Contracts_change_proposal specifications as estimates_no breach of good faith or implied
warranty
A summary judgment for defendant was affirmed in a breach of contract action which
arose when defendant reduced the distance a road was to be resurfaced, milled, and repainted
under this contract because of overlap with another contract. This change undermined
defendant's reliance on specifications in the bid proposal, particularly the amount of reclaimed
asphalt pavement the project would generate, and reduced its profit. However, the contract stated
that the amount of milling and resurfacing were subject to change as the project progressed, and
contract provisions concerning changes were not applicable. Claims of breach of good faith and
breach of defendant's implied warranty that plans and specifications were accurate were not
argued or supported in the brief, or were without merit.
Bugg & Wolf, P.A., by John E. Bugg and William J. Wolf, for
plaintiff-appellant.
Attorney General Roy Cooper, by Special Deputy Attorney
General Fred Lamar and Assistant Attorney General Steven
Armstrong for defendant-appellee.
ELMORE, Judge.
This case arises from the North Carolina Department of
Transportation's (DOT) decision to reduce the amount of necessary
construction under a contract it had with MAPCO, Inc. (MAPCO). On
1 December 2000 the DOT awarded a construction contract to MAPCO
for the milling, resurfacing, and placement of markings on two
sections of Highway 421 in Guilford County. The project was
centered in Division 7 of the DOT and under that division'sauthority. At a pre_construction meeting between the parties,
MAPCO was informed that the DOT was going to reduce the scope of
the contract due to the fact that a small portion of MAPCO's
project was going to overlap with one of the DOT's larger
projects__a project managed at the state level. In order to
prevent the overlap, MAPCO's 11.45 mile project was reduced by
6,900 linear feet, or 1.3 miles. MAPCO, however, had placed its
bid according to the specifications in the bid proposal, in
particular relying on the amount of reclaimed asphalt pavement
(RAP) the project was going to generate. Because of the cost
savings the proposed RAP would generate on the project and profit
made through the sale of the excess, MAPCO lowered its bid or
otherwise credited the DOT. The DOT's alterations in the project
were such that MAPCO would now not realize the gain it bargained
for from the $2,956,775.73 contract.
MAPCO pursued its administrative and statutory remedies
against the DOT without relief. Thereafter it filed suit against
the DOT on 22 May 2003 alleging breach of contract. MAPCO claimed,
in part, that:
14. At the time the project was bid, Mapco
relied to its detriment on the detailed plans
and specifications for the work. Further, at
the time the Department awarded the project to
Mapco, the Department was fully aware that a
portion of work was going to be deleted from
the project but did not inform Mapco of this
until after Mapco had allowed the Department
more than $100,000.00 credit for the material
to be recycled from the milling work as part
of its bid for the work. Mapco's bid
ultimately became part of the contract between
Mapco and the Department.
. . .
17. The Department breached its obligations to
Mapco by failing to adjust the contract amount
to return the value of the credit Mapco
allowed the Department in its bid for the
value of the milling materials.
The DOT denied MAPCO's allegations and also filed for summary
judgment. MAPCO, agreeing that there was no genuine issue of
material fact, also filed for summary judgment. The trial court
ordered summary judgment in favor of the DOT. MAPCO appeals.
Our review of an order for summary judgment is well
understood, see Lee v. R. & K. Marine, Inc., 165 N.C. App. 525,
526-27, 598 S.E.2d 683, 684 (2004), and while both parties agree
there is no genuine issue of material fact, each contends they were
entitled to summary judgment as a matter of law. Even while
viewing the facts in the light most favorable to MAPCO, however, we
agree with the trial court that the DOT was entitled to summary
judgment in its favor.
Included in the contract between the parties is the 1995
edition of the North Carolina Standard Specifications for Roads and
Structures (SSRS). Application of these specifications along with
other provisions within the parties' contract determine who shall
recover. See Teer Comp. v. Highway Commission, 265 N.C. 1, 13, 143
S.E.2d 247, 256 (1965).
It is noted that the statutory procedure is
available when the contractor has completed
his contract with the Highway Commission and
fails to receive 'such settlement as he claims
to be entitled to under his contract.' . . .
The procedure is to resolve any controversy as
to what (additional) amount, if any, thecontractor is entitled to recover under its
terms.
Id. (emphasis in original); see also Thompson-Arthur Paving Co. v.
N.C. Dept. of Transportation, 97 N.C. App. 92, 94, 387 S.E.2d 72,
73 (1990) (statutory recovery is limited to terms of contract and
this is the exclusive remedy); Teer Co. v. Highway Comm., 4 N.C.
App. 126, 142, 166 S.E.2d 705, 716 (1969) (In the absence of an
executed supplemental agreement, the parties are bound by the terms
of the Contract, and recovery, if any will be controlled by its
provisions.). Further, [w]here the provisions of a contract are
plainly set out, the court is not free to disregard them and a
party may not contend for a different interpretation on the ground
that it does not truly express the intent of the parties. Dixon,
Odom & Co. v. Sledge, 59 N.C. App. 280, 284, 296 S.E.2d 512, 514-15
(1982); Teer, 4 N.C. App. at 143, 166 S.E.2d at 716 (quoting 2
Strong's North Carolina Index 2d, Contracts § 12).
The parties' contract states that the amount of milling and
resurfacing are subject to change as the project progresses; in
other words, the figures provided by the DOT and used by MAPCO in
bidding on the project are estimates only.
The quantities shown in the itemized proposal
for the project are considered to be
approximate only and are given as the basis
for comparison of bids. The Department of
Transportation may increase or decrease the
quantity of any item or portion of the work as
may be deemed necessary or expedient.
An increase or decrease in the quantity of any
item will not be regarded as sufficient ground
for an increase or decrease in the unit
prices, nor in the time allowed for thecompletion of the work, except as provided for
the contract.
Despite this language, MAPCO contends that several of the
contract's provisions allow it to recover the lost offset against
the DOT.
First, MAPCO argues that the exclusion of 6,900 linear feet
from the project was an elimination of a contract line item.
Section 104-6 of the SSRS states the DOT may eliminate any item
from the contract, and such action will in no way invalidate the
contract. However, if the contractor has incurred expenses
related to the eliminated item, the contractor is entitled to a
reimbursement of costs. But this provision is not applicable to
the parties' dispute here. The DOT did not eliminate any contract
line item; rather, the DOT reduced the quantity of several line
items of work by shortening the distance of the overall project.
For instance, the DOT did not eliminate MAPCO's need to place a
yellow line marking on the highway, a line item in the contract; it
did, however, reduce the length that marking would need to be.
Second, MAPCO contends the DOT altered the tolerance (depth)
of the milling, and under section 612-4 of the SSRS it is entitled
to additional money. Section 612-4, entitled Tolerance,
addresses the depth a contractor shall mill the existing pavement
before resurfacing it.
Removal of the existing pavement shall be to
the depth required by the plans or project
special provisions. The Engineer may vary the
depth of milling by not more than one inch.
In the event the directed depth of milling per
cut is altered by the Engineer more than one
inch, either the Department of the Contractormay request an adjustment in unit price under
the provisions of Article 104-3.
MAPCO contends that since the depth of milling in the section
removed from the contract was altered from three inches to zero, it
is entitled to the offset. We cannot agree with the applicability
of this provision either. The plain language of the section
applies to alterations or variations in the depth of milling
pavement lengths that exist under the contract, not in offering an
offset when the contractor's distance of pavement to mill is
reduced by direction of the DOT. In fact, according to the record,
the tolerance of the milling in the contract did not vary, instead
36,800 square yards of three inch deep milling was removed from the
contract, along with every other aspect of work to be done to those
36,800 yards.
Third, MAPCO contends the DOT altered the construction plans
and materially changed the character and cost of the work it was
supposed to perform. Section 104-3 of the SSRS addresses these
concerns. This section generally states that if the DOT alters the
contract plans it shall not constitute a breach and the contractor
agrees to perform the work as altered for the original bid price.
But there is a notable conditional exception to this agreement: if
the altered plans or details 1) materially change the character of
the work and 2) materially change the cost of performing the work,
then an adjustment in price is warranted. An adjustment in the
affected contract unit or lump sum prices due to alterations in the
plans or details of construction that materially change the
character of the work and the cost of performing the work will bemade by the Engineer only as provided in this article. According
to this provision, absent a material change in character and cost,
there is no agreement to adjust the price.
MAPCO would have this Court ostensibly ignore the word
material, and instead read the contract to authorize an
adjustment in price any time there is an alteration in the plans.
Yet to do so would reverse the clear intent of this extensive
provision and place it in conflict with others throughout the
contract. See Reaves v. Hayes, 174 N.C. App. 341, 345, 620 S.E.2d
726, 729 (2005) (contract terms are to be harmoniously construed
and each word given effect) (quoting Gaston County Dyeing Machine
Co. v. Northfield Ins. Co., 351 N.C. 293, 299-300, 524 S.E.2d 558,
563 (2000)). Most importantly, MAPCO does not argue that the
deletion of 6,900 linear feet from the contract increased its cost
or materially changed the character of the work it performed.
Rather, MAPCO contends that [s]ince [its] bid price included a
credit for the value of the RAP that [it] was to receive under the
express terms and conditions of the parties Contract, the
Department owed [it] the value of those materials when the
Department changed its plans and took back much of the RAP [it] had
been promised.
But as stated earlier, the quantities in the contract were
estimates, and presumptively, if there was 1) a material change in
the plans or details, or 2) if a major contract item's quantity is
altered greater than fifteen percent, the SSRS, and thus the
parties' contract, allows for flexible adjustments. Outside theseprovisions, there is nothing in this contract or the record before
us that protects MAPCO's interest in the amount of RAP it would be
able to take away from the project had the estimates been actually
realized. Indeed, section 612-1 of the SSRS states: milled
material shall become the property of the Contractor. But there
is nothing to suggest, as the DOT points out, that this provision
entitles MAPCO to anything other than the material actually milled.
Fourth, MAPCO argues that when the DOT reduced the necessary
distance of the resurfacing project it breached the implied duty of
good faith. MAPCO acknowledges that the bid proposal contains
estimated quantities, but suggests that absent an error by the
Department in calculating the 'estimated quantities,' it is
virtually impossible to have any significant variations in those
quantities on a resurfacing project without an alteration to the
plans. MAPCO goes on to claim that the Department did just that,
alter the plans. However, alteration of construction plans is a
conceivable event and one that was specifically dealt with
throughout the contract. Although perhaps hinting that the DOT
acted in bad faith by allowing the estimates to be included in the
proposal while knowing them to be false, this claim is not
supported or argued in the brief.
Last, MAPCO argues that the DOT breached its implied warranty
as to the accuracy of the plans and specifications for the project.
We find this argument lacks sufficient merit. Thus, having
resolved that the trial court did not err in finding summary
judgment in favor of the DOT, we affirm its order.
Affirmed.
Judges McCULLOUGH and LEVINSON concur.
*** Converted from WordPerfect ***