O & M INDUSTRIES,
Plaintiff,
v
.
Davidson County
No. 02 CVS 0062
SMITH ENGINEERING CO., a/k/a
SMITH ENVIRONMENTAL CORPORATION;
KURZ TRANSFER PRODUCTS, L.P., and
KURZ & PARTNERS, L.P.,
Defendants.
Hendrick & Bryant, LLP, by Matthew H. Bryant, for plaintiff-
appellee.
Smith, Currie & Hancock LLP, by Michael W. Knapp, Rolly L.
Chambers, and David Hill Bashford, for defendant-appellant
Kurz Transfer Products, L.P.
BRYANT, Judge.
Kurz Transfer Products, L.P. (defendant) appeals an order by
Judge Christopher M. Collier filed 15 November 2002 granting
summary judgment to O & M Industries (plaintiff) and denying
defendant's motion for summary judgment.
(See footnote 1)
Defendant is a tenant of a manufacturing facility in
Lexington, North Carolina. In December 2000, defendant contracted
Smith Engineering Co. (Smith) to design, manufacture, and install
various equipment at the facility (the project), including a
regenerative thermal oxidizer system (RTO). Smith in turn
contracted plaintiff to manufacture the RTO.
Plaintiff began manufacturing the RTO in March 2001. By June
2001, plaintiff started to have concerns about Smith's financial
situation. During the same time period, defendant was having
similar concerns about Smith's ability to complete the project. On
or about 6 June 2001, plaintiff shipped the completed RTO to
defendant.
Defendant received from plaintiff a Notice of Claim of Lien
by First, Second or Third Tier Subcontractor dated 8 June 2001, in
which plaintiff claimed a lien on funds owed by defendant to Smith
in the amount of $113,655.00. The notice stated in part:
The [plaintiff] lien claimant gives this
notice of claim of lien pursuant to North
Carolina law and claims all rights of
subrogation to which it is entitled under Part
2 of Article 2 of Chapter 44A of the General
Statutes of North Carolina.
On 6 July 2001, defendant made a payment under the contract to
Smith in the amount of $164,831.25, and on 1 August 2001, defendant
made an additional payment to Smith of $150,000.00. Following
these payments, defendant still owed Smith $243,713.00 under the
terms of the contract.
On 22 August 2001, Smith informed defendant of Smith's filing
for bankruptcy. The next day, defendant's controller Dave Seymourstated in an electronic mail (email) to defendant's vice president
Drew Beringer and two others:
The [project] is nearly complete. There are
several issues with efficiency, electrical
connections, and general appearance but these
issues are likely solvable with a $25,000
investment. We still owe Smith $462,443.75.
We have issues with them that could accumulate
to well over $100,000 related to non[-]
performance and contract issues. We have no
intentions of making any further payments
until these issues are settled.
Subsequently, defendant received another Notice of Claim of Lien
by First, Second or Third Tier Subcontractor dated 23 August 2001
in which plaintiff claimed a lien on funds owed by defendant to
Smith in the amount of $127,392.12.
In an amended complaint filed 11 September 2002,
(See footnote 2)
plaintiff
alleged:
31. Defendant . . . had notice of
[plaintiff's] Notice of Claim of Lien in the
amount of $113,665 prior to [the] July 6, 2001
[payment to Smith].
32. Defendant . . . twice made payment
to . . . Smith in amounts in excess of
$113,665 after notice of [plaintiff's] Claim
of Lien.
33. Defendant . . . made payment
directly to Smith with [n]otice and knowledge
of [plaintiff's] Notice of Claim of Lien.
34. Pursuant to N.C.G.S. § 44A-20(b),
[d]efendant . . . is directly liable to
[p]laintiff . . . up to $113,665 for all
payments made to Smith after receipt of the
First Notice.
35. Plaintiff has been damaged by
[d]efendant['s] . . . failure to make payment
to [plaintiff] in the amount of $113,665, and
by its failure to abide by the First Notice.
. . . .
38. Upon information and belief,
[d]efendant . . . has retained $243,713.00
more or less, otherwise payable to . . .
Smith.
In an answer filed 8 October 2002, defendant responded to
plaintiff's allegations:
31. Admitted.
32. It is admitted that [defendant] made
payment to Smith; however, any payments
were made after withholding an amount
sufficient to cover the Notice of Claim
of Lien. . . .
33. Admitted.
34. Denied.
35. Denied.
. . . .
38. It is admitted that the unpaid amount of
[defendant's] contract with Smith is
$243,713.00 and that [defendant] has
retained this amount.
On 26 September 2002, plaintiff filed a motion for summary
judgment, alleging defendant was liable to [plaintiff] in the
amount of $113,655.00 as a result of its payments to Smith . . . on
July 6, 2001 and August 1, 2001. Plaintiff submitted the
affidavit of Smith's former project manager Timothy Bingaman, who
estimated the cost to complete the project to be approximately
$40,000.00.
Defendant also filed a motion for summary judgment dated 9October 2002, stating it had retained approximately $243,713.00 and
that it was not obligated to pay plaintiff because the cost to
complete the project unfinished by Smith would exceed the amount
otherwise owed to Smith. In August 2001, Smith breached its
contract with defendant, and refused to pay plaintiff the amount
owed under Smith's contract with plaintiff. At this point in time
the project remained unfinished, and defendant was forced to
complete the project and resolve existing problems. In support of
its motion, defendant submitted the affidavit of its vice president
Drew Beringer, who stated:
Toward the end of August 2001, Smith abandoned
the Project, forcing [defendant] to undertake
completion of the Project at significant
additional expense. To date, [defendant] has
received estimates from Langbein Engelbracht
America that it will cost approximately
$415,360.00 to complete the Project as called
for in the contract between [defendant] and
Smith and to correct defective work by Smith.
This is $171,647 greater than the amount to be
paid to Smith under its prime contract.
The trial court granted summary judgment to plaintiff, denied
defendant's motion for summary judgment, and ordered defendant to
pay plaintiff $113,655.00 plus interest and attorney's fees.
*** Converted from WordPerfect ***