Link to original WordPerfect file
Link to PDF file
How to access the above link?
Return to nccourts.org
Return to the Opinions Page
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
STATE OF NORTH CAROLINA ex rel. UTILITIES COMMISSION, PUBLIC
STAFF - NORTH CAROLINA UTILITIES COMMISSION and PROGRESS ENERGY
CAROLINAS, INC., Appellees, v. JOHN W. WARDLAW, JR., MARTHA C. W.
STUHMER, THOMAS F. ROBERTS, JR., JOHN P. MEDLIN, FRANK B. MEDLIN,
WESTCHASE INVESTORS, L.L.C., CB WESTCHASE, INC., R. MICHAEL
CONDREY, JOSEPH H. LEVINSON and wife, THEODOSIA LOUISE LEVINSON,
WILLIAM T. SANDERS, JAMES R. LEVINSON and wife, GINGER T.
LEVINSON, JOSEPH LEE LEVINSON, ANN LEVINSON MUNDAY and husband,
CARL B. MUNDAY, NANCY L. EASON and husband, FRANK E. EASON,
CAMPBELL UNIVERSITY, INCORPORATED, SUSAN JONES DREHER and
husband, JAMES DREHER, and WALTON DAVID PARKER, JR. and wife,
LOIS C. PARKER, Appellants
NO. COA05-1481
Filed: 3 October 2006
1. Utilities_transmission line--preferred route--routing study
The Utilities Commission did not err by approving Progress Energy's final preferred
route for a transmission line as analyzed and recommended by Progress Energy's routing study,
because: (1) the Commission considered the evidence presented in Progress Energy's routing
study and at the public hearings on 9 November 2004 and 4 January 2005, including testimony of
three expert witnesses who testified to the merits of the preferred and approved route; (2) the
Commission made numerous findings regarding the preferred route; (3) the Court of Appeals'
review is limited to whether the Commission considered the factors required by law and whether
its findings are supported by competent, substantial, and material evidence in view of the whole
record; and (4) the Court of Appeals is not permitted to review the weight and credibility the
Commission gave, or substitute its judgment for the substantial evidence presented regarding the
preferred route, Progress Energy's routing study, or the future needs of the North Carolina State
University's School of Veterinary Medicine.
2. Utilities_transmission line--burden of proof--alternate route corridors--preferred
route
The Utilities Commission did not improperly place the burden of proof on intervenors to
show that one or more of Progress Energy's alternate route corridors for a transmission line was
superior to Progress Energy's preferred route and of Progress Energy's ability to cross the
alternate routes, because: (1) under N.C.G.S. § 62-105(a), the Commission properly assigned to
Progress Energy the initial burden of proving it had examined alternative routes and its preferred
route was reasonable and in the public interest; (2) after Progress Energy met this burden, the
Commission properly assigned to intervenors the burden of proving an alternate route studied by
the utility is preferable to that proposed or that the utility did not consider or appropriately weigh
relevant factors in reaching its decision; and (3) nothing in the record shows the Commission
failed to properly apply N.C.G.S. § 62-105(a).
3. Appeal and Error--preservation of issues--failure to cite authority
Although intervenors contend the Utilities Commission's approval of Progress Energy's
preferred route for a transmission line was arbitrary and capricious, this assignment of error is
dismissed, because: (1) intervenors failed to cite any authority in support of their argument; and
(2) it is not the role of the appellate courts to create an appeal for an appellant.
Appeal by appellants from order entered 8 April 2005 by the
North Carolina Utilities Commission. Heard in the Court of Appeals
15 August 2006.
Staff Attorney James D. Little, for appellee Public Staff-
North Carolina Utilities Commission.
Smith, Anderson, Blount, Dorsett, Mitchell & Jernigan, L.L.P.,
by James K. Dorsett, III, Dwight W. Allen, and Jackson Wyatt
Moore, Jr., for appellee Progress Energy Carolinas, Inc.
Crisp, Page & Currin, LLP, by Robert F. Page, for appellants.
TYSON, Judge.
John W. Wardlaw, Jr., Martha C. W. Stuhmer, Thomas F. Roberts,
Jr., John P. Medlin, Frank B. Medlin, Westchase Investors, L.L.C.,
CB Westchase, Inc., R. Michael Condrey, Joseph H. Levinson,
Theodosia Louise Levinson, William T. Sanders, James R. Levinson,
Ginger T. Levinson, Joseph Lee Levinson, Ann Levinson Munday, Carl
B. Munday, Nancy L. Eason, Frank E. Eason, Campbell University,
Incorporated, Susan Jones Dreher, James Dreher, Walton David
Parker, Jr., and Lois C. Parker (intervenors) appeal from the
North Carolina Utilities Commission's (the Commission) ordergranting Progress Energy Carolinas, Inc. (Progress Energy) a
Certificate of Environmental Compatibility and Public Convenience
and Necessity. We affirm the Commission's order.
I. Background
On 23 July 2004,
Progress Energy applied to obtain a
Certificate of Environmental Compatibility and Public Convenience
and Necessity to construct approximately 4.3 miles of 230 kilovolt
transmission line in Wake County pursuant to N.C. Gen. Stat. § 62-
100 and Rule 8-62 of the Rules and Regulations of the Commission
.
The proposed transmission line was required to energize a new
distribution substation to be constructed by Progress Energy on
Trenton Road in Cary, North Carolina. A document identified as
Routing Study and Environmental Report for the Trenton Road
Transmission Line Tap Project (routing study) was prepared to
determine the best path to route the new line. The routing study
identified 109 possible alternate routes for the line to energize
the substation. Progress Energy conducted private meetings with
public officials and meetings with the general public to evaluate
the suitability of the alternate routes. The public's input was
considered to select the rating categories and relative weights to
be assigned to the categories. Progress Energy selected the route
with the fourth best cumulative rating score. The Commission scheduled a public hearing on 9 November 2004.
Intervenors petitioned to intervene on 29 October 2004. The
Commission granted intervenors' petition on 3 November 2004 and
issued its order granting Progress Energy's request on 8 April
2005. Intervenors appeal.
II. Issues
Intervenors argue the Commission erred by: (1) approving the
final preferred route recommended by Progress Energy; (2) giving
favorable consideration to the Progress Energy routing study; (3)
relying on the alleged future needs of the North Carolina State
University's School of Veterinary Medicine in approving Progress
Energy's preferred route;
(4) placing the burden of proof on
intervenors to show one or more of the alternate route corridors
was superior over Progress Energy's preferred route and to show
Progress Energy could access the alternate route corridors; and (5)
issuing the order approving the preferred route, which is arbitrary
and capricious.
III. Standard of Review
N.C. Gen. Stat. § 62-105(a) (2005) mandates:
The Commission shall grant a certificate for
the construction, operation, and maintenance
of the proposed transmission line if it finds:
(1) That the proposed transmission line is
necessary to satisfy the reasonable needs ofthe public for an adequate and reliable supply
of electric energy;
(2) That, when compared with reasonable
alternative courses of action, construction of
the transmission line in the proposed location
is reasonable, preferred, and in the public
interest;
(3) That the costs associated with the
proposed transmission line are reasonable;
(4) That the impact the proposed transmission
line will have on the environment is justified
considering the state of available technology,
the nature and economics of the various
alternatives, and other material
considerations; and
(5) That the environmental compatibility,
public convenience, and necessity require the
transmission line.
N.C. Gen. Stat. § 62-94 (2005) provides the standard of review
for this Court:
The court may affirm or reverse the decision
of the Commission, declare the same null and
void, or remand the case for further
proceedings; or it may reverse or modify the
decision if the substantial rights of the
appellants have been prejudiced because the
Commission's findings, inferences, conclusions
or decisions are:
(1) In violation of constitutional provisions,
or
(2) In excess of statutory authority or
jurisdiction of the Commission, or
(3) Made upon unlawful proceedings, or
(4) Affected by other errors of law, or
(5) Unsupported by competent, material and
substantial evidence in view of the entire
record as submitted, or
(6) Arbitrary or capricious.
(C) In making the foregoing determinations,
the court shall review the whole record or
such portions thereof as may be cited by any
party and due account shall be taken of the
rule of prejudicial error. The appellant
shall not be permitted to rely upon any
grounds for relief on appeal which were not
set forth specifically in his notice of appeal
filed with the Commission.
Over twenty-five years ago, this Court stated:
[T]he Commission's order [should] be affirmed
if, upon consideration of the whole record as
submitted, the facts found by the Commission
are supported by competent, material and
substantial evidence, taking into account any
contradictory evidence or evidence from which
conflicting inferences could be drawn.
Substantial evidence is such relevant evidence
as a reasonable mind might accept as adequate
to support a conclusion.
. . . .
In the review of orders from the Commission by
this Court, our action is guided by N.C.G.S.
62-94, and where the Commission's actions do
not violate the Constitution or exceed
statutory authority, appellate review is
limited to errors of law, arbitrary action, or
decisions unsupported by competent, material
and substantial evidence. We look to the
findings of fact and conclusions of the
Commission and determine whether the
Commission has considered the factors required
by law and whether its findings are supported
by competent, substantial and material
evidence in view of the whole record.
Utilities Comm. v. Springdale Estates Assoc., 46 N.C. App. 488,
490-91, 265 S.E.2d 647, 649-50 (1980) (internal quotations and
citations omitted).
Ten years ago, this Court stated, When applying the whole
record test, the court may not replace the Commission's judgment
with its own when there are two reasonably conflicting views of the
evidence. State ex rel. Utilities Comm. v. Public Staff, 123 N.C.
App. 43, 46, 472 S.E.2d 193, 196 (1996).
IV. Preferred Route
[1] Intervenors argue the Commission erred when it approved
Progress Energy's final preferred route as analyzed
and recommended
by Progress Energy's routing study.
Intervenors contend the
preferred route was not one of the 109 alternate routes
studied by
Progress Energy. The record indicates the route approved was
studied and ranked as the fourth best route. Intervenors also
argue the Commission erred when it
gave favorable consideration to
Progress Energy's routing study
a
nd when it
relied on the alleged
future needs of the North Carolina State University's School of
Veterinary Medicine in approving Progress Energy's preferred route
.
Our Supreme Court has stated:
G.S. 62-26.3 requires: all final orders and
decisions of the Commission shall be
sufficient in detail to enable the court on
appeal to determine the controverted questions
presented in the proceedings and shall include(1) findings and conclusions and the reasons
or basis therefor upon all the material issues
of fact, law, or discretion presented in the
record, and (2) the appropriate rule, order,
sanction, relief, or statement of denial
thereof.
Utilities Com. v. Membership Corporation, 260 N.C. 59, 62, 131
S.E.2d 865, 867 (1963) (internal quotations and citations omitted).
Our Supreme Court has stated, The weighing of the evidence
and the drawing of the ultimate conclusion is for the Commission,
not the reviewing court. State ex rel. Utilities Comm. v. Public
Staff, 323 N.C. 481, 491, 374 S.E.2d 361, 367 (1998) (internal
quotations and citations omitted). This Court has stated, the
credibility and weight of testimony are matters to be determined by
the Commission. State ex rel. Utilities Comm. v. Village of
Pinehurst, 99 N.C. App. 224, 227, 393 S.E.2d 111, 113 (1990),
aff'd, 331 N.C. 278, 415 S.E.2d 199 (1992).
The record indicates the Commission considered evidence from
both Progress Energy and intervenors. The Commission's order
provides:
On November 9, 2004, a public hearing was
held in Raleigh. Ten non-Intervenor public
witnesses . . . presented the testimony . . .
of six witnesses.
On November 15, 2004, the Commission
issued an Order Rescheduling Evidentiary
Hearing and Establishing Dates for Prefiled
Testimony. On November 19, 2004, [Progress
Energy] filed direct testimony for SteveWilson, James Umbdenstock, and Chris Wood. On
December 3, 2004, the Intervenors filed direct
testimony for John W. Wardlaw, Jr. and Patrick
N. Connell, and direct testimony and exhibits
for Gregory L. Booth.
On January 4, 2005, an evidentiary
hearing was held in Raleigh. One public
witness, Ted Shear, appeared at the hearing
and testified. [Progress Energy] presented
the direct testimony, exhibits and rebuttal
testimony of Steve Wilson, James Umbdenstock,
and Chris Wood. The intervenors presented the
direct testimony and exhibits of Gregory L.
Booth, Patrick Connell, and John W. Wardlaw,
Jr.
James Umbdenstock, a Progress Energy engineer and responsible
for power distribution planning, testified regarding the necessity
for the construction of the transmission line and substation to be
located at Trenton Road. He stated:
The proposed substation and new 230-kV
line will relieve the overloading on the
existing distribution feeders and substation
and will provide the electric system
infrastructure necessary for the reliable
electric service required by the continuing
commercial development in the area.
Customer growth in population and
electric usage, due to proposed development
and expansion in this area, is expected to
place greater demands on the distribution and
transmission systems.
. . . .
This project will improve the power
quality and reliability in the area, and
reduce the frequency and duration of potential
power outages. Without the new substation,transmission line and related distribution
system upgrades, load in the area would exceed
the electric system capability in the near
future.
Steve Wilson, a Progress Energy Project Manager in the
transmission department, testified regarding the path or route
selection process for the proposed Trenton Road transmission line.
He testified:
After establishing the study area,
potential alternative routes were identified
for the project. The objective was to
identify the routes connecting the existing
Durham-Method 230-kV transmission line and the
proposed new Trenton Road 230-kV Substation
while avoiding or minimizing impacts to both
human and natural resources. Local, state and
federal government agencies were contacted to
gather information on new or proposed
developments and other constraints relevant to
the routing process. . . . If a serious
problem, such as a new home or business, was
identified along a route, adjustments were
made to the route to minimize the potential
impacts or the route was removed from
consideration.
. . . .
The preferred route received one of the
lowest (i.e., best) overall weighted scores of
all the proposed routes, indicating that it
would have one of the lowest overall impacts
on the human and natural environment.
Although the preferred route was not the top
scoring route, this route was selected over
the top three scoring routes because it avoids
traffic concerns.
Anthony Wood, a senior Environmental Scientist and Project
Manager for Burns McDonnell Engineering Company, testified
regarding the potential environmental impacts of the transmission
line. He testified:
The preferred route was selected because
it avoids planned development to the extent
feasible; provides a transmission source for
the planned new substation to serve the
growing load at the Centennial Biomedical
Campus and surrounding area; meets the overall
requirements of the State, which is the
largest landowner in the area, and the City of
Raleigh for land use in the area; uses
existing corridors for the majority of length;
and avoids environmentally sensitive areas.
The preferred route parallels existing
road right-of-way for over 50 percent of the
route, which reduces the required right-of-way
and minimizes impacts to agricultural land,
woodland and wetlands. Over two-thirds of the
length of the proposed route is on State
lands.
Based on the testimony and exhibits received at the hearing
and in Progress Energy's Application, including the Routing Study,
the Commission made the following findings of fact:
3. Current and projected electric load in the
West Raleigh-Cary area of Wake County
continues to grow. Over the last five years,
electrical demand in this area of Wake County
has grown at about 3.6 percent per year, or
approximately one and one-half times the rate
for most of [Progress Energy]'s service area.
The area surrounding the RBC Center has begun
to experience commercial development, and with
an abundance of vacant land adjacent to the
entertainment complex, growth is expected tocontinue over the next several years. Unless
[Progress Energy] constructs a new 230 kV
transmission line and substation in this area,
the demand for electricity will exceed the
capability of the existing facilities in the
West Raleigh-Cary area in the near future.
4. To determine the appropriate route for the
proposed transmission line, [Progress Energy]
analyzed numerous alternatives. Such analyses
consisted of identifying alternative routes,
gather public input and evaluating such routes
based upon their length and impact upon the
social and natural environment, existing homes
and businesses, and future development.
5. The most appropriate route for the new
transmission line is the preferred route
proposed by [Progress Energy] that originates
at a new substation to be located in the
southwest corner of the Wade Avenue,
Interstate 40 (I-40), and Trenton Road
Intersection and extends 4.3 miles to
[Progress Energy]'s existing Durham-Method
230kV transmission line, which runs in a
southeast-northwest direction northeast of
Reedy Creek Road. The proposed transmission
line will be located in the general vicinity
of I-40, Trinity Road and Blue Ridge Road.
. . . .
8. When compared with reasonable alternative
courses of action, construction of the
transmission line in the proposed location is
reasonable, preferred, and in the public
interest.
. . . .
10. The impact the proposed transmission line
will have on the environment is justified
considering the state of available technology,
the nature and economics of the variousalternatives, and other material
considerations.
In its Discussion of Evidence and Conclusions, the
Commission addressed the necessity of the proposed line and
objections to the preferred route. With regard to the necessity of
the proposed line, the Commission stated:
Construction of a new transmission line and
substation will provide the additional
capacity needed to reliably meet the long-term
electrical needs of the area and prevent
overloading of existing electrical supply
facilities. In addition, the proximity of the
new substation to the growing number of
customers in the area will result in shorter
distribution feeders, which will improve power
quality and reliability of service to
[Progress Energy]'s customers due to reduced
exposure to potential causes of disturbances
and outages.
With regard to intervenors'
objections to the preferred route,
the Commission considered community opinions and values relative
to the proposed project. The Commission considered Input []
first obtained through meetings with public officials and local
agencies, and then through public information meetings. Progress
Energy utilized several routing criteria to determine the best
route, including: (1) the residential proximity from each proposed
segment; (2) the number of commercial buildings near the line; (3)
the amount of land to be cleared; (4) the amount of wetlands to be
crossed; (5) the number of streams to be crossed; (6) thevisibility of the new line to the public; (7) the length of the
line; and (8) the number of heavy angles. The Commission held,
Based upon these factors (weighted as appropriate based upon
public input) and Progress Energy's experience in routing
transmission lines, Progress Energy chose the preferred route.
The Commission stated:
The preferred route was selected from over one
hundred routes considered for these reasons:
it avoids planned development to the extent
feasible; it provides a transmission source
for the planned new substation to serve the
growing load at the Centennial Biomedical
Campus and surrounding area; it meets the
overall requirements of the State (the largest
landowner in the area) and the City of Raleigh
for land use in the area; it uses existing
corridors for the majority of its length; and
it avoids environmentally sensitive areas.
The Commission also stated, [w]hile the preferred route does
not have the [best] score for all of the routing factors, most of
its values were among the best scores of all the routes. The
Commission concluded:
After careful consideration, the Commission
concludes that [Progress Energy] has
demonstrated that the proposed transmission
line is necessary for an adequate and reliable
supply of electric energy; that the proposed
location is preferred, and in the public
interest; that the costs associated with the
proposed transmission line are reasonable; and
that the environmental compatibility, public
convenience, and necessity require the
proposed line.
Intervenors' argument that there is not even a 'scintilla' of
evidence in the record to support Progress Energy's selection of
its 'preferred route' is without merit. The Commission considered
the evidence presented in Progress Energy's routing study
and at
the public hearings on 9 November 2004 and 4 January 2005,
including testimony of three expert witnesses who testified to the
merits of the preferred and approved route. The Commission
made
numerous findings regarding the preferred route
.
Intervenors have requested this Court to consider the weight
and credibility of the evidence before the Commission. Our review
is limited to whether or not the Commission considered the factors
required by law and whether its findings are supported by
competent, substantial and material evidence in view of the whole
record
. Utilities Comm. v. Springdale Estates Assoc., 46 N.C.
App. at 494, 265 S.E.2d at 651. Our standard of review does not
permit this Court to review the weight and credibility the
Commission gave, or substitute our judgment for, the substantial
evidence presented regarding the preferred route, Progress Energy's
routing study, or the future needs of the North Carolina State
University's School of Veterinary Medicine.
These assignments of
error are overruled.
V. Burden of Proof
[2] Intervenors argue the Commission improperly
placed the
burden of proof on them to show that one or more of Progress
Energy's alternate route corridors was superior to Progress
Energy's preferred route and of Progress Energy's ability to cross
the alternate routes
.
N.C. Gen. Stat. § 62-105(a) (2005) mandates, [t]he burden of
proof is on the applicant in all cases under this Article, except
that any party proposing an alternative location for the proposed
transmission line shall have the burden of proof in sustaining its
position.
Intervenors argue [i]nstead of requiring [Progress Energy] to
assume the 'burden' of proving that its 'preferred route' is best,
the Commission has, instead, improperly and unlawfully imposed a
'burden of proof' on the Intervenors/Appellants to demonstrate that
the Progress Energy 'preferred route' is not the best.
We
disagree.
Regarding Progress Energy's burden of proof, the Commission
quoted N.C. Gen. Stat. § 62-105(a) and applied its mandates to
Progress Energy's application. The Commission stated, [T]he
electric utility applying for approval to site a transmission line
has the initial burden of proof, including that it examined
'reasonable alternative courses of action' and that 'construction
of the transmission line in the proposed location is reasonable,preferred, and in the public interest.' The Commission concluded
Progress Energy had met its burden and granted it a Certificate of
Environmental Compatibility and Public Convenience and Necessity.
With regard to intervenors' burden of proof, the Commission
stated:
the burden of proof has not been met by the
Intervenors, as required by G.S. 62-105(a),
with regard to any alternative route for the
transmission line. The Intervenors have not
proven that any of their alternatives is
preferable to the proposed route, would
provide long-term reliable electric service to
the load in this high-growth area, or
satisfies NCSU's need for a future
transmission to distribution substation on
campus. The evidence presented by Intervenors
involved their opposition to the line being
placed upon their respective properties, or in
close proximity, and the allegation that
[Progress Energy] could use an alternate route
and thus avoid their properties. These issues
raised by the Intervenors are not relevant to
the Commission's determination of need. None
of the Intervenors presented any evidence on
the feasibility of cost consequences of their
proposals or the impact on other property
owners.
Pursuant to N.C. Gen. Stat. § 62-105(a)
, the Commission
properly assigned to Progress Energy the initial burden of proving
it had examined alternative routes and its preferred route was
reasonable and in the public interest.
After Progress Energy met
this burden, the Commission properly assigned to intervenors the
burden of proving an alternative route studied by the utility ispreferable to that proposed or that the utility did not consider or
appropriately weigh relevant factors in reaching its decision.
N.C. Gen. Stat. § 62-105(a)
. Nothing in the record shows the
Commission failed to properly apply N.C. Gen. Stat. § 62-105(a)
.
This assignment of error is overruled.
VI. Arbitrary and Capricious
[3] Intervenors argue the Commission's approval of Progress
Energy's preferred route is arbitrary and capricious.
N.C.R. App. P. 28(a) (2005) provides, The function of all
briefs required or permitted by these rules is to define clearly
the questions presented to the reviewing court and to present the
arguments and authorities upon which the parties rely in support of
their respective positions thereon. (emphasis supplied).
Intervenors have failed to cite any authorities upon which
[they] rely. Id
. It is not the role of the appellate courts .
. . to create an appeal for an appellant . . . the Rules of
Appellate Procedure must be consistently applied; otherwise, the
Rules become meaningless. Viar v. N.C. DOT, 359 N.C. 400, 402,
610 S.E.2d 360, 361 (2005). This assignment of error is dismissed.
VII. Conclusion
The Commission properly approved Progress Energy's final
preferred route. Under the controlling statute and our standard of
review, this Court's cannot weigh[] . . . the [credibility of the]evidence and . . . draw[] . . . the ultimate conclusion.
State ex
rel.
Utilities Comm.
v.
Public Staff, 323 N.C. at 491, 374 S.E.2d
at 367 (internal quotations and citations omitted).
The Commission did not improperly shift the burden of proof to
intervenors rather than to Progress Energy. N.C. Gen. Stat. § 62-
105(a). Intervenors fail to cite authority to support their
argument
that the Commission's final order is arbitrary and
capricious
in accordance with N.C.R. App. P. 28
. The Commission's
order is affirmed.
Affirmed.
Judges WYNN and HUDSON concur.
*** Converted from WordPerfect ***