How to access the above link?
Return to nccourts.org
Return to the Opinions Page
1. Eminent Domain_takings_sewer line easement_replacement system_not a separate
taking
There was not a separate taking in a sewer project where plaintiff installed a new leach
field, pipe and pump to replace a septic system rendered inoperable by a new permanent sewer
easement (the original taking). The installation of the new septic system did not necessarily flow
from construction of the improvement, but was an effort to accommodate defendants' need for a
new system, to which defendants consented.
2. Eminent Domain_takings_sewer line easement_replacement system_not an
additional taking_instruction on damages
There was no additional taking in a sewer project where plaintiffs built a new septic
system to replace a system rendered inoperable by the new sewer line easement, and no error in
the court's instruction that the jury could (rather than must) consider the condition of the old and
new systems.
3. Easements_sewer line_replacement system_costs born by owners
The owners must bear any costs in maintaining and operating a new pump-based septic
system installed to replace a gravity system rendered inoperable by a sewer line easement.
Plaintiff installed the new system for the owners' personal benefit, retained no ownership in the
new system, and the owners were the only ones directly benefitting.
Office of the City Attorney, by Assistant City Attorney
Catherine C. Williamson, for plaintiff-appellee.
The Odom Firm, PLLC, by T. LaFontine Odom, for defendants-
appellants.
CALABRIA, Judge.
Steven and Lorraine Long (Long), along with TRSTE, Inc.,
trustee, and Wachovia Bank, N.A., (known collectively as
defendants), appeal the 12 November 2004 order concluding the
City of Charlotte's (plaintiff) installation of a new septic
system including pump tank (pump), 400 feet of a 2-inch pipe
(pipe), and new leach field (field) was not an additional
taking of defendants' property for which defendants are entitled to
compensation. We affirm.
On 12 August 2003, pursuant to N.C. Gen. Stat. § 136-103,
plaintiff instituted an eminent domain action by filing a
complaint, declaration of taking, and notice of deposit of
$6,200.00 as either full compensation or as a credit against just
compensation. The plaintiff acquired a permanent sanitary sewer
easement and temporary construction easement across defendants'
property to install both an 8-inch gravity sewer line and a 16-inch
pressurized sewer force main for a development of homes.
The permanent easement ran through defendants' existing leach
field rendering their gravity septic waste disposal system
(disposal system) inoperable. Due to this consequence, plaintiff
hired a licensed soil scientist to determine suitable locations for
the installation of a replacement field for defendants' disposal
system. The defendants requested installation of a new field in a
wooded area 400 feet from the back of their home. Because the new
field, measuring approximately one and one-half times larger than
the original, was at a higher elevation than the defendants' home,
plaintiff had to install a pump out of defendants' front yard toremove waste from the home to the new field. In an area between
the newly installed pump and field, the plaintiff installed the
pipe. The pump, operated by electricity, was connected to the
defendants' electric panel. Plaintiff contracted with a third
party to perform this work and paid all costs associated with the
installation of the new septic waste disposal system.
On 20 July 2004, defendant filed an answer, responded to the
declaration of taking and notice of deposit, and counterclaimed for
inverse condemnation. Specifically, defendant alleged that in
addition to the permanent sewer easement and temporary construction
easement, plaintiff appropriated portions of defendants' property
outside the easements for the pump, pipe and field. On 28 July
2004, plaintiff replied to the counterclaim and denied
appropriating any further property of defendants.
On 23 September 2004, defendants filed a motion pursuant to
N.C. Gen. Stat. § 136-108 to ascertain whether plaintiff had taken
property outside the easements. On 12 November 2004, the trial
court determined plaintiff's installation of the pump, pipe, and
field outside the permanent and temporary easements failed to
constitute an additional taking of defendants' property for which
they were entitled compensation. In addition, in ascertaining just
compensation due defendants for the sewer and construction
easements, the trial court concluded the jury may consider the
effect of this taking on defendants' use of their property,
specifically the condition of their inoperable system and its
replacement. Defendants appeal. [1] Defendants first argue the trial court erred in concluding
the plaintiff's installation of the pump, pipe, and field did not
constitute an additional taking. Defendants contend such an
appropriation of land constituted inverse condemnation since the
damage to the land outside the easements was ineluctably tied to
the construction of both the sewer force main and sewer line. We
disagree.
Inverse condemnation, a cause of action against a
governmental defendant to recover the value of property which has
been taken in fact by the governmental defendant, even though no
formal exercise of the power of eminent domain has been attempted
by the taking agency, Charlotte v. Spratt, 263 N.C. 656, 662-63,
140 S.E.2d 341, 346 (1965) (internal citation and quotation marks
omitted), requires the following: (1) a taking (2) of private
property (3) for a public use or purpose. Adams Outdoor
Advertising of Charlotte v. N.C. Dep't of Transp., 112 N.C. App.
120, 122, 434 S.E.2d 666, 667 (1993). A taking, or entering upon
private property...devoting it to a public use, or...informally
appropriating or injuriously affecting it in such a way as
substantially to oust the owner and deprive him of all beneficial
enjoyment thereof, Ledford v. N.C. State Highway Comm'n, 279 N.C.
188, 190-91, 181 S.E.2d 466, 468 (1971), requires 'substantial
interference with elemental rights growing out of the ownership of
the property.' Adams, 112 N.C. App. at 122, 434 S.E.2d at 667
(quoting Long v. City of Charlotte, 306 N.C. 187, 198-99, 293
S.E.2d 101, 109 (1982)). Importantly, in order to illustrate ataking [a] plaintiff must show an actual interference with or
disturbance of property rights resulting in injuries which are not
merely consequential or incidental. Id. (emphasis added).
[A] municipality is solely liable for the damages that
inevitably or necessarily flow from the construction of an
improvement.... City of Winston-Salem v. Ferrell, 79 N.C. App.
103, 110, 338 S.E.2d 794, 799 (1986) (emphasis added). Thus,
[d]amages to land outside the easements which inevitably or
necessarily flow from the construction of the [improvement] result
in an appropriation of land for public use [to which] [s]uch
damages are embraced within just compensation to which defendant
landowners are entitled. Id.
Ferrell is instructive in determining what is and what is not
considered 'inevitably and necessarily' tied to the construction of
an improvement and thus compensable as a taking under inverse
condemnation. In Ferrell, a contractor entered defendant's
property and built a temporary roadway outside the already acquired
easements so as to haul in supplies for the project. Id. at 105,
338 S.E.2d at 796. The same contractor, also outside of the
prescribed easements, used another portion of defendant's property
as a staging area to store pipes and equipment. Id. This Court
determined that because the contractor's use of the roadway over
defendant's property was essential to provide access to the City's
sewer outfall construction site, ...such use thus necessarily
flowed from the construction of the improvement... . Id. at 112,
338 S.E.2d at 800 (emphasis added). Conversely, [u]nlike theevidence regarding the contractor's use of the roadway, the
evidence regarding its use of the staging area does not show that
such use was necessary to complete the project. Id. at 113, 338
S.E.2d at 800 (emphasis added). This Court holds plaintiff's
conduct clearly fails to amount to an additional taking and
plaintiff's action in the instant case was more like the staging
area in Ferrell, and less like the roadway.
Plaintiff's installation of the pump, pipe, and field on
defendants' property did not necessarily flow from construction of
the improvement, here the 8-inch sewer line and 16-inch sewer main
force. The installation was not part of the improvement project,
but rather the plaintiff's subsequent and separate effort to
accommodate defendants' need for a new septic system. In fact,
defendants consented to the installation of the new pump, pipe, and
field and plaintiff reciprocated by expending $16,000.00 to cover
the cost. Defendants incorrectly assert a separate taking has
occurred. This assignment of error is overruled.
[2] Defendants next argue the trial court erred in holding the
jury may consider the effect of the additional taking on
defendants' use of their residence. Specifically, defendants
contend the jury must consider the condition of their inoperable
gravity septic system and the replacement system installed by
plaintiff since plaintiff's actions constituted inverse
condemnation. We disagree.
N.C. Gen. Stat. § 136-112(1) (2005) provides as the proper
measure of damages for inverse condemnation [w]here only a part ofa tract is taken, the measure of damages for said taking shall be
the difference between the fair market value of the entire tract
immediately prior to said taking and the fair market value of the
remainder immediately after said taking... . (Emphasis added).
Furthermore, '[t]he fair market value of the remainder immediately
after the taking contemplates the project in its completed state
and any damage to the remainder due to the user [sic] to which the
part appropriated may, or probably will, be put.' Dep't. of
Transp. v. Bragg, 308 N.C. 367, 370, 302 S.E.2d 227, 229 (1983)
(quoting Bd. of Transp. v. Brown, 34 N.C. App. 266, 268, 237 S.E.2d
854, 855 (1977)).
In the instant case, a judge or jury determines the amount of
just compensation due defendants by calculating the difference
between the fair market value of defendants' entire tract prior to
the taking of both the permanent sanitary sewer easement and the
temporary construction easement, and the fair market value of the
remainder of defendants' property immediately after both the taking
of these easements and the completion of the project itself. This
calculation must include any potential damage caused to the
remainder of defendants' property due to the use of the easements.
The court determined the amount of just compensation due defendants
by measuring the damages for the taking of the sewer and
construction easements, not the installation of the new septic
system comprised of the pump, pipe, and field. In addition, we
note defendants argue that an additional taking occurred and the
effect of that additional taking upon the fair market value oftheir property must then be calculated. This premise was expressly
refuted above as no additional taking occurred. This assignment of
error is overruled.
[3] Defendants' remaining assignment of error is that the
trial court erred in finding that defendants alone would have to
bear the electrical as well as any maintenance and repair costs to
operate the newly installed pump. We disagree. Here, plaintiff
expended $16,000.00 to install a new pump, pipe, and field solely
for the Longs' personal benefit. The plaintiff retained no
ownership rights in this newly installed septic system. The only
individuals directly benefitting from this new septic system are
the Longs. Thus, any future electrical, maintenance or repair
costs must be borne by the actual owners of this new septic system,
the Longs. This assignment of error is overruled.
Affirmed.
Judges Hudson and Bryant concur.
*** Converted from WordPerfect ***