B & L SURVEYS,
Plaintiff,
v
.
Davidson County
No. 05 CVD 656
ZANDLE B. CLINE,
Defendant.
Samuel Todd Leonard and Kim Howard Black, both pro se, for
plaintiff-appellee.
Morgan, Herring, Morgan, Green, Rosenblutt & Gill, L.L.C., by
John Haworth, for defendant-appellant.
ELMORE, Judge.
Zandle Cline (defendant) appeals a judgment entered by the
district court awarding B & L Surveys (plaintiff) $2,100.00 for
work performed under an implied contract. Defendant does not
challenge the existence of the implied contract. Accordingly, our
sole inquiry is whether the evidence presented in the district
court was sufficient to support the damage award. We conclude that
it was not.
The district court found that an implied contract existed
between plaintiff and defendant for various surveying andengineering services under the doctrine of quantum meruit. That
principle is defined as follows:
Quantum meruit is an equitable principle that
allows recovery for services based upon an
implied contract. The law implies a promise
to pay for services rendered by one party to
another where the recipient knowingly and
voluntarily accepts the services and there is
no showing that the services were gratuitously
given.
Harrell v. Construction Co., 41 N.C. App. 593, 595, 255 S.E.2d 280,
281 (1979) (citing Johnson v. Sanders, 260 N.C. 291, 132 S.E.2d 582
(1963)), aff'd, 300 N.C. 353, 266 S.E.2d 626 (1980). Since
defendant submitted to the City of Lexington required survey
records for development that plaintiff generated, and plaintiff
brought forth those records at the district court hearing, the
court properly concluded that an implied contract existed for the
work performed.
As with any implied contract, there was no express agreement
regarding the price to be paid plaintiff for its services.
Further, our Supreme Court has held that [d]amages are never
presumed. The burden is always upon the complaining party to
establish by evidence such facts as will furnish a basis for their
assessment, according to some definite legal rule. Lieb v. Mayer,
244 N.C. 613, 616, 94 S.E.2d 658, 660 (1956). Thus, the fact-
finder must determine the reasonable value of the uncompensated
goods or services in order for plaintiff to recover more than
nominal damages.
The general rule is that when there is no
agreement as to the amount of compensation to
be paid for services, the person performingthem is entitled to recover what they are
reasonably worth, based on the time and labor
expended, skill, knowledge and experience
involved, and other attendant circumstances,
rather than on the use to be made of the
result or the benefit to the person for whom
the services are rendered.
Turner v. Furniture Co., 217 N.C. 695, 697, 9 S.E.2d 379, 380
(1940).
Factors such as the supply, demand, and quality of the goods
or services may be considered. Cline v. Cline, 258 N.C. 295, 300,
128 S.E.2d 401, 404 (1962). Moreover, the reasonable value of
services rendered is determined largely by the nature of the work
and the customary rate of pay for such work in the community at the
time the work is performed. Environmental Landscape Design v.
Shields, 75 N.C. App. 304, 307, 330 S.E.2d 627, 629 (1985). But
this Court has held that invoices and bills alone, representing
plaintiff's charges for goods and services, are not sufficient to
support a jury award as to the reasonable value of the goods and
services. Harrell, 41 N.C. App. at 595-96, 255 S.E.2d at 281-82;
see also Hood v. Faulkner, 47 N.C. App. 611, 617, 267 S.E.2d 704,
707 (1980) (Although relevant, neither a current bill nor
plaintiff's opinion that the bill is a reasonable amount, alone is
sufficient to establish reasonable value.). However, combining
current bills with evidence of past payments in accordance with
previous bills might be considered as sufficient evidence of the
reasonable value of goods and services. See Booe v. Shadrick, 322
N.C. 567, 571, 369 S.E.2d 544, 556 (1988) (holding that
[witness's] testimony as to what was billed for the materials andlabor and the evidence of payment for part of it at the billed rate
is evidence sufficient for the jury to find reasonable value to the
defendants of the remaining goods and services for which bills were
submitted and no payment was made.).
Plaintiff contends it presented sufficient evidence to support
the district court's judgment of $2,100.00 as a reasonable value of
the unpaid portion of its services; however, plaintiff did not
present any evidence other than the work-products themselves
together with current and previous billing invoices. Plaintiff
failed to present evidence showing the time and labor expended,
skill, knowledge and experience involved, the supply, demand, and
quality, or the customary rate of pay for such work in the
community at the time the work is performed. Current billing
invoices in isolation are not sufficient to support the district
court's award of actual damages. See Harrell, 41 N.C. App. at 595-
96, 255 S.E.2d at 281-82.
Plaintiff's evidence of the current billing invoice combined
with a previously paid invoice for a sketch plan is similarly
insufficient, because plaintiff currently seeks compensation for
various fieldwork and the preparation of an annexation map and
description for the City of Lexington Planning Department, both of
which bear no relation to what value might have been customary for
a prior sketch plan.
Finding no evidence supporting the district court's assessment
of the reasonable value of the unpaid portions of plaintiff'sservices, we remand the case for further proceedings on the issue
of damages, i.e. the value of plaintiff's services.
Reversed and remanded.
Judges McGEE and STEELMAN concur.
Report per Rule 30(e).
*** Converted from WordPerfect ***