How to access the above link?
Return to nccourts.org
Return to the Opinions Page
1. Appeal and Error--appealability--denial of summary judgment--final judgment on
merits rendered
Although defendant contends the trial court erred in a breach of contract case by denying
his motion for summary judgment, this issue cannot be addressed because a final judgment on
the merits has been made.
2. Contracts--breach--impossibility of performance--frustration of purpose
The trial court did not err in a breach of contract case by denying defendant's motions for
a new trial and amendment of judgment based on the jury's calculation of damages, because: (1)
the doctrine of impossibility of performance was inapplicable when the premises at issue still
exist and at the time defendant refused to perform were in the same condition as when the
contract was signed; (2) although defendant contends he could not have opened a restaurant on
the pertinent premises based on the fact that it was impossible to install the proper grease trap,
conclusive evidence was presented that the current tenants of the property were in fact running a
restaurant and had installed a functioning grease trap; and (3) the doctrine of frustration of
purpose cannot be used where the frustrating event was reasonably foreseeable.
3. Damages and Remedies--calculation--present value
The trial court did not abuse its discretion in a breach of contract case by denying
defendant's motions for a new trial and amendment of judgment based on the jury's alleged
failure to follow the court's instructions on calculating damages based on present value, because:
(1) the amount of damages was the same amount requested by plaintiffs, and the trial court
considered and rejected defendant's argument in post-trial motions that this figure had not been
reduced to present value; (2) there is no requirement that a trial court instruct a jury on the
concept and calculation of present damages in cases such as this one; (3) it cannot be said with
certainty that the jury's calculation of damages made no adjustments for present value; and (4)
defendant provided the jury no evidence as to the present value of damages, nor did he request
that the court instruct the jury on a formula or even general guidelines for determining present
value.
4. Costs--attorney fees--breach of lease of real property
The trial court did not err in a breach of lease case by awarding attorney fees to plaintiff
under N.C.G.S. § 6-21.2, because: (1) the term evidence of indebtedness under the statute has
reference to any printed or written instrument, signed or otherwise executed by the obligors,
which evidences on its face a legally enforceable obligation to pay money; and (2) the Court of
Appeals has previously applied N.C.G.S. § 6-21.2 to disputes regarding the lease of real property.
Maupin Taylor, P.A., by John I. Mabe, Jr., Mark Whitson, and
Heather E. Bridgers, for plaintiff-appellee.
Hatch Little & Bunn, L.L.P., by John E. McKnight and David H.
Permar, for defendant-appellant.
HUNTER, Judge.
Lessee Issa F. Shaikh (defendant) appeals from the trial
court's denial of his summary judgment motion and motions for
directed verdict, for a new trial, for judgment notwithstanding the
verdict, and for amendment or modification of the judgment, as well
as the court's granting of WRI/Raleigh's (plaintiff) motion for
attorneys' fees. After careful review, we affirm the trial court's
rulings as to all.
In early 2002, defendant and plaintiff entered into a lease
for premises owned by plaintiff in a shopping center located at
3200 Avent Ferry Road in Raleigh. Defendant's intention was to
operate an Italian and Mediterranean restaurant on the premises.
After signing the lease, he approached public utility department
officials about the layout of the restaurant and learned that, due
to an ordinance passed by the City of Raleigh in 1999, the
restaurant was required to have a 1,000-gallon grease trap.
Defendant had operated restaurants before and was aware of the need
for a grease trap, but believed the minimum capacity for such a
trap was well below the 1,000-gallon mark (closer to 200 or 300
gallons). No grease trap or provisions for installing a grease
trap existed on the premises. When defendant learned of the need for a grease trap of this
size, he obtained estimates from plumbing engineers as to the cost
of modifying the premises to comply with the ordinance. The
engineers provided estimates but noted that, due to the layout of
the premises, any system created was likely to lead to repeated
clogging of the line. As a result, defendant decided he could not
open a restaurant on the premises and so tendered the keys to
plaintiff.
Plaintiff thereafter filed suit for breach of contract. A
jury found defendant liable in the amount of $158,542.13. Upon
motion by plaintiff, the court awarded court costs and attorneys'
fees to plaintiff. Defendant appeals.
[1] We first note that one of defendant's arguments is not
properly before this Court, and thus will not be addressed.
Defendant argues that the trial court erred in denying his motion
for summary judgment because no enforceable contract was created
between the parties.
This Court cannot consider an appeal of denial of the summary
judgment motion now that a final judgment on the merits has been
made:
Improper denial of a motion for summary
judgment is not reversible error when the case
has proceeded to trial and has been determined
on the merits by the trier of the facts,
either judge or jury.
To grant a review of the denial of the summary
judgment motion after a final judgment on the
merits . . . would mean that a party who
prevailed at trial after a complete
presentation of evidence by both sides with
cross-examination could be deprived of a
favorable verdict. This would allow a verdict
reached after the presentation of all the
evidence to be overcome by a limited forecast
of the evidence. In order to avoid such ananomalous result, we hold that the denial of a
motion for summary judgment is not reviewable
during appeal from a final judgment rendered
in a trial on the merits. . . .
Harris v. Walden, 314 N.C. 284, 286, 333 S.E.2d 254, 256 (1985).
See also Gregory v. Kilbride, 150 N.C. App. 601, 615, 565 S.E.2d
685, 695 (2002), disc. review denied, 357 N.C. 164, 580 S.E.2d 365
(2003); Pate v. State Farm Fire & Cas. Co., 136 N.C. App. 836, 837-
38, 526 S.E.2d 497, 498 (2000); Duke University v. Stainback, 84
N.C. App. 75, 77, 351 S.E.2d 806, 807 (1987). Thus, we cannot
address defendant's first argument.
[2] Defendant next argues that because his performance under
the contract was impossible, the court erred in denying his other
motions. Defendant links this argument to assignment of error 8,
which concerns only the failure of the jury to follow the court's
instructions in calculating damages. However, because the argument
does concern denial of the motions listed in the assignment of
error and does relate to a question submitted to the jury, we will
consider it here. N.C.R. App. P. 2.
The trial court found as a matter of law that the lease
agreement signed by the parties was valid, but submitted to the
jury the following question: Was the defendant's failure to
perform under the terms of the commercial lease excused by an event
which was not reasonably foreseeable? The jury answered [n]o,
and was then asked to consider the amount of damages to be awarded.
During the charge conference, the judge laid out a lengthy
example that he planned to give the jury regarding frustration of
purpose. He then gave that example to the jury in his instructions
to them, taking care to distinguish the defense of impossibility --
which he told them was not applicable here -- from the doctrine offrustration of purpose. Specifically, the judge told the jury that
the doctrine of impossibility did not apply because he had
determined that no evidence was presented to show that the
installation of a grease trap was completely impossible in the
context of this dispute.
Defendant argues that the doctrine of impossibility does apply
here, and thus should have been submitted to the jury, because he
could not have operated the restaurant he planned to operate in the
space. This argument misstates the meaning of the doctrine, which
applies when the purpose of a contract is somehow frustrated such
that no one could perform under it, not just the current parties:
Impossibility of performance is recognized in this jurisdiction as
excusing a party from performing under an executory contract if the
subject matter of the contract is destroyed without fault of the
party seeking to be excused from performance. Brenner v. School
House, Ltd., 302 N.C. 207, 210, 274 S.E.2d 206, 209 (1981). See
also Steamboat Co. v. Transportation Co., 166 N.C. 582, 82 S.E. 956
(1914) (applying doctrine to contract between ship owner and party
leasing it for ferrying purposes when ship was destroyed by fire
through no fault of parties); Barnes v. Ford Motor Co., 95 N.C.
App. 367, 382 S.E.2d 842 (1989) (affirming trial court's
instruction on doctrine of impossibility where subject matter of
lease, a tractor, was destroyed). That clearly is not the case
here, as the premises at issue still exist and at the time
defendant refused to perform were in the same condition as when the
contract was signed.
In addition, the trial court's decision was proper based on
the evidence presented at trial: Defendant argues that he couldnot have opened a restaurant on the premises at issue because it
was impossible to install the proper grease trap, but conclusive
evidence was presented that the current tenants of the property
were in fact running a restaurant and had installed a functioning
grease trap. Thus, the court was correct in concluding that the
doctrine of impossibility was not an issue for the jury because,
clearly, installing the trap was not impossible.
However, while defendant specifically defines its argument as
arising under the doctrine of impossibility, defendant's argument
is in fact rooted in the doctrine of frustration of purpose. This
is similar to, but distinct from, the doctrine of impossibility:
'Although the doctrines of frustration and
impossibility are akin, frustration is not a
form of impossibility of performance. It more
properly relates to the consideration for
performance. Under it performance remains
possible, but is excused whenever a fortuitous
event supervenes to cause a failure of the
consideration or a practically total
destruction of the expected value of the
performance. The doctrine of commercial
frustration is based upon the fundamental
premise of giving relief in a situation where
the parties could not reasonably have
protected themselves by the terms of the
contract against contingencies which later
arose.'
Brenner, 302 N.C. at 211, 274 S.E.2d at 209 (quoting 17 Am. Jur. 2d
Contracts § 401). This concept more accurately describes the
argument defendant advances here: That an investigation conducted
after the lease was signed revealed conditions that resulted in
'practically total destruction of the expected value of the
performance.' Id.
However, the doctrine of frustration cannot be used where the
frustrating event was reasonably foreseeable. Brenner, 302 N.C. at
211, 274 S.E.2d at 209. As such, the question submitted to thejury -- Was the defendant's failure to perform under the terms of
the commercial lease excused by an event which was not reasonably
foreseeable? -- correctly conveyed the doctrine of frustration of
purpose. During the charge conference, defendant did not object to
this question being submitted to the jury on either of the two
occasions when the court presented it to both parties. Presumably,
then, this question properly conveyed the issue that defendant
wanted the jury to answer. It also properly conveys the law. As
such, we cannot say the trial court erred on this point.
[3] Defendant's final two arguments are properly before the
Court. The first such argument is that the trial court erred in
denying defendant's motions for new trial and amendment or
modification of judgment
(See footnote 1)
because the jury failed to follow the
court's instructions on calculating damages -- specifically, that
the jury failed to reduce damages to present value. We disagree.
The instructions to the jury regarding present value in the
calculation of damages went as follows:
And, ladies and gentlemen, I further
instruct you that since the landlord in this
case seeks to recover damages for future rents
that were lost, any amount you award as future
damages for breach of contract must be reduced
to their present value because receiving a
smaller sum now is equal sum [sic] to be
received in the future.
In his closing statement, plaintiff's attorney gave
plaintiff's damages as exactly $158,542.13, based on calculations
from plaintiff's exhibit 19, which showed various financial dataconcerning the transactions between the two parties. One of
defendant's attorneys referred to reducing damages to present value
in his closing statement:
Now the third issue, and I think the
Judge will instruct you on this, when you of
course under this document [sic], the payments
that they're calculating are - is money that
they can expect to receive out to - to five
years from now . . . to 2010. And so that's
money that they are not entitled to receive
until five years from now. And so, the law is
that they're only entitled to the present
value of that future stream of revenue.
So, somehow you must figure a way to
discount that stream of revenue. And quite
frankly, nobody in here [sic] and there hasn't
been any evidence as to how you go about doing
it. I think there's something called a
discount rate or some way there - there are
typically formulas to reduce future revenues
to their present value. I - I quite frankly
don't know exactly what they are and there
isn't any evidence in here at all as to how
you are to do that. But in fact, the law
requires you to make some sort of adjustment
for that fact.
The jury returned a verdict in plaintiff's favor for exactly
$158,542.13. Defendant made a motion for new trial or amendment of
judgment under Rule 59 based on the jury's disregard of the trial
court's instructions as to damages.
Defendant argues that, because there is no evidence that this
number represents damages reduced to their present value, the
jury's calculations are invalid and thus the case must be remanded
for new trial. We disagree.
It has been long settled in our
jurisdiction that an appellate court's review
of a trial judge's discretionary ruling either
granting or denying a motion to set aside a
verdict and order a new trial is strictly
limited to the determination of whether the
record affirmatively demonstrates a manifest
abuse of discretion by the judge. . . .
. . .
[I]t is plain that a trial judge's
discretionary order pursuant to G.S. 1A-1,
Rule 59 for or against a new trial upon any
ground may be reversed on appeal only in those
exceptional cases where an abuse of discretion
is clearly shown.
Worthington v. Bynum and Cogdell v. Bynum, 305 N.C. 478, 482-84,
290 S.E.2d 599, 602-03 (1982); see also Roary v. Bolton, 150 N.C.
App. 193, 194, 563 S.E.2d 21, 22 (2002) ([g]ranting a motion for
a new trial under Rule 59 is directed to the discretion of the
trial court. The trial court's ruling will thus not be disturbed
upon appeal without a finding of abuse of discretion) (citations
omitted). An abuse of discretion occurs when the trial court's
ruling 'is so arbitrary that it could not have been the result of
a reasoned decision.' Chicora Country Club, Inc. v. Town of
Erwin, 128 N.C. App. 101, 109, 493 S.E.2d 797, 802 (1997) (quoting
White v. White, 312 N.C. 770, 777, 324 S.E.2d 829, 833 (1985)).
As noted above, the amount of the judgment was the same amount
requested by plaintiffs. The trial court considered and rejected
defendant's argument in post-trial motions that this figure had not
been reduced to present value. We cannot say that this ruling is
an exceptional case that rises to the level of a manifest abuse
of discretion by the trial court.
This Court is aware of no requirement that a trial court
instruct a jury on the concept and calculation of present damages
in cases such as the one at hand. Regardless, it cannot be said
with certainty that the jury's calculation of damages made no
adjustments for present value and thus disregarded the instruction.
Both sides presented evidence as to the amount of damages, such as
the possibility of plaintiff's being able to re-let the premises tonew tenants (thus lowering damages) as well as the possibility of
the current tenants abandoning the premises before expiration of
their lease (thus increasing damages). Further, defendant provided
the jury no evidence as to the present value of damages, nor did he
request that the court instruct the jury on a formula or even
general guidelines for determining present value. As such, we see
no support for defendant's claim at this late date that the jury
failed to properly calculate the present value of damages.
Defendant cites Circuits Co. v. Communications, Inc., 26 N.C.
App. 536, 216 S.E.2d 919 (1975), for the tenet that when a jury
miscalculates damages by disregarding an instruction of the trial
court, the appropriate remedy is remand for a new trial. However,
in Circuits, the trial court made a finding of fact that the jury
had disregarded its instructions and the trial court modified the
amount of the award itself to conform it to those instructions. It
is that act on which the Court based its reversal. Id. at 540, 216
S.E.2d at 922 ([w]e find nothing in the new Rules of Civil
Procedure which would grant to the court the authority to modify
the verdict by changing the amount of the recovery. . . . There
must be a new trial on the issue of damages). This case is
inapposite to the case sub judice, where the trial court made no
such modification to the jury's decision and in fact refused to
disturb it. We find no error.
[4] Defendant next argues that the trial court erred in
granting attorneys' fees based on N.C. Gen. Stat. . 6-21.2 (2005)
because the statute is inapplicable. We disagree.
Upon motion by plaintiff, the trial court ordered defendant to
pay plaintiff attorneys' fees in the amount of $23,781.32 pursuantto N.C. Gen. Stat. . 6-21.2, which states that [o]bligations to
pay attorneys' fees upon any note, conditional sale contract or
other evidence of indebtedness . . . shall be valid and
enforceable, and collectible as part of such debt[.] Defendant
appeals this order on the grounds that a lease is not evidence of
indebtedness under the statute.
Our Supreme Court has held that even where parties have
contractually obligated themselves to pay attorneys' fees, there
must still be statutory authority for their recovery. Enterprises,
Inc. v. Equipment Co., 300 N.C. 286, 289, 266 S.E.2d 812, 814
(1980) (the general rule has long obtained that a successful
litigant may not recover attorneys' fees . . . unless such a
recovery is expressly authorized by statute). Thus, even though
attorneys' fees are expressly provided for by the lease contract,
they must also be authorized by statute.
Our Supreme Court has determined that the language of N.C.
Gen. Stat. . 6-21.2 is to be interpreted broadly: [W]e hold that
the term 'evidence of indebtedness' as used in G.S. 6-21.2 has
reference to any printed or written instrument, signed or otherwise
executed by the obligor(s), which evidences on its face a legally
enforceable obligation to pay money. Enterprises, Inc., 300 N.C.
at 294, 266 S.E.2d at 817. In addition, this Court has applied
N.C. Gen. Stat. § 6-21.2 to disputes regarding the lease of real
property. RC Associates v. Regency Ventures, Inc., 111 N.C. App.
367, 372, 432 S.E.2d 394, 397 (1993). Thus, we see no error in the
trial court's awarding of attorneys' fees on the basis of this
statute. Because the trial court did not err in denying defendant's
motions for new trial and amendment of judgment based on the jury's
calculation of damages, or in awarding attorneys' fees to plaintiff
based on statute, we affirm.
Affirmed.
Chief Judge MARTIN and Judge STROUD concur.
*** Converted from WordPerfect ***