An unpublished opinion of the North Carolina Court of Appeals does not constitute controlling legal authority. Citation is disfavored, but may be permitted in accordance with the provisions of Rule 30(e)(3) of the North Carolina Rules of Appellate Proced
ure.
NO. COA05-214
NORTH CAROLINA COURT OF APPEALS
Filed: 3 January 2006
MIDLAND FIRE PROTECTION, INC.,
Plaintiff,
v
.
Wake County
No. 03 CVS 44
0
CLANCY & THEYS CONSTRUCTION CO.,
Defendant.
Appeal by defendant from judgment entered 15 October 2004 by
Judge Orlando F. Hudson in Wake County Superior Court. Heard in
the Court of Appeals 13 October 2005.
Jordan Price Wall Gray Jones & Carlton, PLLC, by Henry W.
Jones, Jr., and Brian S. Edlin, for plaintiff appellee.
Taylor, Penry, Rash & Riemann, PLLC, by Neil A. Riemann, for
defendant appellant.
McCULLOUGH, Judge.
Defendant Clancy & Theys Construction Company appeals from a
judgment awarding damages to plaintiff Midland Fire Protection,
Incorporated, for breach of contract. We affirm.
Facts
Clancy & Theys was hired in early 2001 to oversee the
construction of a Belk's Department Store at the Streets at
Southpoint Mall in Durham, North Carolina. Though Clancy was a
licensed general contractor, it did not have a license to perform
fire sprinkler work associated with the project. Midland Fire
Protection placed a bid in which it agreed to perform the sprinklerwork for $239,346.00. Clancy accepted this offer in February of
2001 and sent a letter of intent to award Midland the fire
sprinkler work at the quoted price. On 14 February 2001, Clancy
sent Midland the subcontract documenting the agreement.
Subsequently, in March of 2001, Midland received the requisite
North Carolina license to act as a fire sprinkler contractor.
Clancy directed Midland to begin working on the Belk's project on
24 April 2001, and Midland actually began working on 29 May 2001.
Midland had initially estimated that an area of the department
store containing a shoe rack mezzanine would contain approximately
forty sprinkler heads, which would take a total of approximately
fifty hours to install. However, the design of the shoe rack area
was changed, and completion of it was delayed such that Midland
could not complete the related sprinkler work as initially
anticipated by the parties. The mezzanine was not installed until
December 2001, by which time the store had been carpeted,
furnished, and painted, and the sprinkler system had been installed
everywhere except the shoe rack area.
Between October and December 2001, Midland notified Clancy
several times that the changes and delays related to the shoe rack
area would result in additional expenses and work for Midland.
Specifically, Midland mentioned that it would have to install
additional sprinkler heads and refabricate its pipes to meet the
changed design. Further, Midland expressed concerns that, given
the state of completion of the department store, it would be forcedto perform cutting and fabrication tasks outside, which would be
much more time-consuming, difficult, and expensive than performing
these tasks in the building during an earlier stage of the
construction. In response, Clancy requested that Midland submit an
estimate for the additional work. Midland submitted a bid in the
amount of $36,000.00. Clancy expressed concern as to the amount of
the bid and, in December 2001, directed Midland to proceed with the
additional work on a time and materials basis. Clancy advised
Midland to instead keep records of its additional costs.
Accordingly, Midland purchased additional material, and
expended approximately 293 hours of labor to install the sprinkler
system in the shoe rack area. Thereafter, Midland submitted a time
and materials invoice to Clancy for $20,878.80. Clancy accepted
this invoice, added a surcharge, signed the invoice, and presented
the bill to the owner of the building, who ultimately refused to
make payment for the additional work.
Pursuant to the parties' February 2001 agreement, Clancy paid
Midland $239,346.00. Clancy also made payment for some additional
work performed. However, Clancy did not pay the $20,878.80 bill
submitted by Midland for additional materials used and time
expended installing the sprinkler system in the shoe rack area of
the store.
Midland brought suit against Clancy in Wake County Superior
Court for, inter alia, breach of contract. Following a benchtrial, the superior court entered a judgment in Midland's favor.
The court made the following findings of fact:
22. On 14 December 2001, [Clancy] . . .
specifically directed Midland to proceed with the
additional work and to monitor and compile its actual
additional costs and expenses associated with the
additional work with full knowledge of the circumstances
of the timing of the shoe rack installation and damages
to Midland and with the express representation to Midland
to monitor and compile its actual additional costs and
submit the actual additional costs to [Clancy] for
payment . . . .
23. Midland proceeded with the additional work at
[Clancy's] direction and with the reasonable expectation
and reliance upon [Clancy's] direction and representation
that it would be compensated for its actual additional
costs and expenses to complete the work in the shoe rack
area.
24. Midland did in fact complete the work in the
shoe rack area on a timely basis and to the satisfaction
of [Clancy] . . . . Between 24 December 2001 and 25
January 2002, at the request of [Clancy], [Midland]
purchased and installed additional materials in the shoe
rack area and expended exactly two hundred and ninety
three . . . (293) man hours in accomplishing the
additional work in the shoe rack area. During this time
period, Midland installed an additional six (6) sprinkler
heads in the shoe rack area. Midland completed its work
on time and within its schedule and the Owner was able to
meet its schedule for occupancy of the building. [The
additional work] included, without limitation, the
following: sifting through piles of rusted pipes outside
of the building because [Clancy] had put these pipes
outside of the building to make way for a finished
building; locating the pipes outside which were 500 feet
from [the] building; cleaning pipes removed outside by
[Clancy]; salvaging pipes if salvageable; wire brushing
pipes to get rust off; rethreading pipes; going to supply
house for supplies; buying additional supplies; re-
working the piping system [due] to shoe rack[] re-
configurations and performing such work outside the
building and walking across carpet to get to [the] shoe
rack areas. [The employees who did this work] kept
detailed and accurate records of [their] time in the shoe
rack area[]. These additional services and materials wererendered to [Clancy] and were not given gratuitously by
Midland.
25. Midland's original bid on the Project provided
for fifty (50) man hours in accomplishing the work in the
shoe rack area[], however, Midland actually incurred two
hundred and ninety three . . . (293) man hours in
performing the additional work in the shoe rack area.
Midland incurred two hundred and forty three . . . (243)
additional man hours in performing the additional work in
the shoe rack area.
. . . .
27. Per the agreement between Midland and [Clancy],
Midland submitted its invoice for the additional time and
materials expended in the shoe rack area[] in the amount
of twenty thousand eight hundred and seventy eight
dollars and eighty cents ($20,878.80) to [Clancy] on 2
May 2002. The invoice for the additional time and
materials expended in the shoe rack area[] was submitted
on a form that was previously used by Midland in
obtaining additional funds from [Clancy] and on a form
that was previously acknowledged and honored by [Clancy].
28. [Clancy] knowingly and voluntarily accepted the
additional services and materials provided by Midland.
[Clancy] has not paid any amount of the twenty thousand
eight hundred and seventy eight dollars and eighty cents
($20,878.80) to date. The reasonable value of the
additional materials and services rendered by Midland is
twenty thousand eight hundred and seventy eight dollars
and eighty cents ($20,878.80).
29. [Clancy] did pay all two hundred and thirty
nine thousand three hundred and forty six dollars
($239,346.00) to Midland plus all amounts for the
undisputed change orders, which change orders were signed
by both parties after the additional work giving rise to
the change order was accomplished by Midland.
The court made the following conclusions of law:
3. [Clancy] and Midland entered into a contract on
or about 14 December 2001 whereby Midland agreed to
perform additional piping and sprinkler installation
services in the shoe rack area of the Belk's Project.
Midland agreed to perform such services on a time and
materials basis. The parties agreed that Midland would
monitor the additional hours and materials worked andprovided in the shoe rack area, bill [Clancy] for such
additional hours and materials and [that Clancy] would
compensate Midland for such material and services upon
receipt of the bill from Midland.
4. Midland duly performed its contractual duties
to [Clancy] by providing additional labor, material, and
equipment for the shoe rack area[] of the Project.
Midland kept detailed records of the hours expended and
the materials installed in the shoe rack area and
quantified the time and materials for its extra work in
the shoe rack area in a reasonable manner.
5. [Clancy] breached the contract by failing to
compensate Midland for its additional actual costs,
materials and expenses associated with the additional
work in the shoe rack area of the Project.
6. As a direct, proximate and foreseeable result
of [Clancy]'s breach, Midland has sustained damages in
the amount of twenty thousand eight hundred and seventy
eight dollars and eighty cents ($20,878.80). The
additional expenses incurred and time expended by Midland
[were] directly and foreseeably tied to the timing of the
installation of the shoe racks. Midland's bid for the
Belk's project included fifty hours (50) for the work in
the shoe rack area and . . . this estimate was a
reasonable estimate of hours for its bid for this work.
The actual additional costs and the hours incurred by
Midland in the shoe rack area were reasonable and Midland
was not in any way responsible for the added costs in the
shoe rack area.
. . . .
10. Midland's licensure status on 14 February 2001
with the North Carolina State Board of Examiners of
Plumbing, Heating & Fire Sprinkler Contractors is not a
bar to Midland's recovery from [Clancy] . . . .
The trial court ordered Clancy to pay damages, plus interest, to
Midland. From this judgment, Clancy now appeals.
Standard of Review
On an appeal from a bench trial, the trial judge's findings
are conclusive if they are supported by competent evidence eventhough there may be evidence which would support findings to the
contrary. Mann Contr'rs, Inc. v. Flair with Goldsmith
Consultants-II, Inc., 135 N.C. App. 772, 775, 522 S.E.2d 118, 121
(1999). Conclusions of law are reviewed de novo by this Court for
whether they are supported by appropriate findings of fact and are
consistent with applicable law. Id.
I.
We first consider whether the trial court erred by determining
that the parties entered into a second contract in December 2001.
Clancy challenges the finding that a second contract was formed
and, therefore, the ruling that a second contract was breached.
This contention lacks merit.
In its brief, Clancy advances two separate rationales for its
position that there was no second contact. First, Clancy argues
that Midland had already agreed to install the fire protection
system in the shoe rack area for a fixed price, and the only thing
that changed was the amount of effort Midland had to expend to
perform its obligations. Thus, according to Clancy, there was no
'additional work' to be the subject matter of a new contract, and
the trial court erred by determining otherwise.
Under the pre-existing duty rule, 'a promise to perform an
act which [the] promisor is already bound to perform is
insufficient consideration for a promise by the adverse party.'
Sinclair v. Travis, 231 N.C. 345, 354, 57 S.E.2d 394, 400 (1950)
(citation omitted). If a return promise is given in return for apromise to perform a pre-existing duty, there is . . . no new
consideration, and no new agreement. Id.
In the instant case, the trial court was not required to find
that Midland's obligation under the February 2001 contract
precluded the formation of a new agreement in December 2001.
Midland presented evidence that changes to the design of the shoe
rack area required installation of additional sprinkler heads and
refabrication of pipes. Further, Midland's evidence tended to show
that the parties' original agreement presupposed that Midland would
be able to perform cutting and fabrication tasks inside the
building near the installation site as opposed to outside of the
building, where this work would be far more time-consuming,
difficult, and expensive. This evidence permitted inferences that
the amount of Midland's work increased, that additional,
unanticipated labor from Midland was required, and that these
increases in required output served as sufficient consideration for
a new contract. Therefore, lack of consideration did not preclude
the trial court from determining that the parties entered into a
second contract.
Clancy also argues that, even if there was sufficient
consideration upon which to premise a new agreement, a second
contract could not have been formed because the terms of any such
agreement were too indefinite. In particular, Clancy insists that
the parties reached no agreement concerning price or payment terms. In the making of a contract[,] it is essential that the
parties thereto assent to the same thing in the same sense, and
their minds must meet as to all terms. Sides v. Tidwell, 216 N.C.
480, 483, 5 S.E.2d 316, 318 (1939). Therefore, '[i]n order to
constitute a valid . . . agreement, the parties must express
themselves in such terms that it can be ascertained to a reasonable
degree of certainty what they mean. And if an agreement [is] so
vague and indefinite that it is not possible to collect from it the
full intent of the parties[,] it is void[.]' Holder v. Mortgage
Co., 214 N.C. 128, 133, 198 S.E. 589, 591-92 (1938) (citation
omitted). The essential terms of a contract include the subject
matter of the agreement and the price to be paid under it. See
Yaggy v. B.V.D. Co., 7 N.C. App. 590, 600, 173 S.E.2d 496, 503
(holding that the vendor, the vendee, the purchase price,
and . . . the property sold . . . [were] the essential elements of
[a] contract), cert. denied, 276 N.C. 728 (1970).
In the instant case, the evidence tended to show that in
response to a request by Clancy, Midland submitted an estimate in
which it projected that additional work in the shoe rack area would
require 360 man-hours billed at $60 per hour and 162 premium time
man-hours billed at $90 per hour. Likewise, Midland noted that
additional materials would be needed to complete the shoe rack
area. Though Clancy did not accept Midland's bid, it directed
Midland to proceed on a time-and-material basis to install the
[sprinklers for the] shoe rack. This evidence permits aninference that Clancy agreed to pay Midland for labor according to
its hourly rates and agreed to reimburse Midland for necessary
materials. Therefore, the price and payment terms of the parties'
agreement were not so indefinite as to preclude the trial court
from determining that the parties entered into a second contract.
The corresponding assignments of error are overruled.
II.
We next consider Clancy's contention that the trial court
erred by permitting Midland to recover contract damages even though
Midland was not properly licensed to perform fire sprinkler work
when the parties entered into their February 2001 contract. This
contention lacks merit.
In this state, a contract illegally entered into by an
unlicensed general construction contractor is unenforceable by the
contractor. It cannot be validated by the contractor's subsequent
procurement of a license. Brady v. Fulghum, 309 N.C. 580, 586,
308 S.E.2d 327, 331 (1983). This rule is premised upon the
recognition that licensing schemes are enacted to promote safe and
workmanlike construction for the protection of the public. Id. at
584-85, 308 S.E.2d at 330-31. However, [t]he licensing statutes
have no application to the rights and liabilities of contractors
and subcontractors inter se where the public interest is not
involved. Vogel v. Supply Co., 277 N.C. 119, 133, 177 S.E.2d 273,
282 (1970). Specifically, our Supreme Court has held that an
unlicensed general contractor may nevertheless enforce a contractagainst a subcontractor where no injury to the public is apparent
from enforcement of the subcontract between the parties to it.
Id. at 134, 177 S.E.2d at 282. We note that, in the case in which
this holding was issued, the particular subcontractor was not
required to be licensed. Id. at 133, 177 S.E.2d at 282.
The General Statutes provide that a license shall be
obtained . . . before any person, firm or corporation shall engage
in, or offer to engage in, the business of plumbing, heating, or
fire sprinkler contracting, or any combination thereof. N.C. Gen.
Stat. § 87-21(b)(3) (2003). This licensing scheme exists to
protect the public health, comfort and safety. N.C. Gen. Stat. §
87-21(b)(1) (2003). Accordingly, Midland was required to be
properly licensed before contracting to perform any fire sprinkler
work.
However, the facts of the present case do not require us to
resolve the issue of whether a contract for fire sprinkler work may
be enforced against a general contractor by a subcontractor who was
not licensed to perform such work at the time the subcontract was
entered into. In the instant case, there is no dispute about the
work performed by Midland under the parties' original agreement,
which was entered into in February of 2001. As such, the status of
Midland's license in February of 2001 is inconsequential to the
present litigation. Furthermore, Midland did hold an appropriate
license in December 2001, when the parties entered into a secondcontract for Midland to perform the additional work related to the
shoe rack area on a time and materials basis.
Therefore, the trial court did not err by permitting Midland
to recover on its breach of contract claim. The corresponding
assignment of error is overruled.
III.
We next consider Clancy's argument that the trial court erred
by awarding damages in violation of this Court's decision in
Biemann & Rowell Co. v. Donohoe Cos., 147 N.C. App. 239, 556 S.E.2d
1 (2001). This contention lacks merit.
In Biemann, we held that the method of computing damages known
as the total cost method may only be used where no other way to
compute damages is feasible. Id. at 245, 556 S.E.2d at 5. Under
the total cost method, a contractor seeks the difference between
its total costs incurred in performance of the contract and its bid
price. Id. This method is disfavored 'because it blandly
assumes--that every penny of the plaintiff's costs are prima facie
reasonable, that the bid was accurately and reasonably computed,
and that the plaintiff is not responsible for any increases in
cost.' Id. (citation omitted). Biemann involved claims between
multi-prime contractors which did not have a contract with each
other.
In the instant case, the evidence tended to show that Clancy
agreed to pay Midland on a time and materials basis for additional
fire sprinkler installation work in the shoe rack area. By itsnature, this agreement contemplated that Midland would be
compensated for the total cost of performing the additional work.
Under this arrangement, the only feasible way of calculating the
amount owed was to reduce the total amount due Midland for the
additional work by the amount which Midland had already been paid
for work in the shoe rack area. Pursuant to the parties' original
understanding about the time and materials necessary to install
fire sprinklers in the shoe rack area, Midland budgeted fifty hours
of labor and a certain amount of materials, and the original bid
reflected these calculations. Clancy made payment for these hours
and materials when it made payment under the parties' February 2001
agreement. Thus, in this particular situation, Midland's actual
damages for Clancy's breach of the December 2001 contract was the
remaining amount of time and materials spent. There was no other
way to calculate damages.
The trial court found, based on competent evidence, that
Midland's original bid was accurately and reasonably computed, that
its additional costs were reasonable, and that Midland was not
responsible for any increases in the cost of installing fire
sprinklers in the shoe rack area. The trial court then calculated
damages by subtracting the amount Midland had already been paid for
its work in the shoe rack area from the total value of the time and
materials which went into completing the fire sprinkler system in
the shoe rack area. As this calculation was appropriate, the
damages award must be affirmed. The corresponding assignment of error is overruled.
IV.
The foregoing analysis makes it unnecessary for us to address
Midland's cross-assignment of error.
The trial court's judgment is
Affirmed.
Judges ELMORE and LEVINSON concur.
Report per Rule 30(e).
*** Converted from WordPerfect ***