Link to original WordPerfect file
Link to PDF file
How to access the above link?
Return to nccourts.org
Return to the Opinions Page
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the
print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
SCHENKEL & SHULTZ, INC. Formerly known as SCHENKEL & SHULTZ,
ARCHITECTS, P.A., Plaintiff, v. HERMON F. FOX & ASSOCIATES, P.C.,
Defendant
NO. COA 05-1604
Filed: 21 November 2006
1. Statutes of Limitation and Repose--negligence--professional malpractice--breach of
contract--breach of warranty
The trial court did not err by granting summary judgment in favor of defendant
engineering firm on plaintiff architectural firm's claims for negligence, professional malpractice,
breach of contract, and breach of warranty in the structural steel design for a school based on
expiration of the applicable three-year statute of limitations, because: (1) the date of the accrual
of a cause of action is deemed to be the date of discovery of the defective or unsafe condition of a
structure; (2) the discovery rule which sometimes operates to extend the statute of limitations is
intended to apply in situations where the injury becomes apparent only after some delay, or the
claimant might be somehow prevented from realizing the injury; and (3) plaintiff was promptly
notified of defendant's alleged negligence and malpractice and was on notice of a possible breach
beginning in the spring of 2001, and the 8 May 2001 and 9 August 2001 letters (indicating that
plaintiff knew or had reason to know of the harm done to the project and the resulting breach of
the underlying contract and warranty) fall outside of the three-year statute of limitations for the
direct claims alleged in its complaint filed on 1 October 2004.
2. Indemnity--express contract--summary judgment
The trial court erred by granting summary judgment in favor of defendant engineering
firm on plaintiff architectural firm's claim of a right to express contractual indemnity, because:
(1) viewing the evidence in the light most favorable to plaintiff, the record indicated that a
genuine issue of material fact remains as to whether the contract expressly provides, through its
incorporation by reference of a separate contract, for the right to indemnity; (2) when an
agreement is ambiguous and the intention of the parties is unclear, interpretation of the contract
is for the trier of fact like in this case where ambiguity remains as to the intention of the parties
with respect to indemnity; and (3) North Carolina follows the general rule that a cause of action
on an obligation to indemnity normally accrues when the indemnitee suffers actual loss, and
plaintiff filed its claim for indemnity before the school board instituted its action against plaintiff
for costs and damages incurred as a result of steel design errors with the action pending in federal
court, meaning the statute of limitations has not yet tolled against plaintiff for its claim for
indemnity against defendant.
3. Indemnity--implied-in-law--implied-in-fact--summary judgment
The trial court did not err by granting summary judgment in favor of defendant
engineering firm on plaintiff architectural firm's claims for indemnity implied-in-law or
indemnity implied-in-fact, because: (1) in the context of independent contractor relationships, a
right of indemnity under a contract implied-in-fact is inappropriate where, as here, both parties
are well-equipped to negotiate and bargain for such provisions; and (2) in regard to indemnity
implied-in-law, a party must be able to prove each of the elements of an underlying tort such as
negligence, and the record reveals no such evidence.
4. Contracts--breach--counterclaim--summary judgment
The trial court erred by granting summary judgment in favor of defendant engineering
firm on defendant's breach of contract counterclaim for payment allegedly due from plaintiff
architectural firm for defendant's design of the structural steel for a school because: (1) the
general rule regarding bilateral contracts provides that if either party to the contract is materially
in default with respect to performance of his obligations under the contract, the other party
should be excused from the obligation to perform further; (2) the record contained substantial
evidence that defendant's steel design was defective, including numerous letters offered as
exhibits that demonstrated various parties' concern with the structural integrity of defendant's
steel design; and (3) a genuine issue of material fact exists whether defendant breached its
contract with plaintiff by supplying a defective structural steel design for the project.
TYSON, Judge, concurring in part, dissenting in part
.
Appeal by Plaintiff from order entered 25 February 2005 by
Judge Forrest Donald Bridges and order entered 8 August 2005 by
Judge Timothy Kincaid in Superior Court, Mecklenburg County. Heard
in the Court of Appeals 22 August 2006.
Kennedy Covington Lobdell & Hickman, LLP, by Kiran H. Mehta
and Samuel T. Reaves, and Hamilton Martens Ballou & Sipe, LLC,
by Herbert W. Hamilton, for plaintiff-appellant.
Hamilton Moon Stephens Steels & Martin, PLLC, by David G.
Redding and Adrianne Huffman Colgate, for defendant-appellee.
WYNN, Judge.
A right to indemnity may rest on the express contractual
provisions between two parties and would therefore be triggered by
a breach of that contract.
(See footnote 1)
Because we find a genuine issue of
material fact remains as to whether the contract in this case did,
in fact, expressly provide for the indemnification of Plaintiff
Schenkel & Shultz, Inc. by Defendant Hermon F. Fox & Associates,P.C., we reverse the trial court's grant of summary judgment as to
Plaintiff's indemnity claim.
We further find that a genuine issue of material fact remains
as to whether Fox & Associates did, in fact, breach its contract
with Schenkel & Shultz, and also reverse as to Fox & Associates's
counterclaim. However, because we conclude that Schenkel & Shultz
knew or should have known of its injury more than three years
before filing its direct claims of negligence and professional
malpractice, breach of contract, and breach of warranty, we affirm
the trial court's grant of summary judgment in favor of Fox &
Associates on those claims.
On 24 November 1998, the Charlotte-Mecklenburg Board of
Education (the school board) contracted with Schenkel & Shultz to
design a new vocational high school. The contract required
Schenkel & Shultz to retain outside consultants or engineers to
prepare certain portions of the work, if Schenkel & Shultz did not
possess the in-house expertise necessary for the task. In April
1999, Schenkel & Shultz contracted with Fox & Associates to provide
structural steel design for the school. Drawings prepared by Fox
& Associates were incorporated into the final construction plans
submitted to the school board, and construction commenced in the
fall of 2000.
In the spring of 2001, contractors, subcontractors, and other
consultants began to question the adequacy of the structural steel
design prepared by Fox & Associates, who, after being notified of
the issues, reviewed its design and determined certain errors hadoccurred. Thereafter, Fox & Associates prepared and submitted
remedial designs, which required additional work by the steel
fabricators and erectors on-site to correct the errors. As a
result, several multi-prime contractors incurred increased costs
and invoiced the school board for payments exceeding three million
dollars.
On 3 October 2001, the school board sent Schenkel & Shultz a
letter stating that Schenkel & Shultz would be held responsible
for the cost of corrective work along with the cost required to
accelerate the schedule due to delays caused by the corrective
work. The following day, Schenkel & Shultz notified Fox &
Associates by letter that it would look to [Fox & Associates] and
[its] insurance carrier for full restitution of this cost.
On 5 February 2002, Schenkel & Shultz sent Fox & Associates
another letter asserting that it intended to hold Fox & Associates
liable for any damages associated with deficiencies in the
structural steel design. Additionally, Schenkel & Shultz
maintained that, Pursuant to the . . . agreement between [Schenkel
& Shultz and Fox & Associates] . . ., [Schenkel & Shultz] hereby
demands that [Fox & Associates] defend, indemnify and hold harmless
[Schenkel & Shultz] in connection with any such claims.
After failed mutual attempts to resolve the matter out of
court, Schenkel & Shultz brought an action against Fox & Associates
on 1 October 2004, alleging negligence and professional
malpractice, breach of contract, breach of warranty, and
indemnification. In response, Fox & Associates moved to dismissand counterclaimed for breach of contract due to failure to pay,
and thereafter moved for judgment on the pleadings. The school
board, in turn, brought an action against Schenkel & Shultz for
negligence and professional malpractice, breach of contract, and
breach of warranty, on 29 December 2004.
(See footnote 2)
On 25 February 2005, after converting Fox & Associates's
motion to dismiss to a motion for summary judgment, the trial court
granted summary judgment to Fox & Associates and dismissed with
prejudice Schenkel & Shultz's direct claims for negligence and
professional malpractice, breach of contract, and breach of
warranty, finding that such claims were barred by the statutes of
limitations. Thereafter, Fox & Associates moved for summary
judgment as to Schenkel & Shultz's remaining claim for
indemnification and its own counterclaim for breach of contract.
On 9 August 2005, the trial court granted Fox & Associates's motion
as to both claims and ordered Schenkel & Shultz to pay Fox &
Associates the contractual amount.
Schenkel & Shultz now appeals both orders of summary judgment,
arguing that the trial courts erred by (I) dismissing its direct
contract, tort, and warranty claims on the basis of the statutes of
limitations; (II) granting summary judgment to Fox & Associates onthe claim for indemnification; and, (III) granting summary judgment
to Fox & Associates on its counterclaim for breach of contract.
I.
[1] Schenkel & Shultz first argues the trial court erred by
holding that the applicable statutes of limitations barred its
direct claims under contract, tort, and warranty. We disagree.
Claims of breach of contract, negligence and professional
malpractice, and breach of warranty are all governed by a three-
year statute of limitations. See N.C. Gen. Stat. § 1-52(1) (2005)
(breach of contract); N.C. Gen. Stat. § 1-52(5) (2005) (any other
injury to the person or rights of another, not arising on contract
and not hereafter enumerated); N.C. Gen. Stat. § 1-52(16) (2005)
(for personal injury or physical damage to claimant's property).
In most cases, the statute of limitations begins to run when the
claim accrues, which generally occurs at the time of the breach.
See Miller v. Randolph, 124 N.C. App. 779, 781, 478 S.E.2d 668, 670
(1996) (The statute begins to run when the claim accrues; for a
breach of contract action, the claim accrues upon breach.); see
also Kaleel Builders, Inc. v. Ashby, 161 N.C. App. 34, 44, 587
S.E.2d 470, 477 (2003), disc. review denied, 358 N.C. 235, 595
S.E.2d 152 (2004) (The statute of limitations for breach of
warranty is also three years, accruing at breach.). Our Supreme
Court has stated that
The accrual of the cause of action must
therefore be reckoned from the time when the
first injury was sustained. . . . When the
right of the party is once violated, even in
ever so small a degree, the injury, in the
technical acceptation of that term, at oncesprings into existence and the cause of action
is complete.
Mast v. Sapp, 140 N.C. 533, 537-40, 53 S.E. 350, 351-52 (1906).
Moreover, [t]he bar of the statute of limitations is an
affirmative defense and cannot be availed of by a party who fails,
in due time and proper form, to invoke its protection. Overton v.
Overton, 259 N.C. 31, 36, 129 S.E.2d 593, 597 (1963).
Nevertheless, a statutory discovery rule offers a claimant
additional time in certain contract or negligence actions to have
the opportunity to discover the harm before the three-year statute
of limitations begins to accrue. See N.C. Gen. Stat. § 1-52(16)
(2005) (for personal injury or physical damage to claimant's
property, the cause of action . . . shall not accrue until bodily
harm to the claimant or physical damage to his property becomes
apparent or ought reasonably to have become apparent to the
claimant, whichever event first occurs.); N.C. Gen. Stat. § 1-
15(c) (2005) (a cause of action for malpractice arising out of the
performance of or failure to perform professional services shall be
deemed to accrue at the time of the occurrence of the last act of
the defendant giving rise to the cause of action).
Here, Schenkel & Shultz argues that a genuine issue of
material fact remains as to when the causes of action began to
accrue, namely, when the harm was complete or either became
apparent or ought reasonably to have become apparent. Schenkel &
Shultz points to its complaint, filed 1 October 2004, which asserts
that the school board notified Schenkel & Shultz of its belief that
there were numerous problems with the structural steel design ofthe project [b]eginning in October 2001. However, in the 25
February 2005 order granting summary judgment, the trial court
found that
[I]t has been established by uncontroverted
evidence that [Schenkel & Shultz] had actual
notice and/or reason to know of its claims
arising out of any alleged negligence and
professional malpractice, breach of contract
and breach of warranty by [Fox & Associates]
in connection with the structural steel design
on the Project no later than August 9, 2001, a
date more than three years prior to the filing
of Plaintiff's complaint.
This finding was based on the trial court's consideration of the
pleadings, exhibits thereto, the Affidavit in Opposition to Motion
for Judgment of the Pleadings filed by [Schenkel & Shultz] and the
attachments thereto, and the arguments of counsel. Included in
those documents was an 8 May 2001 letter from Schenkel & Shultz to
the construction project manager, acknowledg[ing] receipt of your
letter dated May 3, 2001 regarding concerns raised by your
structural steel subcontractor about the integrity of the
structural steel design on this project and noting that Fox &
Associates had decided to re-examine their complete structural
steel design on this project. Additionally, the record contains
a letter from the project manager to Schenkel & Shultz, dated 9
August 2001, notifying Schenkel & Shultz of problems with the
structural steel design in a specific part of the school being
constructed.
Nonetheless, Schenkel & Shultz contends that the causes of
action began to accrue not when the design was negligently provided
or when it was informed of the potential steel design problems, butwhen it was actually harmed by Fox & Associates's conduct. Thus,
Schenkel & Shultz asserts that the accrual began in October 2001,
when the school board first notified Schenkel & Shultz that it
would be held responsible for the cost overruns and delays, and Fox
& Associates declined to indemnify Schenkel & Shultz for the
damages.
In a similar action against an architect for negligence
arising out of a construction project, this Court held that the
date of the accrual of a cause of action is deemed to be the date
of discovery of the defective or unsafe condition of a structure,
and . . . the action must be brought within three years
thereafter. Quail Hollow East Condominium Ass'n v. Donald J.
Scholz Co., 47 N.C. App. 518, 527, 268 S.E.2d 12, 18, disc. review
denied, 301 N.C. 527, 273 S.E.2d 454 (1980); see also New Bern
Assocs. v. Celotex Corp., 87 N.C. App. 65, 70, 359 S.E.2d 481, 484,
disc. review denied, 321 N.C. 297, 362 S.E.2d 782 (1987) ([T]he
date the damage to its building was apparent or ought to have been
reasonably apparent is the date [the plaintiff's] cause of action
accrued.). Moreover, the discovery rule, which sometimes
operates to extend the statute of limitations, is intended to apply
in situations where the injury becomes apparent only after some
delay, or the claimant might be somehow prevented from realizing
the injury. See Black v. Littlejohn, 312 N.C. 626, 637-38, 325
S.E.2d 469, 477 (1985).
Such is not the case here, where Schenkel & Shultz was
promptly notified of Fox & Associates's alleged negligence andmalpractice and was on notice of a possible breach beginning in the
spring of 2001. The 8 May 2001 and 9 August 2001 letters fall
outside of the three-year statutes of limitations for the direct
claims alleged in its complaint filed on 1 October 2004. The
letters indicate that Schenkel & Shultz knew or had reason to know
of the harm done to the project and the resulting breach of the
underlying contract and warranty. Such knowledge would begin the
accrual of the three-year statutes of limitations for Schenkel &
Shultz's direct claims.
Accordingly, we find that no genuine issue of material fact
remains as to whether Schenkel & Shultz's direct claims were barred
by the statutes of limitations. We therefore affirm the trial
court's order of summary judgment as to Schenkel & Shultz's claims
of negligence and professional malpractice, breach of contract, and
breach of warranty.
II.
[2] Schenkel & Shultz next argues that a genuine issue of
material fact remains as to whether Schenkel & Shultz has a right
to express contractual indemnity, indemnity implied-in-law, or
indemnity implied-in-fact.
(See footnote 3)
See Kaleel, 161 N.C. App. at 38, 587S.E.2d at 474 ([A] party's rights to indemnity can rest on three
bases: (1) an express contract; (2) a contract implied-in-fact; or
(3) equitable concepts arising from the tort theory of indemnity,
often referred to as a contract implied-in-law.
).
We agree that v
iewing the evidence in the light most favorable
to Schenkel & Shultz,
the record indicates that a genuine issue of
material fact remains as to whether the contract in this case
expressly provides, through its incorporation by reference to a
separate contract, for the right to indemnity.
See Martin County
v. R.K. Stewart & Son, Inc., 63 N.C. App. 556, 558, 306 S.E.2d 118,
119 (1983) (finding a general contractor and subcontractor to be
bound by an incorporation by reference to all the provisions that
those several instruments contain).
Here, Schenkel & Shultz and Fox & Associates signed aStandard Form Agreement Between Architect and Consultant, which
provides in Paragraph 1.1.2 of Article 1, Consultant's
Responsibilities, that
The Consultant's [Fox & Associates's] services
shall be performed according to this Agreement
with the Architect [Schenkel & Shultz]
in the
same manner and to the same extent that the
Architect [Schenkel & Shultz] is bound by the
attached Prime Agreement to perform such
services for the Owner [the school board].
Except as set forth herein, the Consultant
[Fox & Associates] shall not have any duties
or responsibilities for any other part of the
Project.
(Emphasis added). The school board and Schenkel & Shultz likewise
signed a Standard Form Agreement Between Owner and Designer, in
which Paragraph 1.7 specifies that [t]he Designer [Schenkel &
Shultz] shall be responsible for any error, design inconsistencies
or omissions in the drawings, specifications, and other documents
and that [t]he Designer [Schenkel & Shultz] will correct, at no
additional cost or charges to the Owner [the school board] any and
all errors and omissions in the drawings, specifications, and other
documents prepared by the Designer [Schenkel & Shultz].
Paragraph
12.4 of the Agreement further provides that
In the event a claim, suit, or cause of action
is made against the Owner [the school board] .
. . for . . . loss or damage resulting solely
from any negligent act or omission of the
Designer [Schenkel & Shultz] or out of the
Designer's [Schenkel & Shultz's] breach of
this Agreement,
the Designer [Schenkel &
Shultz] agrees to defend and hold the Owner
[the school board], its agents, employees,
servants, representatives, successors and
assigns harmless and indemnified from and
against any loss, costs, damages, expenses,
attorneys fees and liability with respect to
such claim, suit, or cause of action.
(Emphasis added). Thus, the Prime Agreement did expressly provide
for a right to indemnity, and the contract between Schenkel &
Shultz and Fox & Associates did bind the parties in the same
manner and to the same extent as the Prime Agreement.
Additionally, when an agreement is ambiguous and the intention
of the parties is unclear, interpretation of the contract is for
the trier of fact.
Silver v. N.C. Bd. of Transp., 47 N.C. App.
261, 270, 267 S.E.2d 49, 55 (1980);
see also Int'l Paper Co. v.
Corporex Constructors, Inc., 96 N.C. App. 312, 317, 385 S.E.2d 553,
556 (1989) (Ambiguities in contracts are to be resolved by a trier
of fact upon consideration of a range of factors including the
expressions used, the subject matter, the end in view, the purpose
and the situation of the parties.). This Court has previously
held that summary judgment was improper on the question of
indemnity when contractual provisions _ including one that was
incorporated by reference as part of an addendum to the contract _
conflicted as to the scope of indemnity.
See Int'l Paper, 96 N.C.
App. at 316-17, 385 S.E.2d at 556. We find that the same is true
here, where ambiguity remains as to the intention of the parties
with respect to indemnity.
(See footnote 4)
Moreover, North Carolina follows the general rule that a cause
of action on an obligation to indemnify normally accrues when the
indemnitee suffers actual loss.
See Premier Corp. v. Economic
Research Analysts, Inc., 578 F.2d 551, 553-54 (4th Cir. 1978); N.C.
Gen. Stat. § 1-52 Case Notes (2005). Although the
Premier case
involved the sale of securities, the facts are analogous to the
instant case: the plaintiff brought an action for indemnity based
on an express contractual claim, but not until four years after the
underlying breach of contract, and, in fact, after the contract had
actually expired. The Fourth Circuit held that the indemnity claim
was not barred by the statute of limitations because the payment
for which the plaintiff sought indemnity was made several months
prior to the claim being filed, although more than three years
after the breach of contract.
Id. Thus, the actual loss was
suffered within the three-year period.
Here, Schenkel & Shultz filed its claim for indemnity beforethe school board instituted its action against Schenkel & Shultz
for costs and damages incurred as a result of steel design errors.
That action is still pending in federal court. Thus, the statute
of limitations has not yet tolled against Schenkel & Shultz for its
claim for indemnity against Fox & Associates.
[3] Though we find an issue of fact exists regarding Schenkel
& Shultz's claim for express contract indemnity, we reject Schenkel
& Shultz's contentions for indemnity under the theories of contract
implied-in-fact and contract implied-in-law.
As to a contract implied-in-fact, to determine if a right to
indemnity exists, we look to [the parties'] relationship and its
surrounding circumstances.
Kaleel, 161 N.C. App. at 40, 587
S.E.2d at 475. In the context of independent contractor
relationships, a right of indemnity under a contract implied-in-
fact is inappropriate where, as here, both parties are well
equipped to negotiate and bargain for such provisions.
See id.
Accordingly, in light of the ability and capacity of parties to
construction contracts to negotiate and bargain for mutually
agreeable terms, we decline to read a right of indemnity implied-
in-fact into the independent contractor agreement in this case. As
previously stated by this Court, to do otherwise would be to do so
in every general and subcontractor agreement, thus infringing upon
this state's long standing and coveted principle of freedom of
contract.
Id. at 41, 587 S.E.2d at 475.
Regarding a contract implied-in-law, this Court has described
indemnity through a contract implied-in-law as a rather discretelegal fiction, but has nonetheless stated that such a claim
arises from an underlying tort, where a passive tort-feasor pays
the judgment owed by an active tort-feasor to the injured third
party.
Id. at 39, 587 S.E.2d at 474. Thus, to successfully
assert a right to indemnity based on a contract implied-in-law, a
party must be able to prove each of the elements of an underlying
tort such as negligence. Moreover, expert witness testimony would
be necessary to prove a right to indemnity grounded in an
underlying claim of negligence, i.e., one that arises from a
contract implied-in-law. To prove negligence, Schenkel & Shultz
would be required to show that Fox & Associates had breached the
professional standard of care, which would almost certainly
necessitate expert witness testimony.
See Associated Indus.
Contractors, Inc. v. Fleming Eng'g, Inc., 162 N.C. App. 405, 409-
12, 590 S.E.2d 866, 870-72 (2004),
aff'd, 359 N.C. 296, 608 S.E.2d
757 (2005). Since the record reveals no such evidence, we reject
Schenkel & Shultz's claim for indemnity under a contract implied-
in-law.
In sum, because a genuine issue of material fact remains as to
the intention of the parties to provide for a right to indemnity by
incorporation by reference and the flow-through contractual
provision, we reverse the trial court's order of summary judgment
as to Schenkel & Shultz's claim for express contract indemnity.
However, we uphold the trial court's order of summary judgment
regarding Schenkel & Shultz's claims for indemnity under the
contract theories of implied-in-fact and implied-in-law.
III.
[4] Lastly, Schenkel & Shultz argues that the trial court
erred in granting summary judgment to Fox & Associates on its
counterclaim, when Fox & Associates breached its contract with
Schenkel & Shultz. Fox & Associates's counterclaim alleged
Schenkel & Shultz breached the contract by failing to pay Fox &
Associates the money due for services performed pursuant to the
contract. The trial court granted summary judgment in favor of Fox
& Associates, awarding the company $37,787.50. We agree with
Schenkel & Shultz and accordingly reverse the trial court's order
on this issue.
The general rule governing bilateral contracts provides that
if either party to the contract is materially in default with
respect to performance of his obligations under the contract, the
other party should be excused from the obligation to perform
further.
Paul B. Williams, Inc. v. Se. Reg'l Mental Health Ctr.,
89 N.C. App. 549, 551, 366 S.E.2d 516, 518 (1988). Schenkel &
Shultz argues that [i]t is undisputed in the record that [Fox &
Associates's] steel design was defective and that [Fox &
Associates] breached the contract by failing to perform its
contractual obligations in a professional manner.
The record contains substantial evidence that Fox &
Associates's steel design was defective, including numerous letters
offered as exhibits that demonstrated various parties' concern with
the structural integrity of Fox & Associates's steel design.
Accordingly, we believe a genuine issue of material fact existswhether Fox & Associates breached its contract with Schenkel &
Shultz by supplying a defective structural steel design for the
project. We therefore find that the trial court erred in granting
summary judgment in favor of Fox & Associates on its counterclaim,
and we reverse.
Affirmed in part, reversed in part.
Judge HUDSON concurs.
Judge TYSON concurs in part and dissents in part by separate
opinion.
TYSON, Judge, concurring in part, dissenting in part.
The majority's opinion correctly affirms the trial court's
order of summary judgment on Schenkel & Shultz, Inc., formerly
known as Schenkel & Shultz Architects, P.A.'s (plaintiff) claims
for negligence and professional malpractice, breach of contract,
and breach of warranty and reverses the trial court's order
granting summary judgment regarding Hermon F. Fox & Associates,
P.C.'s (defendant) counterclaim.
The majority opinion's conclusion that, because a genuine
issue of material fact remains as to the intention of the parties
to provide for a right to indemnity by incorporation by reference
and the 'flow-through' contractual provision and reversal of the
trial court's order granting defendant's motion for summary
judgment regarding plaintiff's claim for express contractual
indemnity is error. Plaintiff's failure to preserve or argue the lack of an expert
witness as a ground to grant summary judgment warrants dismissal of
this assignment of error. Alternatively, since the majority's
opinion addresses the merits of plaintiff's assignment of error,
plaintiff cannot establish indemnity negligence liability as a
matter of law without an expert witness and testimony. Plaintiff's
express contract indemnity claim also fails because indemnity
agreements imposing liability must be unequivocally clear. See
Candid Camera Video v. Mathews, 76 N.C. App. 634, 636, 334 S.E.2d
94, 96 (1985) (Indemnity against negligence must be made
unequivocally clear in the contract.), disc. rev. denied, 315 N.C.
390, 338 S.E.2d 879 (1986). The trial court properly granted
defendant's motion for summary judgment. I respectfully dissent
from the reversal of the trial court's grant of summary judgment on
plaintiff's indemnity claim.
I. Failure to Assign Error
Plaintiff argues the trial court erred in granting summary
judgment in favor of defendant on its indemnity claim. Defendant
argued four separate grounds in support of dismissing plaintiff's
indemnity claim in its motion for summary judgment:
3) [Defendant] now seeks the dismissal of the
Derivative Claim pursuant to Rule 56 on the
grounds that there are no material issues of
fact and that [defendant] is otherwise
entitled to judgment as a matter of law.
Specifically:
a) There is no express right to contractual
indemnification between [defendant] and the
Plaintiff;
b) There is no justification for an implied-in-fact indemnification between [defendant]
and Plaintiff;
c) [Defendant] and Plaintiff, as engineer and
supervising architect, do not satisfy the
active-passive framework required for common
law indemnification; and
d) Without an expert witness to establish
[defendant's] professional standard of care
and breach thereof, Plaintiff cannot establish
liability as a matter of law.
A. Lack of Expert Witness
On appeal, defendant argues plaintiff failed to designate an
expert witness prior to expiration of the deadline and cannot
satisfy its burden to establish defendant negligently performed its
duties under the contract without expert testimony. I agree.
The trial court's summary judgment order does not specify upon
which ground summary judgment was granted, and states, There are
no genuine issues of fact material to Plaintiff's claim for
indemnification against Defendant and that Defendant is entitled to
judgment as a matter of law. Plaintiff failed to assign error or
argue reversal of the trial court's summary judgment order due to
its failure to provide an expert witness to prove defendant failed
to meet the applicable standard of care. This failure on
plaintiff's indemnity claim alone supports affirming the trial
court's order.
1. Standard of Care Required
The standard of care provides a template against which the
finder of fact may measure the actual conduct of the professional.
The purpose of introducing evidence as to the standard of care in
a professional negligence lawsuit 'is to see if this defendant'sactions lived up to that standard[,]' and this is generally
established by expert testimony. Associated Indus. Contr'rs, Inc.
v. Fleming Eng'g, Inc., 162 N.C. App. 405, 410, 590 S.E.2d 866, 870
(2004) (quoting Little v. Matthewson, 114 N.C. App. 562, 567, 442
S.E.2d 567, 570 (1994), aff'd per curiam 340 N.C. 102, 455 S.E.2d
160 (1995)), aff'd on other grounds, 359 N.C. 296, 608 S.E.2d 757
(2005).
The scope of appellate review is limited to consideration of
the assignments of error set forth in the record on appeal and
argued in appellant's brief. N.C. R. App. 10(a) (2006); N.C. R.
App. 28(a) (2006). Plaintiff failed to set forth any argument in
its appellate brief to excuse its failure to designate an expert
witness.
Plaintiff's brief only addresses three of the four grounds
defendant argued to grant summary judgment. Plaintiff's failure to
designate an expert witness supports the trial court's grant of
summary judgment in favor of defendant. Plaintiff's assignment of
error is not preserved or is abandoned and should be dismissed.
II. Lack of an Expert Witness
The majority's opinion holds a genuine issue of material fact
exists whether the contract between plaintiff and the school board
provided for the indemnification of plaintiff by defendant by
incorporation-by-reference and the flow-through contractual
provision. Presuming an indemnity provision exists in these
contracts, summary judgment is still proper and the trial court's
judgment should be affirmed. No indemnity provision exists in thecontract between plaintiff and defendant.
The indemnity provision plaintiff relies upon states:
In the event a claim, suit, or cause of action
is made against [the school board] and/or [the
school boards'] representatives for any
personal injury, including death, or property
damage (other than to the work itself), or
other loss or damage resulting solely from any
negligent act or omission of the [plaintiff]
or out of [plaintiff's] breach of this
Agreement, [plaintiff] agrees to defend and
hold [the school board] . . . harmless and
indemnified from any loss, costs, damages,
expenses, attorneys fees and liability with
respect to such claim, suit, or cause of
action.
(Emphasis supplied). Even if this indemnity provision requires
defendant to indemnify plaintiff, plaintiff cannot establish
negligence liability as a matter of law without expert testimony to
establish defendant's professional standard of care and breach
thereof. See Handex of the Carolinas, Inc. v. County of Haywood,
168 N.C. App. 1, 10-11, 607 S.E.2d 25, 31 (2005) (The standard of
care provides a template against which the finder of fact may
measure the actual conduct of the professional. The purpose of
introducing evidence as to the standard of care in a professional
negligence lawsuit 'is to see if this defendant's actions 'lived
up' to that standard[,]' and generally this is established by way
of expert testimony. (quoting Associated Indus. Contr'rs, Inc. v.
Fleming Eng'g, Inc., 162 N.C. App. 405, 410, 590 S.E.2d 866, 870
(2004) (quoting Little v. Matthewson, 114 N.C. App. 562, 567, 442
S.E.2d 567, 570 (1994), aff'd per curiam, 340 N.C. 102, 455 S.E.2d
160 (1995))).
Plaintiff failed to disclose his expert witnesses within thetime required. If defendant's duty to indemnify arises out of
[plaintiff's] breach of the Agreement, with the school board,
expert testimony is required to establish the breach. The trial
court's order granting defendant's motion for summary judgment on
plaintiff's indemnification claim should be affirmed on the merits.
III. Contractual Indemnity
The majority's opinion holds the trial court's order granting
defendant's motion for summary judgment regarding plaintiff's
indemnification claim should be reversed because a genuine issue of
material fact remains as to whether the contract between plaintiff
and defendant expressly provided for indemnification. I disagree.
Plaintiff argues that defendant is contractually bound to
indemnify it because plaintiff had contractually agreed to
indemnify the school board. As noted earlier, the contract between
plaintiff and the school board provides, in part, that:
In the event a claim, suit, or cause of action
is made against [the school board] and/or [the
school boards'] representatives for any
personal injury, including death, or property
damage (other than to the work itself), or
other loss or damage resulting solely from any
negligent act or omission of the [plaintiff]
or out of [plaintiff's] breach of this
Agreement, [plaintiff] agrees to defend and
hold [the school board] . . . harmless and
indemnified from any loss, costs, damages,
expenses, attorneys fees and liability with
respect to such claim, suit, or cause of
action.
The contract between plaintiff and defendant does not include this
covenant or any express contractual provision for defendant to
indemnify plaintiff. Plaintiff relies on Section 1.1.2 of its
contract with defendant to argue the above language wasincorporated by reference or implied into its contract with
defendant. Section 1.1.2 of the contract between plaintiff and
defendant provides:
[Defendant's] services shall be performed
according to this Agreement with [plaintiff]
in the same manner and to the same extent that
[plaintiff] is bound by the attached Prime
Agreement to perform such services for [the
school board]. Except as set forth herein,
[defendant] shall not have any duties or
responsibilities for any other part of the
project.
Plaintiff drafted the contract with defendant and failed to
reference, include, or bargain for any indemnification by
defendant. See Silvers v. Horace Mann Ins. Co., 324 N.C. 289, 295,
378 S.E.2d 21, 25 (1989) (contracts are construed against the
drafter).
Courts strictly construe an indemnity clause against the
party asserting it. Hoisington v. ZT-Winston-Salem Assocs., 133
N.C. App. 485, 494, 516 S.E.2d 176, 183 (1999), disc. rev.
improvidently allowed, 351 N.C. 342, 525 S.E.2d 173 (2000). This
Court has stated:
In interpreting a contract of indemnity, the
court should give effect to the intention of
the parties. But where the contractual
language is clear and unambiguous, the court
must interpret the contract as written.
Indemnity against negligence must be made
unequivocally clear in the contract,
particularly in a situation where the parties
have presumably dealt at arm's length.
Candid Camera Video, 76 N.C. App. at 636, 334 S.E.2d at 96
(internal citation omitted) (emphasis supplied).
A court is not free to incorporate, imply, or write into aclear and unambiguous contract covenants and conditions the
parties themselves did not include. Id.; see Klein v. Insurance
Co., 289 N.C. 63, 66, 220 S.E.2d 595, 597 (1975) (A court cannot
rewrite a contract and make a new contract for the parties.).
Where the language of a contract is clear and unambiguous,
the court is obligated to interpret the contract as written, and
the court cannot look beyond the terms to see what the intentions
of the parties might have been in making the agreement. Renfro v.
Meacham, 50 N.C. App. 491, 496, 274 S.E.2d 377, 379 (1981) (citing
Root v. Allstate Insurance Co., 272 N.C. 580, 158 S.E.2d 829
(1968)).
The majority's opinion correctly states, a right to indemnity
may rest on the express contractual provisions between two
parties. Here, the contract between plaintiff and defendant
clearly and unambiguously does not contain an express contractual
provision requiring defendant to indemnify plaintiff. No provision
contained in the contract between the parties requires defendant to
indemnify or hold plaintiff harmless for its negligence.
The trial court properly interpreted the contract and
correctly determined it did not unequivocally provide for
defendant to indemnify plaintiff. Candid Camera Video, 76 N.C.
App. at 636, 334 S.E.2d at 96. The trial court correctly granted
defendant's motion for summary judgment on plaintiff's
indemnification claim. That portion of the trial court's order
should also be affirmed.
IV. Conclusion
The majority's opinion correctly affirms the trial court's
order of summary judgment dismissing plaintiff's claims for
negligence and professional malpractice, breach of contract, and
breach of warranty, and reverses summary judgment for plaintiff on
defendant's counterclaim.
Plaintiff's failure to preserve or argue its lack of an expert
witness as a ground to grant defendant's motion for summary
judgment supports dismissal of plaintiff's indemnity claim.
Plaintiff's assignment of error should be dismissed.
Alternatively, because the majority's opinion addresses the
merits of plaintiff's assignment of error, the trial court properly
granted defendant's motion for summary judgment. Plaintiff cannot
establish negligence liability as a matter of law without an expert
witness.
Handex of the Carolinas, Inc., 168 N.C. App. at 10-11,
607 S.E.2d at 31.
Summary judgment on plaintiff's indemnity claim should also be
affirmed because the contract plaintiff drafted and relies on does
not unequivocally provide for indemnification by defendant.
See
Candid Camera Video, 76 N.C. App. at 636, 334 S.E.2d at 96
(Indemnity against negligence must be made unequivocally clear in
the contract.). The contract between plaintiff and defendant does
not contain an indemnity provision. Courts should not incorporate,
imply, or write into the parties' contract a provision the parties
themselves failed to include.
I vote to affirm the trial court's order granting defendant's
motion for summary judgment and dismissing plaintiff'sindemnification claim. I respectfully dissent.
Footnote: 1 See Kaleel Builders, Inc. v. Ashby, 161 N.C. App. 34, 38,
587 S.E.2d 470, 474 (2003),
disc. review denied, 358 N.C. 235,
595 S.E.2d 152 (2004).
Footnote: 2 This case was removed to federal court on 17 February
2005. Schenkel & Shultz filed a third-party complaint against
Fox & Associates in the action, and the district court dismissed
that complaint following the two entries of summary judgment
against Schenkel & Shultz on its four actions against Fox &
Associates in state court.
See Charlotte-Mecklenburg Bd. of
Educ. v. Schenkel & Shultz, Inc., No. 3:05-CV-69, 2006 WL 1642140
(W.D.N.C. 2006).
Footnote: 3 Procedurally, we
note in passing that specific assignments
of error are not required where . . . the sole question
presented in [one party's] brief is whether the trial court erred
in granting summary judgment in favor of [the other party]. The
appeal from the judgment is itself an exception thereto.
Vernon, Vernon, Wooten, Brown & Andrews, P.A. v. Miller, 73 N.C.
App. 295, 297, 326 S.E.2d 316, 319 (1985) (citing
West v. Slick,
60 N.C. App. 345, 299 S.E.2d 657 (1983),
rev'd on other grounds,
313 N.C. 33, 326 S.E.2d 601 (1985). In such cases, [o]ur review
is limited to whether, on the face of the record proper, summary
judgment was appropriately entered or if genuine issues ofmaterial fact exist so that the case should be remanded.
Id.
The appellee in such an instance is still provided notice of the
basis upon which an appellate court might rule.
See Viar v.
N.C. Dep't of Transp., 359 N.C. 400, 401, 610 S.E.2d 360, 361
(2005).
Here, Schenkel & Shultz assigned as error the trial court's
grant of summary judgment denying its claim for indemnity on
three different grounds: (1) express contract; (2) contract
implied-in-fact; and, (3) contract implied-in-law. As such, the
assignments of error were proper in questioning whether a genuine
issue of material fact remains as to any of these three bases.
Moreover, we observe that the dissent's assertion that
Schenkel & Schultz's failure to preserve or argue the lack of an
expert witness as a ground to grant summary judgment[] warrants
dismissal of this assignment of error conflates the issues of
negligence and breach of contract, either of which could be the
basis for indemnity according to the contract between the
parties,
see Paragraph 12.4, Standard Form Agreement Between
Owner and Designer,
infra. As expert witness testimony
concerning the professional standard of care would not be
necessary to establish a breach of contract, we find it to be an
independent basis for Schenkel & Schultz's appeal and properly
preserved in its assignments of error to this Court.
Footnote: 4 The dissent cites to
Candid Camera Video World, Inc. v.
Mathews, 76 N.C. App. 634, 334 S.E.2d 94 (1985),
disc. review
denied, 315 N.C. 390, 338 S.E.2d 879 (1986), as standing for the
proposition that [i]ndemnity against negligence must be made
unequivocally clear in the contract, particularly in a situation
where the parties have presumably dealt at arm's length.
Id. at
636, 334 S.E.2d at 96 (citing
Cooper v. H.B. Owsley & Son, Inc.,
43 N.C. App. 261, 267, 258 S.E.2d 842, 846 (1979)). Although
Candid Camera does contain that language, the case actually
concerned whether the indemnification clause of a lease agreement
was applicable to the managers of a shopping mall, rather thanjust to the owners and the store. Thus, this Court did not
specifically address whether the contractual terms regarding
indemnity extended to acts of negligence; rather, the opinion
dealt with whether the contract applied to the parties to the
action. Moreover, the
Cooper case cited in
Candid Camera
supports our position here; in
Cooper, although the lease
agreement in question did not specifically reference negligence
or breach of contract, this Court still found negligence to be
included in the phrase from whatsoever cause arising such that
the rental company was required to indemnify the owner against
liability for injuries sustained by third persons. 43 N.C. App.
at 268, 258 S.E.2d at 846. Here, by contrast, the contract
contained language concerning both any negligent act or
omission and breach of this Agreement.
Again, however, we note that despite the dissent's approach
to the instant case solely as a professional negligence action,
indemnity would also be required if a breach of contract were
found.
*** Converted from WordPerfect ***