1. Public Works--state construction project--payment bond--materials supplied to
second-tier subcontractor
Defendants' motion for summary judgment was properly denied where plaintiff was
seeking payment for materials supplied to a second-tier subcontractor on a State Ports project.
The plain language of N.C.G.S. § 44A-25, which controls payment and performance bonds for
state construction contracts, includes first and second-tier subcontractors.
2. Estoppel--recovery of unpaid debt by subcontractor--timely notice
Plaintiff was not estopped from recovery of an unpaid debt for materials furnished to a
subcontractor on a State Ports project where plaintiff's notice to the prime contractor of the
subcontractor's failure to pay was timely given according to statutory requirements. The
Legislature instituted specific time limitations for notification to provide certainty for all parties
for claims upon a payment bond; less definite requirements for notification would create
uncertainty and undermine the statutory scheme.
3. Estoppel--defense of collusion--not affirmatively pled
Defendants waived the defense of estoppel by collusion by not affirmatively setting it
forth in their original or amended answer in an action to collect unpaid debts from material
furnished to a subcontractor on a State Ports project. Even if their position was properly
asserted, defendants did not show factual evidence that plaintiff acquiesced to false
representations by the subcontractor (there was no abuse of discretion in the exclusion of an
affidavit submitted less than two business days before the hearing).
4. Accord and Satisfaction--construction claim--debt specifically exempted
A defense of accord and satisfaction was properly rejected in a construction claim where
plaintiff specifically omitted this debt in the agreement.
5. Civil Procedure--summary judgment--continuance
There was no abuse of discretion in the denial of defendants' motion to continue a
summary judgment hearing on a State Ports construction claim.
Vann & Sheridan, L.L.P., by James W. Sprouse, Jr. and James R.
Vann, for plaintiff-appellee.
Brooks, Pierce, McLendon, Humphrey & Leonard, L.L.P., by
Michael D. Meeker, Clinton R. Pinyan, and Caroline R. Heil,
for defendant-appellants N.C. Monroe Construction Company and
Travelers Casualty & Surety Company of America.
HUNTER, Judge.
N.C. Monroe Construction Company (defendant-Monroe),
Travelers Casualty & Surety Company of America (defendant-
Travelers), and Diversified Fire Protection of Wilmington, Inc.
(defendant-Diversified) appeal from an order entered 15 December
2003 granting summary judgment to HSI North Carolina, LLC
(plaintiff) and denying summary judgment to defendants.
The issues in this case are whether the trial court erred in:
(1) granting summary judgment to plaintiff and denying summary
judgment to defendants as a matter of law, (2) finding plaintiff
was entitled as a matter of law to the awarded damages, (3) failing
to find plaintiff's claim was barred by equitable estoppel, (4)
rejecting defendants' defense of accord and satisfaction, and (5)
denying defendants' motion for continuance. As we find no error,
we affirm the trial court's decision.
On 10 June 2001, defendant-Monroe entered into a prime
contract with the North Carolina State Ports Authority for the
Transit Shed T-6 Expansion Project (Port Project). The Port
Project was bonded, as required by N.C. Gen. Stat. § 44A-26 (2003),by defendant-Travelers. Defendant-Monroe subcontracted with
defendant-Diversified to install a fire protection system for the
Port Project. Defendant-Diversified assigned the project to
another corporation also owned by the owner of defendant-
Diversified (Wilmington), for performance of the fire protection
installation. Wilmington, after approval of a credit application,
purchased materials needed for the project from plaintiff beginning
4 September 2001 and continuing until 10 January 2002. Plaintiff
was not paid by Wilmington for the materials. On 15 March 2002,
within 120 days of last furnishing materials, plaintiff gave
written notice to defendant-Monroe of the payment bond claim as
required by N.C. Gen. Stat. § 44A-27(b) (2003).
Plaintiff brought suit against defendants to recover payment
for materials used in the Port Project. After a period of
discovery, both parties moved for summary judgment. On 15 December
2003, the trial court granted summary judgment in plaintiff's
favor, awarded damages in the amount of $91,676.09 plus interest,
and denied defendants' motion for summary judgment. Defendants
appeal from this order.
Our Supreme Court has held that:
In resolving issues of statutory
construction, we look first to the language of
the statute itself. It is a well-established
rule of statutory construction that '[w]here
the language of a statute is clear and
unambiguous, there is no room for judicial
construction[,] and the courts must give [the
statute] its plain and definite meaning, and
are without power to interpolate, or
superimpose, provisions and limitations not
contained therein.'
Walker v. Bd. of Trustees of the N.C. Local Gov't. Emp. Ret. Sys.,
348 N.C. 63, 65-66, 499 S.E.2d 429, 430-31 (1998) (citations
omitted). Here, the language is clear and unambiguous. Thelegislature has specifically defined the term in question,
subcontractor, to include both individuals who have contracted to
provide materials directly to the contractor, as well as those who
have contracted with subcontractors, sometimes referred to as
first- and second-tier subcontractors, under the construction
contract. The language of § 44A-27, further, specifically provides
that a claimant who has a direct contractual relationship with any
subcontractor may bring an action on the payment bond. Id. By its
plain language, therefore, the statutory definition includes first
and second-tier subcontractors to the construction contract.
Here, plaintiff contracted to furnish materials to Wilmington,
a second-tier subcontractor, who had subcontracted with defendant-
Diversified, a first-tier subcontractor, to install the fire
protection system under defendant-Diversified's contract with
defendant-Monroe, the prime contractor. Under the statutory
definition in § 44A-25(6), defendant-Diversified qualifies as a
subcontractor, that is a party who had contracted to perform labor
for a contractor, defendant-Monroe, in connection with a
construction contract. Likewise, Wilmington also qualifies as a
subcontractor, that is a party who had contracted to perform labor
for a subcontractor, defendant-Diversified, in connection with a
construction contract.
(See footnote 1)
Plaintiff, therefore, under the plain
language of the statute, is a claimant with a direct contractualrelationship with a subcontractor, but with no contractual
relationship, express or implied, with the contractor. Thus, under
the terms of § 44A-27(b), plaintiff is entitled to bring an action
on the payment bond if notice to the contractor is given within the
requisite 120 days.
Defendants contend that as our courts have not previously
interpreted this provision of the Little Miller Act, federal
precedent must control. Such is not the case. Our courts have
previously noted that guidance can be obtained from federal
interpretations of the Miller Act, on which our corresponding state
act is modeled, but have not held such interpretations to be
binding. Syro Steel Co. v. Hubbell Highway Signs, Inc., 108 N.C.
App. 529, 534, 424 S.E.2d 208, 211 (1993). Further, in this case,
such federal precedent would be of no use. Unlike the federal
Miller Act, which provides no definition of subcontractor, MacEvoy
v. United States, 322 U.S. 102, 108, 88 L. Ed. 1163, 1168 (1944),
as noted supra, our state statute specifically defines
subcontractor in the context of the statute. N.C. Gen. Stat. §
44A-25(6).
As plaintiff has a statutory right to seek payment from
defendants under N.C. Gen. Stat. § 44A-27, we therefore find the
trial court did not err in denying defendants' motion for summary
judgment as a matter of law.
*** Converted from WordPerfect ***