated 20 September 2000. Poythress therefore contends that
ANE's failure to comply with these notice provisions of the General
Contract necessarily defeats its claims. We agree.
[T]he most fundamental principle of contract
construction_[is] that the courts must give effect to the plain and
unambiguous language of a contract.
Johnston County v. R.N. Rouse
& Co., 331 N.C. 88, 95, 414 S.E.2d 30, 34 (1992). The plain
language of the contract in this case provides that the
Subcontractor is bound to the Contractor under the same obligations
as the Contractor is bound to the Owner. Those obligations bind
the parties to a time certain during which notice of delay for
compensation must be given. That time was not observed by ANE
here, and thus ANE's complaint is defeated.
Poythress also contends that pursuant to Article 23 of the
subcontract, Poythress shall only be liable to pay ANE for delay to
the extent that Poythress is paid for said delay by the project
owner. ANE's president, Thoreson, admitted in his deposition
testimony that Poythress was never paid for these delays by the
owner. Our General Statutes state that [p]ayment by the owner to a
contractor is not a condition precedent for payment to a
subcontractor and payment by a contractor to a subcontractor is not
a condition precedent for payment to any other subcontractor, and
an agreement to the contrary is unenforceable. N.C. Gen. Stat. §
22C-2 (2003). When a contract contains provisions which are
severable from an illegal provision and are in no way dependent
upon the enforcement of the illegal provision for their validity,
such provisions may be enforced.
Rose v. Materials Co., 282 N.C.
643, 658, 194 S.E.2d 521, 532 (1973). We therefore conclude that
the pay when paid clause of the contract is indeed unenforceable,
but that it is severable from the rest of the contract and does not
defeat the other portions of the contract, such as the notice of
delay provision, which are in no way dependent on the illegal
provision.
We agree with Poythress's argument that Articles 7 and 23 of
the subcontract create an affirmative defense which ANE cannot
surmount and which operates to bar ANE's claims, such that summary
judgment was properly entered in favor of Poythress.
Affirmed.
Judges McCULLOUGH and BRYANT concur.
*** Converted from WordPerfect ***