Link to original WordPerfect file
Link to PDF file
How to access the above link?
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the
print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
HANDEX OF THE CAROLINAS, INC., Plaintiff, v. COUNTY OF HAYWOOD,
AND MUNICIPAL ENGINEERING SERVICES COMPANY, P.A., Defendants
NO. COA03-1658
Filed: 18 January 2005
1. Contracts_-professional negligence in performance of contract--failure to allege
contractual privity or intended third-party beneficiary--directed verdict
The trial court did not err by granting directed verdict in favor of defendant engineering
company on plaintiff's contract claims for professional negligence arising out of a contract for
the extension of a county landfill, because: (1) where there were no allegations of contractual
privity or that plaintiff was an intended third-party beneficiary under the professional contract,
plaintiff's exclusive remedy against the professional sounds in tort; and (2) plaintiff's complaint
does not allege privity of contract with defendant or that plaintiff was an intended third-party
beneficiary of the contract between defendant county and defendant engineering company.
2. Negligence--professional negligence--directed verdict
The trial court did not err by granting directed verdict in favor of defendant engineering
company on plaintiff's claim for professional negligence regarding the standard of care for a
civil engineer administering a landfill project, because: (1) the lay testimony of plaintiff's civil
engineer did not rebutt the relevant standard of care set out by defendant's expert civil engineer;
(2) viewed in its most favorable light, plaintiff's lay testimony established the witness's opinion
of what the administering engineer should have done in overseeing the bidding and contract
modifications requests and it does not show, as required to sustain the claim, what an engineer
practicing under the relevant standard of care actually does nor any specific instances of breach
of that relevant standard; and (3) the alleged breaches to the standard of care for administering
this landfill project, concerning the localized expectations and terms of art relating to excavation
and landfill construction, does not fall within the realm of a layperson's common knowledge and
experience.
3. Costs--depositions--mediation fees--witness fees--service of process fees for trial
subpoenas
The trial court's order in a general contract/tort based civil action awarding defendant
company costs under N.C.G.S. § 6-20 for depositions, mediation fees, witness fees, and service
of process fees for trial subpoenas is remanded for a modification to eliminate the award of
deposition costs, because: (1) costs under N.C.G.S. § 6-20 is limited to those items enumerated
in N.C.G.S. § 7A-305(d), and the trial court does not have discretion to award costs under
N.C.G.S. § 6-20 which are not enumerated; and (2) there is no statutory authority for the award
of deposition costs.
4. Contruction Claims--breach of contract--timeliness of notice to proceed with
construction
The trial court erred by failing to grant directed verdict in favor of defendant county for
contractual breaches that were not submitted to defendant engineering company as a claim for
contract modification regarding the extension of a landfill based on defendant county allegedly
causing delay in issuing the notice to proceed with the construction, because: (1) defendant
county gave timely notice under the terms of the bid and contract; and (2) there was no evidenceof breach of contract or claim made for a time extension due to the agreed change from
Alternative 1 to Alternative 2.
5. Contruction Claims--breach of contract--lost timber value
The trial court did not err by denying defendant county's motion for directed verdict for
contractual breaches that were not submitted to defendant engineering company as a claim for
contract modification regarding the extension of a landfill based on lost timber value on the
contract site based on the county clearing 20 acres of timber on the landfill site after the bids had
been accepted for the landfill and despite language in the contract that all timber shall become
property of the contractor, because: (1) the general conditions language of the contract is
ambiguous as to whether the question of whose property the timber was at the time of the clear
cutting falls withing the purview of a dispute or other matter relating to the acceptability of the
work or the performance of the work; and (2) the issue was properly presented to the jury when
any delay in the removal of the remaining stumps was proximately caused by this breach.
6. Contruction Claims--breach of contract--additional time and travel costs
The trial court erred by failing to grant defendant county's motion for directed verdict for
contractual breaches that were not submitted to defendant engineering company as a claim for
contract modification regarding the extension of a landfill based on additional time and travel
costs of defendant company's management, because: (1) as a condition precedent for raising
them in subsequent litigation, the costs should have been requested as part of a change order for
the work to which they were directly related; and (2) judging by the eight change orders sought
under this construction contract, defendant county had not waived the requirement of section
12.01 of the General Conditions that additional cost requests must be made through change
orders.
7. Construction Claims--lost timber revenue--rock removal and blasting--additional
time cost--undercutting of unsuitable soils
Claims arising from the construction of a landfill extension which were proper for the
jury to consider should have been limited to: (1) lost timber revenue from the county's clear-
cutting of the landfill site and damages related to stump removal; (2) evidence of the claim for
rock removal and blasting and related damages due to its denial of negotiating its price as stated
in Addendum 1 (change order #2); (3) evidence of additional time as authorized by the contract
for abnormal weather conditions which had occurred within the scope of the contract's time for
substantial completion and final payment (change order #3); and (4) undercutting of unsuitable
soils as approved by defendant company (change order #4).
8. Trials--motion for new trial--single-figure verdict
A new trial should be granted to determine both the question of liability and damages as
to the four claims for lost timber revenue, rock removal and blasting, additional time, and
undercutting of unsuitable soils, because in light of the single-figure jury verdict, it cannot be
determined whether the jury awarded damages pursuant to any of the four claims properly
submitted to the jury.
9. Damages and Remedies--liquidated damages--substitute for actual damages
While liquidated damages may still be awarded even if no actual damages arise from the
breach, they cannot be awarded in addition to actual damages because it would constitute double
recovery. Therefore, at any new trial, the liquidated damages provision of the pertinent contractshall be deemed as a substitute for any actual damages suffered by defendant county due to
plaintiff company's delay.
10. Damages and Remedies_-alteration of verdict--liquidated damages--monies retained
by county
Without more evidence, the trial court did not have authority to alter the verdict so
substantially from the $16,000 sum the jury returned as a verdict to $137,107.60 that the trial
court interpreted as the amount withheld by defendant county over and above the jury's finding
of $16,000 liquidated damages. However, the question of liquidated damages and monies
retained by defendant county may again be argued and clarified since a new trial has been
granted on plaintiff company's remaining claims.
Appeal by plaintiff from order entered 17 April 2003 by Judge
James L. Baker, Jr., and appeal by defendant County of Haywood from
judgment entered 6 May 2003 by Judge James L. Baker Jr., in Haywood
County Superior Court. Heard in the Court of Appeals 14 September
2004.
Roberts & Stevens, P.A., by Sarah Patterson Brison Meldrum and
Walter L. Currie, for plaintiff appellant-appellee.
Jeffrey W. Norris & Associates, P.L.L.C., by Jeffrey W.
Norris, for defendant appellant-appellee County of Haywood.
Van Winkle, Buck, Wall, Starnes & Davis, P.A., by Philip J.
Smith and W. James Johnson, for defendant appellee Municipal
Engineering Services, Inc.
McCULLOUGH, Judge.
This appeal arises from the alleged breaches of duties owed by
all parties under a contract for the extension of an existing
landfill (the landfill or the project) site in the White Oak
section of Haywood County. The extension was to create a new
landfill cell, approximately ten acres in surface area, to meet the
County's solid waste disposal needs. Parties to the appeal are:
County of Haywood (County), who solicited bids and then was
contractually bound for the additional excavation of the landfill;Handex of the Carolinas, Inc. (Handex), who upon submitting the
lowest bid was awarded the contract for the project by the County
(the contract); and Municipal Engineering Services (MES), who
was contracted by the County to provide a number of engineering
services related to the bidding and performance of the project (the
County-MES contract). Due to a number of problems arising from
the performance of the contract, Handex brought suit against MES
for professional negligence and breach of contract, and against the
County for breach of contract. The County counterclaimed for breach
of contract.
The Facts
I. The Bidding Process
The County-MES contract consisted of the following engineering
services: providing design services, reviewing and obtaining lump-
sum bids, administering contract performance, and reviewing and
advising on change orders by the contractor. For the project, MES
prepared the contract documents and specifications along with the
lump-sum bid advertisement, instructions to bidders, and the bid
form. This was made part of the contract. The bids were based on
certain specifications, specifically that the site work for the
project consisted of approximately 160,000 cubic yards of spoil,
excavation, compaction, tests, waste disposal, berm construction,
etc. The bid form and instructions called for a base bid portion,
plus bids on Alternative 1 (utilizing a clay liner) and Alternative
2 (utilizing a synthetic liner). Handex was the low bidder for both
alternatives and was awarded the contract for Alternative 1, as
notified by letter 14 September 2000. In that letter, MES informedHandex that Notice to Proceed was expected for 21 September 2000,
after a Permit to Construct had been issued by North Carolina Waste
Section (NCWS). MES informed Handex that a preconstruction
meeting was required to be held.
II. Notice to Proceed
The preconstruction meeting was held with NCWS in mid-October
2000. The record indicates NCWS had recently modified their
requirements, and was then allowing liner systems like that in the
County's advertised bid as Alternative 2. Handex's bid for
Alternative 2 was $8,960.00 less than their bid for Alternative 1.
Testimony of the County Manager, Mr. Jack Horton (Mr. Horton),
asserted that Handex insisted on Alternative 2, and that the
contract had to be re-awarded. Mr. Horton testified further that
he believed that the County accepted Alternative 2 because
Alternative 2 would actually be a lot quicker and shorten the time
of construction as compared to Alternate 1. Handex's
representative at the preconstruction meeting testified that it was
an open discussion upon which Alternative 2 was generally
decided. Alternative 2 was bid for a total lump-sum price of
$2,272,343.61. The County and Handex entered into a written
contract for the base bid work and Alternative 2 on or about 13
October 2000. In a letter dated 8 November 2000, MES gave Handex
Notice To Proceed as of 13 November 2000.
III. Implementation of the Contract
The contract provided Handex 180 days from the Notice to
Proceed to achieve Substantial Completion on the landfill, and 45
days from Substantial Completion to be ready for Final Payment. The date of Substantial Completion was to be 12 May 2001 and Final
Completion 45 days thereafter. If Handex did not complete within
those times, the contract allowed the County to retain $1,000.00
for each day Handex was late in reaching Substantial Completion,
and $500.00 for each day until Final Completion. Under the
contract, these were to be assessed as liquidated damages should
Handex finish late, obligating the County to pay only the
difference of monies owed under the contract upon Final Completion.
Handex completed the work 93 days beyond the Substantial Completion
date, and 10 days beyond Final Completion.
The contract contained three sections: the General Conditions
section, the General Specifications section, and the Project
Specifications section. The Project Specifications section covers
only requirements differing from what appears in the General
Specifications section. The contract required that, if Handex
desired to make a claim during the course of the project as to one
of its terms, or a Change Order for time or money, these claims
would be submitted to MES. Section 9.09 of the General Conditions
states in pertinent part:
A. ENGINEER will be the initial
interpreter of the requirements of the
Contract Documents and judge of the
acceptability of the Work thereunder. Claims,
disputes and other matters relating to the
acceptability of the Work, the quantities and
classifications of Unit Price Work, the
interpretation of the requirements of the
Contract Documents pertaining to the
performance of the Work, and Claims seeking
changes in the Contract Price or Contract
Times will be referred initially to ENGINEER
in writing, in accordance with the provisions
of paragraph 10.05, with a request for a
formal decision.
B. When functioning as interpreter and
judge under this paragraph 9.09, ENGINEER will
not show partiality to OWNER or CONTRACTOR and
will not be liable in connection with any
interpretation or decision rendered in good
faith in such capacity.
Section 10.05 of the General Conditions of the contract provided:
A. Notice: Written notice stating the
general nature of each Claim, dispute, or
other matter shall be delivered by the
claimant to ENGINEER and the other party to
the Contract promptly (but in no event later
than 30 days) after the start of the event
giving rise thereto. Notice of the amount or
extent of the Claim, dispute, or other matter
with supporting data shall be delivered to the
ENGINEER and the other party to the Contract
within 60 days after the start of such event.
During the course of the project construction, there were
eight attempts made to modify or change the contract terms or
specifications. Of these, the County and MES approved only one,
and MES recommended another be modified which was denied by the
County. Handex appealed each of the seven denials by the County.
Additionally, under the terms of the contract, Handex took issue
with the delayed start time of the project, additional expenses
absorbed by Handex in finishing the project, and timber removal
from the project site by the County.
III. Litigation/Judgment/Issues on Appeal
On 21 December 2001, Handex filed a complaint initiating this
action against MES for professional negligence and breach of
contract and against Haywood for breach of contract. MES filed
their answer 8 March 2002. The County filed their answer and a
counterclaim seeking to recover the agreed upon amount for
liquidated damages under the contract and engineering fees from
Handex. A trial was held 7-17 April 2003. At the close of all
evidence, MES and the County moved for directed verdict pursuant to
N.C. Gen. Stat. § 1A-1, Rule 50(a) (2003). The trial court granted
a directed verdict in favor of MES, dismissing all claims against
MES with prejudice. In a later order, the trial awarded MES
costs in the amount of $6,919.17. Handex appealed both of these
orders.
At the close of all evidence, the trial court denied the
County's motion for directed verdict. The court also denied the
County's request that the jury be given a detailed verdict sheet,
and instead allowed the jury a single figure verdict sheet. This
verdict sheet also provided for the award of liquidated damages and
engineering costs to the County. The jury rendered a verdict
against the County for breach of contract and awarded Handex
damages. The judgment entered by the court ordered the County to
pay the following: $201,928.41 for the damages of the breach of
contract, less $1.00 in damages Handex could have avoided; and,
$137,107.60 of monies owed to Handex under the contract, as this
figure was the difference between the $153,107.60 retained by the
County as liquidated damages and the $16,000.00 the jury actually
awarded. The County filed a motion for judgment notwithstanding
the verdict (JNOV), a motion to amend the judgment, or in the
alternative, a motion for a new trial. These motions were denied in
an order by the trial court. The court further awarded Handex
costs. The County appealed.
Additional evidence, facts, and relevant contract provisions
are raised as necessary in the legal analysis below.
Handex's Appeal
In their appeal, Handex raises two issues: Handex argues that
the trial court erred in granting a directed verdict in favor of
MES; and that the court erred in awarding MES costs. We address
these in turn.
I. Directed Verdict in Favor of MES
A. Standard of Review
When ruling on a motion for a directed verdict, the trial
court must consider the evidence in the light most favorable to the
nonmovant, taking the evidence supporting the nonmovant's claims as
true with all contradictions, conflicts, and inconsistencies
resolved in the nonmovant's favor so as to give the nonmovant the
benefit of every reasonable inference. Newton v. New Hanover County
Bd. of Education, 342 N.C. 554, 563, 467 S.E.2d 58, 65 (1996). 'On
appeal the standard of review for a JNOV . . . is the same as that
for a directed verdict,' requiring the issue be presented to a
jury if there is more than a scintilla of evidence to support each
element of the nonmovant's primae facie case. Kearns v. Horsley,
144 N.C. App. 200, 207, 552 S.E.2d 1, 6, disc. review denied, 354
N.C. 573, 559 S.E.2d 179 (2001)(citations omitted).
B. Handex's Claims
In the case at bar, Handex brought claims for breach of
contract and breach of professional negligence against MES.
1. Contract Claims
[1] For Handex to survive a directed verdict motion for its
contract claims against MES for professional malpractice, Handex
was required to present beyond a scintilla of evidence eitherprivity of contract with MES and elements of contractual breach, or
that Handex was an intended third party beneficiary of the County-
MES contract, of which Handex was denied its intended benefits due
to some breach by MES.
Leary v. N.C. Forest Prods., Inc., 157 N.C.
App. 396, 404, 580 S.E.2d 1, 6, aff'd per curium, 357 N.C. 567, 597
S.E.2d 673 (2003). In Leary, we clarified the divisions of this
somewhat convoluted area of professional malpractice claims,
stating that where there is neither allegations of contractual
privity, or that the plaintiff was an intended third-party
beneficiary under the professional contract, that plaintiff's
exclusive remedy against the professional sounds in tort. Id. See
also Davidson and Jones, Inc. v. County of New Hanover, 41 N.C.
App. 661, 667, 255 S.E.2d 580, 584, disc. review denied, 298 N.C.
295, 259 S.E.2d 911 (1979) (where we held that an architect, in the
absence of privity of contract, may be sued by a general contractor
for breach of an architect's common law duty of due care in the
performance of his contract with the owner, but that neither the
general contractor nor a subcontractor could maintain a cause of
action alleging negligent performance of the architect's contract
with the County).
There were two contracts in play governing the landfills
construction: the County-MES contract, where MES was to provide
various engineering services to the County for the landfill
project; and the contract between the County and Handex for the
excavation work and construction of the landfill.
Handex's complaint does not allege privity of contract with
MES, nor that Handex was the intended third-party beneficiary ofthe County-MES contract. Their complaint refers only to the terms
set forth in Article 9 of the County-Handex contract, and alleges
as a contractual claim that, [t]he Engineer has breached its
contractual duties owed to Handex under the Contract. The
Contract being referred to is the County-Handex contract. Handex
alleges its contractual claims stem from Section 9.09(B) of the
County's contract with Handex, as set out above. Without providing
more, we do not believe this is sufficient to find contractual
privity between Handex and MES, nor is it sufficient for Handex to
raise a claim as a third-party beneficiary under the County-MES
contract.
Therefore, we need not consider the evidence supporting
Handex's breach of contract theory, as we find no basis for MES's
liability to Handex sounding in contract. The trial court was not
in error in granting directed verdict on this issue.
This assignment of error is overruled.
2. Professional Negligence
[2] To survive a motion for directed verdict on a claim of
professional negligence, Handex was required to present more than
a scintilla of evidence for each of the following elements: (1)
the nature of MES's profession; (2) MES's duty to conform to a
certain standard of conduct; and (3) a breach of the duty
proximately caused injury to Handex. See Greene v. Pell & Pell
L.L.P., 144 N.C. App. 602, 604, 550 S.E.2d 522, 523 (2001); see
also, Davidson & Jones, Inc., 41 N.C. App. at 667, 255 S.E.2d at
584. At issue in this appeal is whether Handex provided sufficient
evidence of the relevant standard of care for a professional civilengineer akin to that applied by MES, and whether or not MES
breached that standard.
The standard of care provides a template against which the
finder of fact may measure the actual conduct of the professional.
The purpose of introducing evidence as to the standard of care in
a professional negligence lawsuit 'is to see if this defendant's
actions lived up to that standard[,]' and generally this is
established by way of expert testimony. Associated Indus. Contr'rs,
Inc. v. Fleming Eng'g, Inc., 162 N.C. App. 405, 410, 590 S.E.2d
866, 870 (2004)(quoting Little v. Matthewson, 114 N.C. App. 562,
567, 442 S.E.2d 567, 570 (1994), aff'd per curiam, 340 N.C. 102,
455 S.E.2d 160 (1995)). Implicit in the expert's establishment of
the professional standard of care as the baseline for the jury, is
that by way of establishing that standard the expert can assist the
jury in discerning whether defendant's professional performance or
conduct did not conform therewith, and thus was in breach of that
duty and the proximate cause of plaintiff's injury. The only
exception to the requirement of establishing the professional
standard of care by way of expert testimony is where the common
knowledge and experience of the jury is sufficient to evaluate
compliance with a standard of care[.] Delta Env. Consultants of
N.C. v. Wysong & Miles Co., 132 N.C. App. 160, 168, 510 S.E.2d 690,
695, disc. review denied, 350 N.C. 379, 536 S.E.2d 70 (1999). The
common knowledge exception to the requirement of expert testimony
in professional negligence cases is implicated where the conduct is
gross, or of 'such a nature that the common knowledge of lay
persons is sufficient to find the standard of care required, adeparture therefrom, or proximate causation.' Little, 114 N.C.
App. at 568, 442 S.E.2d at 571 (quoting Bailey v. Jones, 112 N.C.
App. 380, 387, 435 S.E.2d 787, 792 (1993)).
In the case at bar, Handex offered the lay testimony of the
Vice-President of Handex's operating divisions, Mr. Gary Conway
(Mr. Conway). Mr. Conway was a licensed civil engineer in the
State of Texas. In light of his experience on approximately 50 to
100 landfill projects, he testified to what he believed was
misleading information as to the quantity of excavation in the bid
advertisement and subsequent contract ambiguities for the County
landfill. He testified as to each contract modification request,
and certain instances where he believed MES was insufficient in
administering the request. Later, Handex put on MES's expert Mr.
Bill Lapsley (Mr. Lapsley), over MES's objection, to establish
the standard of care. MES had subpoenaed Mr. Lapsley to rebut any
expert or other evidence Handex might have called to establish the
relevant standard of care and breach thereof. During Handex's
examination, it was established that Mr. Lapsley was a registered
professional civil engineer in North Carolina, licensed since 1974.
Particularly, Mr. Lapsley was familiar with the methods and
peculiarities of earth work in Western North Carolina, and that he
was familiar with the standard of care of licensed engineers who
design and observe construction for the purpose of administering
contracts for these earth work jobs. On cross-examination by MES,
Mr. Lapsley stated: I can see no violations of the standard of
care that this engineer did, that I would have done the same thingthat this engineer did. I found no flaws in his response and how he
handled the situation.
We believe the testimony of Mr. Conway neither rebuts nor
raises more than a scintilla of evidence that MES breached the
relevant standard of care set out by Mr. Lapsley. Viewed in its
most favorable light, Mr. Conway's testimony established his
opinion of what the administering engineer should have done in
overseeing the bidding and contract modifications requests. It does
not show, as is required to sustain the claim, what an engineer
practicing under the relevant standard of care actually does, nor
any specific instances of breach of that relevant standard.
Furthermore, we cannot find that the alleged breaches to the
standard of care for administering this landfill project,
concerning the localized expectations and terms of art relating to
excavation and landfill construction, fall within the realm of a
layperson's common knowledge and experience. Delta Env. Consultants
of N.C., 132 N.C. App. at 168, 510 S.E.2d at 695-96.
Thus, Handex
failed to carry the elements of a primae facie case for
professional negligence upon which a jury could find MES in breach
of its duty and directed verdict was proper.
This assignment of error is overruled.
II. Costs
[3] MES's motion for costs in this case was made pursuant to
N.C. Gen. Stat. § 6-21 (2003), and it was under this authority the
court awarded fees. A reading of N.C. Gen. Stat. § 6-21 reveals
this statute does not authorize costs for the general contract/tort
based civil action at bar. However, this was not raised inHandex's responsive motion on the issue, nor was it specifically
assigned as error in this appeal. As both parties argue this issue
in their briefs as if the court awarded costs under N.C. Gen. Stat.
§ 6-20 (2003), and because the court had authority to do so under
that provision, we will frame our analysis in conformance.
N.C. Gen. Stat. § 6-20 provides that: In other actions,
costs may be allowed or not, in the discretion of the court, unless
otherwise provided by law. In Department of Transp. v. Charlotte
Area Mfd. Housing, Inc., 160 N.C. App. 461, 469, 586 S.E.2d 780,
785 (2003), we determined:
[T]he language of N.C.G.S. § 6-20 states that
in other actions, costs may be allowed or
not, in the discretion of the court . . . .
By referring to other actions, section 6-20
apparently grants a trial judge discretion to
determine whether or not costs should be taxed
to a party in an action not specified in
sections 6-18 and 6-19. Thus, the discretion
granted is the discretion to allow costs, not
the discretion to judicially create costs. Put
differently, the word discretion qualifies
the word allowed, not the word costs.
We then held that costs, as intended by the legislature to be used
in N.C. Gen. Stat. § 6-20, is limited to those items enumerated in
N.C. Gen. Stat. § 7A-305(d) (2003).
Id. at 470, 586 S.E.2d at 785.
In short, the trial court does not have discretion to award costs
under N.C. Gen. Stat. § 6-20 which are not otherwise enumerated in
the exhaustive list set out in N.C. Gen. Stat. § 7A-305(d).
The following is an itemized list composing the $6,919.17
award of costs to MES: deposition costs of $1,980.61; half the
expert witness fee generated by Mr. Lapsey, totaling $4,612.34;
MES's portion of the mediation fee, totaling $300.00; service of
process fees for trial subpoenas, totaling $17.22. In light ofDepartment of Transp., we find statutory authority for the
following awards: mediation fees pursuant to N.C. Gen. Stat. § 7A-
305(d)(6); witness fees of Mr. Lapsley, an expert witness under
subpoena pursuant to N.C. Gen. Stat. § 7A-305(d)(1) and N.C. Gen.
Stat. § 7A-314 (2003); and service of process fees for trial
subpoenas, pursuant to N.C. Gen. Stat. § 7A-305(6). We find no
statutory authority for the award of deposition costs.
Therefore, the order awarding costs to MES must be modified to
eliminate the award of deposition costs.
Haywood's Appeal
In their appeal, Haywood County raises the following issues:
the County argues that the trial court erred in denying its motion
for directed verdict and its motion for judgment notwithstanding
the verdict (JNOV); that the court erred denying its motion to
amend the judgment, and in the alternative, its motion for a new
trial. Because we find the court should have granted directed
verdict on some of the claims submitted to the jury, and that the
judgment was based in part on an irregularity at trial not
clarified by the record, we grant a new trial in accordance with
the mandate set forth below.
I. Denial of Directed Verdict and JNOV
A. Standard of Review
Upon review of the trial court's denial of Haywood's motion
for directed verdict and JNOV, we apply that standard as set out in
Handex's appeal from MES's directed verdict.
B. Evidence of Handex's Claims against the County The County argues there was insufficient evidence to submit to
the jury the question of any of the numerous contractual breaches
alleged by Handex. These alleged breaches fall into two categories:
those not submitted to MES as a claim for a contract modification--
delay in the notice to proceed, lost timber value and related
delay, and additional time and travel of Handex's management; and
those claims submitted to MES for approval as contract
modifications--additional rock and other soil excavation,
additional liner, additional undercutting, and weather-related
delays.
1. Claims Not Submitted to MES
[4] The jury was allowed to consider claims first raised by
Handex in this litigation contending the County caused delay
issuing the Notice to Proceed the construction, and causing
damages to Handex. Section 2.02 of the bid provided the Bid will
remain subject to acceptance for (90) days after Bid opening[.]
The Supplemental Conditions provide, [t]he Contract Times will
commence to run on the day indicated in the Notice to Proceed. A
Notice to Proceed may be given at anytime within 60 days after the
Effective Date of the Agreement. Though the record is unclear,
the bid opening seems to have occurred sometime in late August of
2000. Within the 90-day time period, the County awarded Handex's
bid for Alternative 1 on or about 14 September 2000, and later
contracted with Handex on Alternative 2 on or about 13 October
2000.
In a letter dated 8 November 2000, MES gave Handex the
Notice To Proceed as of 13 November 2000. Therefore, this was
timely under the terms of the bid and contract, and there was noevidence of breach of contract or claim made for a time extension
due to the agreed change from Alternative 1 to Alternative 2. The
trial court erred in not granting directed verdict on this claim
for breach.
[5[ The next issue not formally raised as a claim under the
contract was related to timber ownership on the construction site.
The County, in preparation for the landfill, clear-cut 20 acres of
timber on the landfill site after the bids had been accepted for
the landfill. This was done despite section 1.01.1(d) of the
General Conditions, providing that all timber...shall become
property of the Contractor. We believe this to be a clear breach
by the County of this provision. The expected timber proceeds were
likely to be used by contractors to submit lower bids. The County
claims that Handex failed to preserve this claim by submitting it
as a formal claim to MES as provided by section 9.09 and that it
was untimely under section 10.05 of the General Conditions. We
disagree that these provisions preclude Handex's ability to later
litigate this claim for breach. We find the General Conditions
ambiguous as to whether the question of whose property the timber
was at the time of the clear cutting falls within the purview of a
dispute or other matter relating to the acceptability of the
work or the performance of the work as set out in section 10.05.
(Emphasis added.) Furthermore, because any delay in the removal of
the remaining stumps was proximately caused by this breach, that
issue was also properly allowed to be presented to the jury.
Therefore, the court was correct in allowing those issues involving timber removal to be determined by the jury, despite first being
raised in this litigation.
[6] Lastly, the jury was allowed to consider evidence of
claims related to additional management costs and travel time costs
caused by the County's alleged breach during the performance of the
contract. These costs were never sought by Handex as contract
modifications made through the change order process, and were
evidenced only by a description of the revised contract value in
one of Handex's numerous exhibits. The transcript reflects that
these additional travel and management costs were related to the
performance of obligations of the contract or attempted contract
modifications. Therefore, as a condition precedent for raising them
in subsequent litigation, they should have been requested as part
of a change order for the work to which they were directly related.
Judging by the eight change orders sought under this construction
contract, the County had clearly not waived the requirement of
section 12.01 of the General Conditions that additional cost
requests must be made through change orders. Therefore, we believe
evidence of these additional management and travel costs were
improperly submitted to the jury as evidence of damages, and hold
the trial court erred in not granting directed verdict on these
claims of breach.
2. Claims Submitted to MES as Change Orders
[7] The first change order denied by the County was change
order #2 requesting additional money and time for blasting and rock
excavation. At issue was the language of Addendum 1 to the
construction contract, stating that costs for removal of rockencountered in the excavation area would be negotiated at the time
of removal. However, Addendum 2, sealed by MES a day after
Addendum 1, states excavation material in the bid is
unclassified. Mr. Lapsley, the only expert witness before the
court, stated on cross-examination that unclassified meant the
contractor would not be paid for any particular type of material
they were removing. In response, Handex put on evidence that
showed that another bidder's inquiry of MES into the effect of
Addendum No. 2, it was recorded that [a]ddendum 2 _ rock will
still be paid for if encountered. Upon this conflicting evidence,
we believe Addendums 1 & 2, when read together, raise an ambiguity
in the contract and therefore provided a question to be properly
submitted to the jury. See Crider v. Jones Island Club, Inc., 147
N.C. App. 262, 266-67, 554 S.E.2d 863, 866-67 (2001), disc. review
denied, 356 N.C. 161, 568 S.E.2d 192 (2002) (Where we reaffirmed
the long-standing rule of contract interpretation that when a
contract is ambiguous, deciphering its potential interpretations is
for the jury). We note that no days should have been credited for
the rock excavation, as Addendum 1 clearly only allowed for
negotiation of cost, but not additional time.
Change orders #3 and #8 denied by the County both related to
the contract's provisions governing abnormal weather conditions.
Change order #3 sought additional time of 30 days due to poor
weather conditions.
The contract provided that abnormal weather
conditions were to be determined based upon the National Weather
Service's thirty-year average. The evidence before the jury
provided two different interpretations of what constituted the timeframe for measuring these conditions, thus affecting calculations
of whether it was above or below the National Weather Service's
thirty-year average. It was also unclear, as testified to by Mr.
Conway, whether the average was to consider days of rain, or
inches of rain, and where the statistical data for the weather
conditions was to be collected. We find this means of determining
abnormal weather conditions ambiguous. Therefore, for change
order #3, we believe there was sufficient evidence of an abnormal
weather condition as described in Handex's weather logs and data
to give the issue to the jury. However, concerning change order
#8's request for time and price adjustment, Handex's request for
$80,000.00 was not an offered remedy under the express contract
terms set out in section 12.05(A) of the General Conditions (an
equal amount of time lost due to [abnormal weather conditions is
the] exclusive remedy.
Handex was required to get insurance under
the contract to cover such costs pursuant to General Condition
5.06.
Furthermore, the contract clearly states that claims for
more time due to abnormal weather conditions would only be
considered when brought within the Contract Times as stated in
12.03 of the General Conditions. Their request, made 10 July 2001,
was well outside of the contract time. Therefore, the requests in
change order #8 was governed by the express terms of the contract
for which there was no issue of fact to be decided by a jury.
Change order #4 sought by Handex was for additional
undercutting of 2,532 cubic yards of unsuitable soils and
backfilling in the subgrade. Handex requested $17,121.60 with a
time extension of 14 calendar days. MES approved the request forexcavation of the unsuitable soils, though modifying it to allow
only 3 days and $13,470.24. The modification was made because the
contract specifications stated that cost of backfilling was already
included in the cost of excavation. Despite MES's recommendation,
the County denied the claim as authorized by MES, and Handex
appealed. Mr. Lapsley testified that he believed Handex was
entitled to the claims for time and money as modified by MES. We
believe that on this issue, in light of the fact MES approved the
change order as modified, there was more than a scintilla of
evidence upon which a jury was properly allowed to determine
whether the County had breached the contract denying the change
order as modified.
Change order #5 sought by Handex was for
$28,112.00 and 14
calendar days based upon a need for an increase in the liner area
square footage for the landfill phase. The bid for the liner
system was at the unit quantity of 448,000 square feet. The
contract states that payment will only be made for actual number
of units incorporated in the work, and that [m]easurement for
payment of the Composite Liner System...will be based on... the
plane whose boundaries are the anchor and liner extension
trenches, and the cost shall include an appropriate allowance for
seam overlap, wrinkles, expected wastage, slopes, irregular shapes,
etc. At trial, Mr. Lapsley's testimony provided that the
appropriate allowances should have been considered in the bid
itself, and, therefore, MES properly denied the change order. For
their change order, Handex attached a land survey stating that the
actual verified surface area of the landfill was 460,550 squarefeet for the clay liner, and 485,300 square feet for the membrane
liner surface area. We agree with Mr. Lapsley and the County. The
terms plane and expected wastage plainly indicated that the
liner area required for the landfill was a figure to be
incorporated into the bid, with the appropriate allowance to be
estimated in addition to the 448,000 square feet of the landfill's
plane. Therefore, we do not believe there was sufficient evidence
of breach to present this issue to the jury.
Change order #6 by Handex sought neither additional time nor
costs. Rather, they requested to take cover soil from the borrow
area outside the clearing limits without seeding or landscaping
the area. This was in express contravention of the terms of the
Project Specification section 3.03, requiring that in such
instances [r]eclamation, which will include but not be limited to
seeding and mulching...at the Contractor's expense. The court
erred in failing to grant directed verdict on this claim of breach.
Change order #7 sought by Handex was for the approval of
$196,655.00 and an additional 29 workdays. The basis of this
request was, by Handex's calculations, that they had encountered
38% more excavation and 92% more berm construction in the field
than was depicted in the bid and contract. We find the bidding
provisions incorporated in the contract and the relevant
contractual provisions govern this issue. Handex submitted a lump
sum bid, without using any local survey, for the amount and cost of
earth work it estimated the landfill project required. This figure
was 165,000 cubic yards, approximately 5,000 yards more than what
was estimated in the bid advertisement. The record indicates thatafter their low bid had been awarded, Handex later hired Mr. Randy
Herron, a local surveyor, to calculate the earth work quantities of
the project, based on the documents MES provided for the initial
bid. In the Instructions to the Bidder portion of the contract,
section 4.07 stated: It is the responsibility of the Bidder before
submitting a Bid to: Obtain and carefully study (or assume
responsibility for doing so) all additional supplemental
examinations...which may affect cost, progress, or performance...
and to agree at the time of submitting its Bid that no further
examinations...are necessary for the determination of its bid for
performance. Moreover, when Handex discovered the earth work was
more significant than they had bid, instead of halting excavation
and putting the County and MES on notice as required by the General
Conditions section 4.03 of the contract, they continued to
excavate. In sum, in addition to not doing their due diligence
during the bidding process, Handex did not comply with General
Conditions requiring they halt excavation when making a claim that
the site differs materially from that represented in the bid and
contract. Therefore, the trial court should have granted directed
verdict on the claim of additional excavation because the County's
denial of Handex's claim was authorized under the terms of the
contract and made without breach. On facts akin to those at bar, we
affirmed a trial court's grant of JNOV on the seasoned principle of
construction/contract law:
[t]hat plaintiff encountered
difficulties which it failed to anticipate when making its bid did
not entitle it to the increased compensation it now seeks to
recover.
Brokers, Inc. v. Board of Education,
33 N.C. App. 24, 30, 234 S.E.2d 56, 60, disc. review denied, 293 N.C. 159, 236
S.E.2d 702 (1977)
C. Summary of Claims for Which Directed Verdict was
Improper
In this case, the evidence of claims which was proper for the
jury to consider should have been limited to the following: (1)
lost timber revenue from the County's clear-cutting of the landfill
site and damages related to the stump removal; (2) evidence of the
claim for rock removal and blasting and related damages due to its
denial of negotiating its price as stated in Addendum 1 (change
order #2); (3) evidence of additional time as authorized by the
contract for abnormal weather conditions which had occurred
within the scope of the contract's time for Substantial Completion
and Final Payment (change order #3); and lastly (4) undercutting of
unsuitable soils, as approved by MES (change order #4).
II. Denial of Motion for Amended Judgment/New Trial
[8] The County also motioned for a new trial and amended
judgment pursuant to N.C. Gen. Stat. § 1A-1, Rule 59(a)(7) (2003).
The County argued that, because some, if not all, of Handex's
claims were not supported by the evidence and therefore that the
single-figure verdict awarded by the trial court was not
authorized, a new trial must be granted. We agree.
Rule 59(a)(7) of the North Carolina Rules of Civil Procedure
provides that grounds for a new trial may be when [i]nsufficiency
of the evidence to justify the verdict or that the verdict is
contrary to law. N.C. Gen. Stat. § 1A-1, Rule 59(a)(7) (2003).
An appellate court's review of a trial judge's discretionary
ruling denying a motion to set aside a verdict and order a newtrial is limited to a determination of whether the record clearly
demonstrates a manifest abuse of discretion by the trial judge.
Pittman v. Nationwide Mutual Fire Ins. Co., 79 N.C. App. 431, 434,
339 S.E.2d 441, 444, disc. review denied, 316 N.C. 733, 345 S.E.2d
391 (1986). A new trial as to damages only should be ordered if the
damage issue is separate and distinct from the other issues and the
new trial can be had without danger of complication with other
matters in the case. Robertson v. Stanley, 285 N.C. 561, 568-69,
206 S.E.2d 190, 195 (1974). It must be clear that the error in
assessing damages did not affect the entire verdict. Id. If it
appears the damages awarded were from a compromise verdict, a new
trial on damages alone should not be ordered. Weyerhaeuser Co. v.
Supply Co., 292 N.C. 557, 566, 234 S.E.2d 605, 610 (1977).
As set out above, we have determined those claims raised by
Handex which were properly submitted to the jury, and those claims
which were clearly governed by the terms of the contract. In light
of the single-figure jury verdict, we cannot determine whether the
jury awarded damages pursuant to any of the four claims properly
submitted to the jury, and we are therefore constrained to grant a
new trial to determine both the question of liability and damages
as to these four claims. Weyerhaeuser Co., 292 N.C. at 566, 234
S.E.2d at 610 (where the Supreme Court modified this Court's grant
of a new trial on the issue of damages relating to counterclaims
under a contract, and granted a new trial on the question of
liability as well).
[9] Also at issue in this appeal is the propriety and amount
of liquidated damages and extra engineering fees awarded to theCounty by the jury's verdict. The County, under the terms of the
contract, began retaining liquidated damages for the days Handex
was overdue for Substantial Completion, at $1,000.00 per day, and
overdue for Final Payment, at $500.00 per day. In addition, the
County retained amounts it attributed to extra engineering fees
caused by Handex's delay. In total, the monies held by the County
at the time the jury rendered its verdict, including interest, was
approximately $153,107.60. The jury's verdict awarded the County
$16,000.00 in liquidated damages, and $8,880.00 for extra
engineering fees.
We first address the extra engineering fees. The trial court,
though allowing the jury to assess them for purposes of appellate
review, ordered that under North Carolina's jurisprudence the
County was not entitled to the engineering fees in addition to
liquidated damages. The trial court was correct in this ruling.
Our Supreme Court has long held that liquidated damages, when not
a penalty, may be awarded as both parties' measure of the
estimated, actual damages that would arise in the event of a
breach. Knutton v. Cofield, 273 N.C. 355, 363, 160 S.E.2d 29, 35-36
(1968). Therefore, while liquidated damages may still be awarded
even if no actual damages arise from the breach, they cannot be
awarded in addition to actual damages because this would constitute
double recovery. Id. Therefore, at any new trial, the liquidated
damages provision of the contract shall be deemed as a substitute
for any actual damages suffered by the County due to Handex's
delay.
[10] Turning next to the liquidated damages that were awarded
to
the County at trial. After the jury returned their verdict with
the $16,000.00 sum, the jury was discharged. Handex then raised
the following issue:
[HANDEX'S ATTORNEY]: I believe that
leaves us with the issue of the $160,000 or so
that the County is holding. I am assuming
that the answer to question number two is a
true damages award and is not inclusive of the
$160,000.
Handex's attorney at that time requested another question be
submitted to the jury as to whether the County was required to
return the difference of the monies it had retained as liquidated
damages and engineering fees, and the $16,000.00 awarded by the
jury. To this the court concluded:
THE COURT: ...If the plaintiff had the
money, then I can see that as creating a real
problem. I can't _ when you think about it
though, there's no way they could have
intended that the $201,000 be increased by the
money that [the County is] holding. It
wouldn't make sense that way.
The transcript from a subsequent hearing held before the trial
court issued its judgment was lost and is not part of the record on
appeal. There was, however, the affidavit of one juror expressing
what he alleged the verdict to encompass. Despite its initial
strict reading of the jury's verdict, in its judgment order, the
trial court interpreted the verdict to encompass $137,107.60 to be
recovered by Handex as the amount withheld by the County over and
above the jury's finding of $16,000.00 liquidated damages.
Vital to a party's right to a jury, when so requested, is the
verdict:
A verdict is a substantial right. A trial
judge in the due and orderly administration of
justice has the power to set a verdict asidein his discretion or as a matter of law, and
it is his duty to do so when a palpable
miscarriage of justice would result. The
ultimate objective of the law is to guarantee
justice to all the parties. A trial is the
process ordained and sanctioned for realizing
that objective. A jury in proper cases may
correct its verdict with the approval of the
court in the event the verdict does not
correctly express the actual agreement of the
jury.
Bundy v. Sutton, 207 N.C. 422, 427, 177 S.E. 420, 422 (1934). Our
courts have consistently held that the general rule prohibiting
jurors from impeaching their own verdict does not prevent the
reception of evidence from jurors on the issue of whether a
clerical error was made by the jury in recording their verdict.
Chandler v. U-Line Corp., 91 N.C. App. 315, 324-25, 371 S.E.2d 717,
722-23, disc. review denied, 323 N.C. 623, 374 S.E.2d 583 (1988).
In Chandler, we held that where the trial court sets aside or
amends a verdict pursuant to Rule 59 after the jury has been
discharged, there must be evidence that all jurors are in agreement
that the verdict sheet did not represent their intentions. Id.
In the case at bar, without more, we do not believe the court
had authority to alter the verdict so substantially. However,
because we are granting a new trial on Handex's remaining claims,
the question of liquidated damages and monies retained by the
County may again be argued and clarified.
Conclusion
The mandate of this opinion, based upon our thorough review of
the transcripts, record, briefs, and exhibits, is as follows: The
court's grant of directed verdict for MES is affirmed on the claims
of breach of contract and professional negligence. The court'saward of costs shall be amended to allow only those costs permitted
by statute. Concerning Handex's numerous contract claims against
the County, a new trial is appropriate for those four claims for
which there was sufficient evidence to survive directed verdict.
Additionally, concerning the County's counterclaims for breach and
liquidated damages, these too may be re-litigated. At any new
trial, there shall be clear instruction as to the following: that
any liquidated damages found under the contract cannot be increased
by actual damages proved at trial; and that the verdict specify
whether the amount of liquidated damages set by the jury is in lieu
of the $153,107.60 retained by the County with the balance to be
returned to Handex, or if it is an award of damages in addition to
those monies.
Affirmed in part, modified in part, reversed in part, and new
trial.
Judges TIMMONS-GOODSON and HUNTER concur.
*** Converted from WordPerfect ***