An unpublished opinion of the North Carolina Court of Appeals does not constitute controlling legal authority. Citation is disfavored, but may be permitted in accordance with the provisions of Rule 30(e)(3) of the North Carolina Rules of Appellate Proced
ure.
NO. COA03-1074
NORTH CAROLINA COURT OF APPEALS
Filed: 17 August 2004
ETHEL ROSA and
GAYLE GRAZIANO,
Plaintiffs,
v
.
Clay County
No. 01 CVS 81
JAMES WILLIAM LONG,
Defendant.
Appeal by plaintiff from judgment entered 4 October 2002 by
Judge James U. Downs in Clay County Superior Court. Heard in the
Court of Appeals 19 May 2004.
Jones, Key, Melvin & Patton, P.A., by Fred H. Jones and Camila
J. Wright, for the plaintiffs.
McKinney & Tallent, P.A., by Zeyland G. McKinney, Jr., for
defendant.
TIMMONS-GOODSON, Judge.
Ethel Rosa and Gayle Graziano (plaintiffs) appeal a jury
verdict and award in favor of James William Long (defendant) on
a claim of breach of contract. For the reasons stated herein, we
hold that the trial court committed no error.
The evidence at trial tends to show the following: In June of
1999, plaintiffs entered into a written contract with defendant, a
licensed general contractor, to build a log cabin house in Clay
County, North Carolina. The contract provided that defendant would
build the house for the sum of $193,662.60. The contract further
provided that defendant would receive a ten percent commission
based on the cost of building the house. Plaintiffs obtained abuilding loan and established a bank account from which defendant
was to make scheduled withdrawals to pay for construction.
Building of the log cabin commenced in August of 1999.
During construction, plaintiffs requested modifications to the
original plans. These modifications, in addition to an increase in
the cost of building materials, drove the building cost above
$193,662.60. The bank account containing the funds from the
building loan was depleted by February of 2000 and plaintiffs
informed defendant that they would pay him directly thereafter.
In April of 2000, plaintiffs visited the construction site and
defendant informed them that he was due $20,363.41 for his work.
Defendant stated that he would not finish the project until he was
paid. Plaintiffs subsequently moved into the house before
construction was complete. Plaintiffs completed the work on the
house themselves and filed the underlying complaint against
defendant for breach of contract.
During the pretrial discovery phase, plaintiffs filed a
Request for Admissions pursuant to N.C. Gen. Stat. § 1A-1, Rule 36
that included a request that defendant admit that the contract was
for a fixed price. On 17 December 2001, defendant's attorney
mistakenly responded affirmatively to the request. The request and
response were as follows:
1. Admit that the Contract between you and
Plaintiffs was a fixed price contract.
ANSWER: It is admitted that the initial
contract was for a fixed price.
In all other discovery documents, defendant maintained that the
contract was not a fixed price contract. Immediately before trial,
defendant filed a motion seeking relief from the admission. The
trial court granted the motion.
Contemporaneously, plaintiff filed a motion for summary
judgment, citing the erroneous admission as proof that there was no
genuine issue of material fact with regard to the nature of the
contract. As a result of the court's ruling on defendant's motion
requesting relief from admissions, the trial court found there was
sufficient evidence to establish a genuine issue of material fact
and subsequently denied plaintiff's motion for summary judgment.
The trial court also denied plaintiffs' motion in limine, which
sought to exclude evidence tending to show that the contract at
issue was other than for a fixed price, thus allowing such
evidence to be presented to the jury. After hearing evidence from
both parties, the trial court presented six questions to the jury,
which the jury answered as follows:
1. Did the plaintiffs and [] defendant enter
into [the contract] with the intention that it
was a fixed-price contract for the
construction of the plaintiff's house?
Answer: NO
2. If so, did the defendant breach his
agreement with the plaintiffs?
Answer: [not applicable]
3. What amount of damages are the plaintiffs
entitled to recover from the defendant?
Answer: [not applicable]
4. Did the plaintiffs and the defendant enter
into [the contract] with the intention that it
was a cost-plus contract for the construction
of the plaintiffs' house?
Answer: YES
5. If so, did the plaintiffs breach their
agreement with the defendant?
Answer: YES
6. What amount of damages is the defendant
entitled to recover from the plaintiffs?
Answer: $20,294.67
Plaintiffs filed motions for directed verdict, judgment
notwithstanding the verdict and for new trial. The trial court
denied all of the motions and entered judgment for defendant.
Plaintiffs appeal.
__________________________________________________________
The issues on appeal are whether the trial court erred by (I)
denying plaintiffs' motion in limine; (II) denying plaintiffs'
motion for summary judgment; (III) denying plaintiffs' motions for
directed verdict and judgment notwithstanding the verdict; (IV)
denying plaintiffs' motion for a new trial; (V) permitting the jury
to interpret the contract; and (VI) allowing defendant's motion for
relief from answers to plaintiffs' requests for admissions.
Plaintiffs first argue that the trial court erred by denying
plaintiffs' motion in limine to exclude evidence showing the
contract was not for a fixed price. We disagree.
A ruling on a motion in limine is within the sound discretion
of the trial court and will only be disturbed on appeal in the case
of a manifest abuse of discretion. State v. Hightower, 340 N.C.735, 746-47, 459 S.E.2d 739, 745 (1995). Such a motion operates to
exclude anticipated prejudicial evidence before such evidence is
actually offered in the hearing of a jury. Id. at 746, 459 S.E.2d
at 745. A motion in limine may be granted to prevent the jury
from ever hearing the potentially prejudicial evidence thus
obviating the necessity for an instruction during trial to
disregard that evidence if it comes in and is prejudicial. State
v. Tate, 300 N.C. 180, 182, 265 S.E.2d 223, 225 (1980).
Plaintiffs' motion in limine sought to exclude any evidence
that demonstrated that the contract was other than a fixed price
contract. A fixed price contract is a contract in which the buyer
agrees to pay the seller a definite and predetermined price
regardless of increases in the seller's cost or the buyer's ability
to acquire the same goods in the market at a lower price. Black's
Law Dictionary 345 (8th ed. 2004). A cost plus contract is a
contract in which payment is based on a fixed fee or a percentage
added to the actual cost incurred. Black's Law Dictionary 344
(8th ed. 2004).
On the issue of contract interpretation this Court has held as
follows:
If the language of a contract is clear and
only one reasonable interpretation exists, the
courts must enforce the contract as written
and cannot, under the guise of interpretation,
rewrite the contract or impose [terms] on the
parties not bargained for and found within
the contract. If the contract is ambiguous,
however, interpretation is a question of fact,
and resort to extrinsic evidence is
necessary[.] An ambiguity exists in a
contract if the 'language of a contract is
fairly and reasonably susceptible to either ofthe constructions asserted by the parties.'
Thus, if there is any uncertainty as to what
the agreement is between the parties, a
contract is ambiguous. This Court's review
of a trial court's determination of whether a
contract is ambiguous is de novo.
Crider v. Jones Island Club, Inc., 147 N.C. App. 262, 266-67, 554
S.E.2d 863, 866-67 (2001) (citations omitted), disc. rev. denied,
356 N.C. 161, 568 S.E.2d 192 (2002).
In the case sub judice, there is ambiguity in the language of
the contract. The contract reads, in pertinent part:
[T]he CONTRACTOR agrees to construct a single
family dwelling on the OWNER'S lot, subject to
the specifications attached hereto . . . for
the sum of $193,662.60 which constitutes the
costs of construction of a log home subject to
the specifications of the OWNER'S plan
attached hereto . . . which includes a 10%
allowance for changes.
. . . .
CONTRACTOR is to receive a commission for
supervisory services rendered in connection
with construction
as previously noted at 10%.
The ten percent to be calculated on all
materials so purchased and paid for by
CONTRACTOR, ten percent of the subcontracts
obtained by CONTRACTOR, and ten percent of
all labor expended in construction of said
house[]. The remainder of the contract price
shall be paid upon the completion, finishing
and acceptance of all required work, labor,
services and materials according to the
specifications, drawings, and terms of this
agreement.
. . . .
This is a turn key job and all work and
expenses of any sort to the construction
. . . shall be paid by the CONTRACTOR.
(emphases added).
The contract's first provision asserts that defendant agrees
to build the log home for the sum of $193,662.60 . . . which
includes a 10% allowance for changes. This suggests that the
contract is a fixed price contract because the language suggests an
ultimate sum to cover the total cost of the project. The use of
the term turn key job further supports the proposition that this
is a fixed price contract. A turn key job is one in which the
contractor agrees to complete the work of building and
installation to the point of readiness for operation or occupancy.
Webster's New International Dictionary 2468 (3d ed. 1966); See also
Black's Law Dictionary 1555 (8th ed. 2004).
However, the contract later asserts that defendant is to
receive a ten percent commission in addition to the $193,662.60
price of the project. This provision conflicts with the definition
of a fixed price contract, which includes the contractor's fee or
commission in the price of the project.
For these reasons, the contract can be reasonably interpreted
as a fixed cost contract or as a cost plus contract. Therefore,
the question of interpretation becomes one of fact for the jury.
See Crider v. Jones Island Club, Inc., 147 N.C. App. 262, 266-67,
554 S.E.2d 863, 866-67, disc. rev. denied, 356 N.C. 161, 568 S.E.2d
192 (2002). We conclude that the trial court properly determined
that the language of the contract was ambiguous and therefore did
not abuse its discretion in denying plaintiffs' motion in limine to
exclude all evidence of the contract as a cost plus contract. Plaintiffs next argue that the trial court erred in denying
their motion for partial summary judgment with respect to the issue
of whether the contract was for a fixed price. We disagree.
Summary judgment is appropriately granted where the pleadings,
depositions, and other documentary evidence show that no genuine
issue of material fact exists and that any party is entitled to
judgment as a matter of law. Lynn v. Burnette, 138 N.C. App. 435,
437-38, 531 S.E.2d 275, 278 (2000). The burden to demonstrate the
absence of a triable issue lies with the moving party, and can be
accomplished by one of two means: (1) by showing that an essential
element of the opposing party's claim is nonexistent; or (2) [by]
demonstrating that the opposing party cannot produce evidence
sufficient to support an essential element of the claim or overcome
an affirmative defense which would work to bar [their] claim.
Wilhelm v. City of Fayetteville, 121 N.C. App. 87, 89, 464 S.E.2d
299, 300 (1995)(citation omitted). In deciding whether summary
judgment is proper, the trial court must consider the evidence in
the light most beneficial to the non-moving party, drawing all
inferences from the evidence against the moving party and in favor
of the nonmovant. Schmidt v. Breeden, 134 N.C. App. 248, 251-52,
517 S.E.2d 171, 174 (1999).
In the case sub judice, plaintiffs seek partial summary
judgment declaring that the contract is a fixed price contract. As
we concluded supra, the language of the contract is ambiguous.
Furthermore, taking into consideration all the pleadings, answers
to requests for admissions and answers to interrogatories, werecognize that with the exception of the answer to request for
admission mistakenly answered by defendant's attorney, defendant
maintained in all his pretrial documents that the contract was a
cost plus contract. Therefore, taking all the evidence on this
issue in a light most favorable to the plaintiff, we hold that
there existed genuine issues of material fact. Thus, the trial
court did not err by denying plaintiffs' motion for partial summary
judgment.
Plaintiffs next argue that the trial court erred in denying
plaintiffs' motions for directed verdict and judgment
notwithstanding the verdict. We disagree.
A motion for judgment notwithstanding the verdict is a renewal
of an earlier directed verdict motion; therefore, the same standard
of review applies to both motions. Norman Owen Trucking v.
Morkoski, 131 N.C. App. 168, 172, 506 S.E.2d 267, 270 (1998). When
reviewing motions for directed verdict and judgment notwithstanding
the verdict, the trial court must determine whether the evidence,
considered in the light most favorable to the non-moving party, is
sufficient to present the case to the jury. Id. The motion
should be denied if there is more than a scintilla of the evidence
supporting each element of the non-movant's claim. Id. A
directed verdict should not be granted when conflicting evidence
has been presented on contested issues of fact. Ace Chemical Corp.
v. DSI Transports, Inc., 115 N.C. App. 237, 242, 446 S.E.2d 100,
103 (1994). In considering a motion for directed verdict, the
trial court does not decide upon the weight or credibility of theevidence, but instead maintains the sole duty of determining
whether sufficient evidence is present upon which the jury could
base a verdict. Benfield v. Costner, 67 N.C. App. 444, 449, 313
S.E.2d 203, 207 (1984).
Upon review of the evidence, we conclude that there is more
than a scintilla of evidence supporting defendant's claim that the
contract is a cost plus contract. Although we note that plaintiffs
presented evidence that the contract is a fixed price contract, the
weight and credibility of the evidence is a matter for the jury to
decide. Thus, the trial court did not err in denying plaintiffs'
motions for a directed verdict and for judgment notwithstanding the
verdict.
Plaintiffs next assign error to the denial by the trial court
of a new trial based on three contentions: (1) the trial court
erred by failing to conclude that the contract at issue was
unambiguously for a fixed price; (2) the trial court erred when it
permitted defendant to withdraw his admission; and (3) the jury
verdict was contrary to law, because it allowed defendant to
recover on his counterclaim despite the evidence that the contract
unambiguously provided for a fixed price. We disagree.
Rule 59(a) of the Rules of Civil Procedure permits a trial
court to grant a new trial where the trial court finds [e]rror in
the law occurring at the trial and objected to by the party making
the motion . . . [or] insufficiency of the evidence to justify the
verdict or that the verdict is contrary to law. N.C. Gen. Stat.
§ 1A-1, Rule 59(a)(7), (8) (2003). Our review of a ruling denyinga motion for a new trial is limited to determining whether the
trial court abused its discretion. Pittman v. Nationwide Mutual
Fire Ins. Co., 79 N.C. App. 431, 434, 339 S.E.2d 441, 444, disc.
rev. denied, 316 N.C. 733, 345 S.E.2d 391 (1986).
Plaintiff's first and third bases for a new trial are grounded
in the argument that the trial court erred by finding the language
of the contract clear and unambiguous. Having concluded supra that
the trial court did not err in finding that the language was
ambiguous, we conclude that the trial court did not abuse its
discretion in denying plaintiffs' motion for a new trial on these
theories.
As discussed infra, the court did not abuse its discretion in
granting defendant's motion to withdraw admissions. Therefore,
plaintiffs' argument that the trial court should grant a new trial
based on this theory is also overruled.
Plaintiffs next argue that the trial court erred by permitting
the jury to interpret the contract and conclude that it was not a
fixed price contract. We disagree.
If the contract is ambiguous, however, interpretation is a
question of fact, and resort to extrinsic evidence is necessary[.]
Crider v. Jones Island Club, Inc., 147 N.C. App. 262, 266-67, 554
S.E.2d 863, 866 (2001)(citatoins omitted), disc. rev. denied, 356
N.C. 161, 568 S.E.2d 192 (2002). If [the] contract is ambiguous,
effect is for [the] jury. Root v. Insurance Co., 272 N.C. 580,
590, 158 S.E.2d 829, 837 (1968)(quoting Williams v. Insurance Co.,
209 N.C. 765, 771, 185 S.E. 21, 24 (1936)). As discussed supra, we conclude that the trial court correctly
determined that the contract language was ambiguous. Therefore,
the interpretation of the contract becomes a question of fact and
the trial court properly permitted the jury to interpret and answer
the question. We conclude the trial court did not err in
permitting the jury to interpret the contract.
Plaintiffs' final argument is that the trial court erred by
allowing defendant's motion for relief from answers to plaintiffs'
requests for admissions. We disagree.
Rule 36 of the Rules of Civil Procedure governs Requests for
Admissions and provides, in pertinent part, that [a]ny matter
admitted under this rule is conclusively established unless the
court on motion permits withdrawal or amendment of the admission.
N.C. Gen. Stat. § 1A-1, Rule 36(b) (2003). The trial court will
permit withdrawal or amendment of an admission if the presentation
of the merits of the action will be subserved and if the non-
moving party fails to demonstrate that withdrawal or amendment will
prejudice him in the maintenance of his action or its defense on
the merits. N.C. Gen. Stat. § 1A-1, Rule 36(b) (2003). The
standard of review of a trial court's decision to amend or withdraw
a party admission is abuse of discretion. Whitley v. Coltrane, 65
N.C. App. 679, 681, 309 S.E.2d 712, 715 (1983).
In the case sub judice, defendant's lawyer inadvertently and
erroneously responded affirmatively to a request for admission that
the contract in question was a fixed price contract. Defendant
filed a written motion for the trial court to withdraw theadmission. Defendant argued in the motion that due to the
inadvertent nature of the response and the remaining portions of
defendant's deposition which contradict the erroneous admission,
justice would be served and plaintiffs would not be prejudiced by
withdrawal of the admission.
Plaintiffs argue that the withdrawal prejudiced them because
it was made on the eve of the trial and therefore left them no
time to revise their strategy. Defendant's official statements in
all other documents establish defendant's position that the
contract was a cost plus contract and not a fixed price contract.
Defendant's Answer and Counterclaim to the Complaint denied the
allegation that the contract was for a fixed price. Defendant's
written answers to plaintiffs' interrogatories described the
contract in cost plus terms and during his deposition defendant
maintained this position.
With the exception of a mistake by his attorney, defendant
made it abundantly clear throughout the pretrial period that he
believed that his agreement with plaintiffs was a cost plus
contract. Thus, we conclude that the trial court did not abuse its
discretion in allowing the withdrawal of the admission. Therefore,
this assignment of error is overruled.
No error.
Judges McGEE and TYSON concur.
Report per Rule 30(e).
*** Converted from WordPerfect ***