Link to original WordPerfect file
Link to PDF file
How to access the above link?
Return to nccourts.org
Return to the Opinions Page
All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
VECELLIO & GROGAN, INC., Plaintiff, v. PIEDMONT DRILLING &
BLASTING, INC., and RANGER INSURANCE COMPANY, Defendants
NO. COA06-887
Filed: 1 May 2007
1. Construction Claims_blasting during sewer construction_cause of damage_issue of
fact
Summary judgment on a strict liability claim arising from blasting during sewer
construction was improper because there was a genuine issue of material fact as to the cause of
the damage. Plaintiff argued that the cause was improper or excessive use of blasting materials
by defendant; defendant argued it was an improper sequence of events (blasting after a first
pipeline was laid) to which plaintiff had consented.
2. Construction Claims_sewer line blasting_contract and negligence claims_summary
judgment
Summary judgment was improperly entered for defendant on claims for breach of
contract and negligence that arose from a sewer construction project. Plaintiff asserted breaches
of contract about which there were material issues of fact other than the contractual indemnity
clause; precedent cited by defendant did not hold that strict liability and negligence are never
valid claims between parties to a contract; and plaintiff brought claims with allegations of
damage to property other than that which was the subject of the contract, which is a valid basis
for a complaint in tort.
3. Contract_indemnification clause_redacted
The trial court erred by entering summary judgment for defendant on a contract
indemnification claim. Assuming that a phrase in the contract impermissibly indemnified
plaintiff against its own negligence, the problem may be solved by removing the offending
phrase; the clause, when redacted, simply states the common law rule of strict liability.
4. Appeal and Error_preservation of issues_inclusion of documents in record
An appellate argument concerning the quashing of a subpoena was not preserved where
the court sealed the documents in question but plaintiff did not did not include a copy of the
documents in the record.
Appeal by plaintiff from order entered 13 February 2006 by
Judge Henry W. Hight, Jr., and from order entered 3 August 2004 by
Judge Robert H. Hobgood, both entered in Wake County Superior
Court. Heard in the Court of Appeals 21 February 2007.
Parker, Poe, Adams & Bernstein L.L.P., by Charles C. Meeker,
Brian D. Darer, Catherine B. Arrowood and Melissa S.
Daigneault, for plaintiff-appellant.
Young Moore & Henderson P.A., by Walter E. Brock, Jr., and Jay
Tobin, for defendant-appellee Piedmont Drilling & Blasting,
Inc.
Johnston, Allison & Hord, P.A., by Greg C. Ahlum, for amicus
curiae Carolinas Associated General Contractors of America,
Inc.
LEVINSON, Judge.
Plaintiff appeals from summary judgment entered in favor of
defendants, and from an order granting defendant's motion to quash
its subpoena served on Forensic Analysis & Engineering Corporation.
We reverse in part and dismiss in part.
The relevant facts are summarized as follows: Plaintiff,
Vecellio & Grogan, Inc. (V&G), is a West Virginia corporation doing
business as a general contractor on road construction contracts.
In 2002 V&G was under contract with the North Carolina Department
of Transportation (NCDOT) to construct part of a road improvement
project for North Carolina Highway 64. The contract required V&G
to install two below-ground sewer lines. These lines, designated
Sewer Lines A and B, were parallel to each other and about thirty
feet apart. Defendant, Piedmont Drilling & Blasting, Inc.
(Piedmont), is a North Carolina corporation that provides drilling
and blasting services. In October 2002 V&G executed a subcontract
with Piedmont, wherein Piedmont agreed to drill and blast the
trenches for Sewer Lines A and B. V&G subcontracted with another
company to construct the actual sewer lines.
On 1 April 2003 Piedmont was blasting the trench for Sewer
Line B. Sewer Line A was partially completed, and piping wasinstalled between two points known as manholes 3 and 4. Piedmont
set off an explosion in Sewer Line B which caused damage to both
Sewer Lines A and B. The present appeal arises from V&G's claim
that Piedmont is liable for the damages resulting from its blasting
in Sewer Line B.
Following the explosion on 1 April 2003, the parties contacted
Ranger Insurance Company (Ranger), the insurance company that had
insured Piedmont. Ranger hired Forensic Analysis & Engineering
Corporation (FAEC) to investigate the matter. On 13 May 2003
Ranger paid V&G $600,000 with a check marked Advance Payment for
Property Damages. Neither Ranger nor Piedmont would pay V&G any
more money, and on 24 November 2003 V&G filed suit against Piedmont
and Ranger for damages not covered by Ranger's advance payment
check. V&G sought damages based on strict liability, negligence,
breach of contract, and contractual indemnity; additionally,
plaintiff sought a declaratory judgment regarding Ranger's
obligations. In an amended answer and counterclaim, Piedmont
denied the material allegations of the complaint and brought a
counterclaim for unpaid labor.
On 23 February 2004 V&G issued a subpoena to FAEC for
documents pertaining to the blast. Ranger and Piedmont moved to
quash the subpoena; their motions were granted by the trial court
in August 2004.
Ranger moved for summary judgment in July 2005. The parties
agreed to entry of summary judgment, under the terms of which
Ranger was ordered to provide coverage for all non-liquidateddamages for which Piedmont was ultimately found liable. Ranger is
not a party to this appeal.
In January 2006 V&G moved for partial summary judgment on the
issue of liability, and Piedmont moved for summary judgment on all
of plaintiff's claims. By order entered 13 February 2006, the
trial court granted Piedmont's summary judgment motion, denied
V&G's summary judgment motion, and dismissed all of V&G's claims.
Thereafter, Piedmont dismissed its counterclaim, allowing V&G to
appeal the trial court's summary judgment order. Plaintiff also
appeals the trial court's order quashing its subpoena for FAEC.
Standard of Review
Summary judgment is appropriate 'if the pleadings,
depositions, answers to interrogatories, and admissions on file,
together with the affidavits, if any, show that there is no genuine
issue as to any material fact and that [a] party is entitled to a
judgment as a matter of law.' N.C. Gen. Stat. § 1A-1, Rule 56(c)
(2005). On appeal of a trial court's allowance of a motion for
summary judgment, we consider whether, on the basis of materials
supplied to the trial court, there was a genuine issue of material
fact and whether the moving party is entitled to judgment as a
matter of law. Evidence presented by the parties is viewed in the
light most favorable to the non-movant. Summey v. Barker, 357
N.C. 492, 496, 586 S.E.2d 247, 249 (2003) (citation omitted).
Strict Liability for Ultra Hazardous Activities
[1] Plaintiff argues first that the trial court erred by
dismissing its claim for damages based on defendant's being
strictly liable for damages caused by its blasting.
Plaintiff correctly asserts that blasting with explosives is
deemed an ultra hazardous activity, for which strict liability is
imposed. Insurance Co. v. Blythe Brothers Co., 260 N.C. 69, 131
S.E.2d 900 (1963). In Blythe, plaintiffs sought compensation for
damages caused by defendant's use of explosives to blast a tunnel
for a sewer line. The Court held:
Blasting is considered intrinsically
dangerous; it is an ultrahazardous activity .
. . since it requires the use of high
explosives and since it is impossible to
predict with certainty the extent or severity
of its consequences. . . . Blasting
operations are dangerous and must pay their
own way. . . . The principle of strict or
absolute liability for extrahazardous activity
thus is the only sound rationalization.
Id. at 74, 117 S.E.2d at 904 (quoting Wallace v. A. H. Guion &
Company (S.C.), 237 S.C. 349, 354, 117 S.E.2d 359, 361 (1960))
(citations omitted). North Carolina cases decided after Blythe
have uniformly held that blasting is an ultra hazardous activity
for which the actor is strictly liable. See, e.g., Kinsey v.
Spann, 139 N.C. App. 370, 374, 533 S.E.2d 487, 491 (2000), in which
this Court reiterated that:
Ultrahazardous activities are those that are
so dangerous that even the exercise of
reasonable care cannot eliminate the risk of
serious harm. In such cases, the employer is
strictly liable for any harm that proximately
results. In other words, he is liable even if
due care was exercised in the performance of
the activity. In North Carolina, onlyblasting operations are considered
ultrahazardous.
(citing Woodson v. Rowland, 329 N.C. 330, 350-51, 407 S.E.2d 222,
234 (1991)) (internal quotation marks omitted).
Defendant concedes that blasting is subject to strict
liability, but contends that in the instant case summary judgment
was properly granted on plaintiff's strict liability claim.
Defendant argues that recovery is barred by plaintiff's assumption
of risk. Plaintiff argues that assumption of risk is not even a
permissible defense to a claim based on strict liability, and that
even if it were available as a defense that plaintiff did not
assume the risk of the 1 April 2003 blast.
As this case appears before us on appeal from summary
judgment, the question before us is whether a genuine issue of
material fact exists. It is clear from the record that the parties
disagree as to the cause of the damage resulting from the blast:
plaintiff argues that the cause was defendant's improper or
excessive use of blasting materials
; defendant argues that it was
the improper sequence of events (i.e., blasting after the other
pipeline had been laid), and that the sequence was a change from
that agreed upon by the parties, but a change to which plaintiff
consented. These arguments present questions of fact for a jury to
resolve, and as such summary judgment was improper.
No North Carolina cases directly address the point of how
assumption of the risk relates to a claim based on defendant's
strict liability for damages arising from an ultra hazardous
activity. Moreover, because we cannot know whether the evidencepresented at trial on remand will even present a factual issue of
assumption of risk, the issue of its availability as a defense in
this case is not before us at this time.
For this reason, summary judgment on plaintiff's strict
liability claim was improper.
Claims for Negligence and Breach of Contract
[2] Defendant argues that summary judgment was properly
granted on plaintiff's breach of contract and negligence claims.
We disagree.
Defendant contends that the only contractual provision at
issue is the indemnification clause, which defendant asserts is
invalid and unenforceable. However, plaintiff's complaint
includes,
inter alia, allegations that:
. . . .
10. Pursuant to Section 1.10 of the Subcontract,
Piedmont agreed to adequately and properly
perform its work so as to avoid damage to
persons or property. . . .
. . . .
14. The blast set off by Piedmont on April 1, 2003
was excessive and improperly conducted. Upon
information and belief, Piedmont improperly
used too much explosive in setting off the
blast.
. . . .
26. V&G incorporates the allegations contained in
paragraphs 1-25 of the Complaint as set forth
in full herein.
27. Piedmont has breached the Subcontract by,
among other things, failing to adequately and
properly protect the blasting work to avoid
injury or damage to property.
We conclude that plaintiff asserts other breaches of contract in
addition to the indemnification clause, and that there are issues
of material fact pertaining to these allegations.
Defendant also asserts that principles of strict liability
and negligence are inapplicable due to the contractual
relationship of the parties. Specifically, defendant cites Trull
v. Well Co., 264 N.C. 687, 142 S.E.2d 622 (1965), for the
proposition that strict liability is never applicable as between
contracting parties. Defendant mischaracterizes the holding of
Trull.
In Trull, plaintiff-homeowner sought damages from the
vibrations of well-digging machinery allegedly caused by defendant
well-driller's negligence. The Court held that plaintiff had not
proven negligence, and declined to extend the definition of ultra
hazardous endeavors to include well-drilling. In dicta, the Court
observed that, even if it had ruled that drilling was ultra
hazardous, it did not appear that the plaintiff would necessarily
be entitled to recovery, and that plaintiff had not produced
evidence of the parties' respective obligations or the issue of
proximate cause. This does not constitute a holding that strict
liability and negligence are never valid claims between parties to
a contract.
Regarding plaintiff's negligence claim, defendant argues the
trial court properly granted summary judgment on the grounds that
the negligence claim is barred by their contractual relationship.
Defendant cites Ports Authority v. Roofing Co., 294 N.C. 73, 240S.E.2d 345 (1978), in support of this argument. However, Ports
Authority acknowledged that there are many decisions of this and
other courts holding a promisor liable in a tort action for a
personal injury or damage to property proximately caused by his
negligent, or wilful, act or omission in the course of his
performance of his contract. Id. at 81, 240 S.E.2d at 350. The
opinion sets out four general categories of such cases, while
noting that it may well be that this enumeration of categories in
which a promisor has been held liable in a tort action by reason of
his negligent, or wilful, act or omission in the performance of his
contract is not all inclusive. Id. at 82-83, 240 S.E.2d at 351.
In the instant case, plaintiff has brought claims based both
on negligence and breach of contract. The allegations in its
complaint allege damage to property other than that which was the
subject of the contract between the parties, that being one of the
categories recognized in Port Authorities as a valid basis for a
complaint in tort. Moreover, there are material issues of fact
regarding both the breach of contract and negligence claims. We
conclude that summary judgment was improperly entered on these
claims.
Contractual Indemnification
[3] Plaintiff argues that the trial court erred by not
granting its motion for summary judgment damages based on an
indemnification clause in the contract between plaintiff and
defendant. The term 'indemnity clause' is defined by Black's Law Dictionary
784 (8th ed. 2004) as a contractual provision in which one party
agrees to answer for any specified or unspecified liability or harm
that the other party might incur. Under N.C. Gen. Stat. § 22B-1
(2005), a construction contract generally may not include a
provision whereby a party is indemnified for its own negligence.
The statute states in pertinent part that:
Any promise or agreement in . . . a contract
or agreement relative to . . . construction .
. . [of a] highway . . . purporting to
indemnify or hold harmless the promisee . . .
against liability for damages . . .
proximately caused by or resulting from the
negligence, in whole or in part, of the
promisee . . . is against public policy and is
void and unenforceable. . . .
The indemnity clause at issue herein states in relevant part that:
41. INDEMNITY. To the fullest extent permitted by
law, Subcontractor shall indemnify and hold
harmless the Owner and Contractor . . . from
and against claims, damages, losses and
expenses . . . arising out of or resulting
from performance of Subcontractor's Work
regardless of whether or not such claim,
damage, loss or expense is caused in part by a
party indemnified hereunder. . . .
Defendant contends that this clause is invalid and unenforceable
because the last phrase, regardless of whether or not such claim,
damage, loss or expense is caused in part by a party indemnified
hereunder[,] serves to indemnify plaintiff against its own
negligence. We conclude that even assuming, arguendo, that the
indemnification clause violates G.S. § 22B-1, this problem may be
solved by simply removing the offending phrase. The indemnification clause starts with the phrase [t]o the
fullest extent permitted by law, which restricts its application
to those situations permitted by law. Indemnification is further
limited to damages arising out of or resulting from performance of
Subcontractor's Work[.] Thus, on its face the indemnity clause is
self-limiting: indemnification is restricted to damages (1) that
arise or result from performance of defendant's work; and (2) that
are permitted by law.
If the last phrase were removed, the clause would state:
41. INDEMNITY. To the fullest extent permitted by
law, Subcontractor shall indemnify and hold
harmless the Owner and Contractor . . . from
and against claims, damages, losses and
expenses . . . arising out of or resulting
from performance of Subcontractor's Work[.]
Significantly, common law establishes that defendant is
strictly liable for damages arising from blasting, even without an
indemnity clause. Accordingly, the indemnity clause when redacted
simply states the common law rule of strict liability.
We also note that in International Paper Co. v. Corporex
Constructors, Inc., 96 N.C. App. 312, 315, 385 S.E.2d 553, 555
(1989), this Court considered a similar indemnification clause
stating in relevant part:
The Builder shall indemnify and hold harmless
the Owner . . . against all claims, losses,
and expenses . . . arising out of or resulting
from the performance of the work, provided
that any such claim, damage, loss or expense .
. . is caused in whole or in part by any
negligent act or omission of the Builder . . .
regardless of whether or not it is caused in
part by a party indemnified hereunder.
This Court held that removing the phrase regardless of whether or
not it is caused in part by a party indemnified hereunder would
make the clause enforceable:
By striking the offending language the Court
does not rewrite the contract or substitute
its own terms in the provision for those of
the parties. We merely sever the portion that
is void as against public policy from an
otherwise valid indemnity provision.
Id. at 316, 385 S.E.2d at 555. As in International Paper, any
problem with the indemnity clause can be cured by removal of the
offending phrase. Accordingly, we conclude that the trial court
erred by entering summary judgment in favor of defendant on
plaintiff's claim based on contractual indemnification. Assuming
that the evidence at trial were to show that the contract is valid
in all other respects, the indemnification clause may be enforced.
_______________________
[4] Finally, plaintiff argues that the trial court erred by
quashing its subpoenas for FAEC. We conclude that plaintiff failed
to properly preserve this issue for our review.
In February 2004 plaintiff issued a document subpoena for
FAEC, seeking [a]ll documents in your possession, custody, or
control, related to the [NCDOT] Project No. 8.1402210, . . .
including, but not limited to, all correspondence with Piedmont
Drilling & Blasting, Inc., Ranger Insurance Company, Park
Construction Corp., and Vecellio & Grogan, Inc. FAEC produced
certain documents from its file, without objection from Piedmont.
However, in regards to the remainder of FAEC's file, Piedmont moved
to quash the subpoena, arguing that it is improper discovery ofexpert consultant materials under Rule 26; that it is overly broad
and unduly burdensome; that it encompasses materials prepared in
anticipation of litigation for Piedmont. Piedmont's motion to
quash was granted by the trial court in an order concluding in
pertinent part that:
The Court has . . . reviewed the privilege log
and the documents actually produced to
plaintiff from the files of [FAEC] . . . and
has conducted an
in camera review of those
documents withheld from production in response
to the subpoena.
Based upon the foregoing, the Court finds and
concludes that the documents withheld from
production in response to the subpoena were
documents prepared by [FAEC] . . . in
anticipation of potential litigation with the
plaintiff; . . . and that the materials
withheld from production are protected by the
work-product doctrine. . . .
It is, therefore, ORDERED that the objections
of the defendants to the subpoena are
sustained and the motions to quash are allowed
as to those documents withheld and listed in
the privilege log, and that the documents
presented for
in camera review shall be sealed
and maintained with the case file. . . .
On appeal, plaintiff challenges the trial court's ruling on
defendant's motion to quash the subpoena. However:
Rule 9(a) [of the North Carolina Rules of
Appellate Procedure] provides that 'copies of
all other papers filed and statements of all
other proceedings had in the trial court which
are necessary to an understanding of all
errors' should be included in the record on
appeal. N.C.R. App. [P]. 9(a)(1)(j) (2005).
As [plaintiff] failed to include a copy of the
[documents withheld by FAEC], we do not
address this issue.
County of Jackson v. Nichols, 175 N.C. App. 196, 201, 623 S.E.2d
277, 281 (2005) (emphasis added) (citations omitted). Plaintiff's
appeal from this order is dismissed.
We reverse the trial court's entry of summary judgment in
favor of defendant, and dismiss plaintiff's appeal from the order
quashing its subpoena.
Reversed in part and Dismissed in part.
Judges HUNTER and McCULLOUGH concur.
*** Converted from WordPerfect ***