NO. COA06-37
NORTH CAROLINA COURT OF APPEALS
Filed: 1 May 2007
CAPE FEAR MEDICAL CENTER, L.L.C.,
and MED CARE OF NORTH CAROLINA,
P.L.L.C., a/k/a KASTNER URGENT
CARE FACILITY,
Plaintiffs,
v
.
New Hanover County
No. 04 CVS 0813
S.K. ANDERSON CONSTRUCTION CO.,
INC.,
Defendant and Third-Party
Plaintiff,
v.
BARKER-GUIDRY ARCHITECTS, INC.,
MOORE'S GLASS SERVICE, INC.,
LARRY & DEENA, INC., d/b/a
HINNANT MASONRY CO., INC.,
MELVIN STUCCO COMPANY, INC.,
CAROLINA COMMERCIAL FLOORCOVERING,
INC., f/d/b/a CAROLINA COMMERCIAL
FLOORCOVERING, LLC, and MATTHEWS
& SONS FLOORS, INC., d/b/a
MATTHEWS & SONS FLOOR MAINTENANCE,
Third-Party Defendants.
Appeal by Third-Party Plaintiff from order entered 4 October
2005 by Judge Russell J. Lanier, Jr., in New Hanover County
Superior Court. Heard in the Court of Appeals 17 August 2006.
Maupin Taylor, P.A., by H. Mark Hamlet, for Third-Party
Plaintiff-Appellant.
Wallace, Morris, Barwick, Landis & Stroud, P.A., by Kimberly
Connor Benton, for Third-Party Defendant-Appellee Moore's
Glass Service, Inc.
Anderson, Johnson, Lawrence, Butler & Bock, L.L.P., by Steven
C. Lawrence, for Third-Party Defendant-Appellee Larry & Deena,
Inc., d/b/a Hinnant Masonry Co., Inc.
STEPHENS, Judge.
Third-Party Plaintiff-Appellant S.K. Anderson Construction
Co., Inc. (Anderson) was the general contractor for the
construction of Plaintiffs' urgent care facility. As general
contractor, Anderson orally contracted with Third-Party Defendant-
Appellee Larry & Deena, Inc., d/b/a Hinnant Masonry Co., Inc.
(Hinnant Masonry or Hinnant) for the provision and installation
of all masonry material required for the facility's exterior.
Similarly, Anderson orally contracted with Third-Party Defendant-
Appellee Moore's Glass Service, Inc. (Moore's Glass) for the
provision and installation of the facility's windows. During the
facility's construction, and before the windows had been installed,
a large amount of water entered the building during a heavy
rainstorm. Though Anderson completed all construction on the
facility in March 2001, Moore's Glass completed its work not later
than 31 January 2001, and Hinnant Masonry completed its work not
later than 4 February 2001. Plaintiffs moved into the facility on
12 March 2001.
Within a year of moving into the facility, Plaintiffs
experienced moisture-related problems in the building. In March
2003, Plaintiffs noticed that mold was growing on the exterior of
the building and that the mold was coming through the sheetrock
into the interior of the building. In August 2003, Plaintiffs
notified Anderson that there was moisture intrusion in the
building. On 5 March 2004, Plaintiffs filed a complaint against
Anderson alleging negligence and breach of contract in Anderson'sconstruction of the facility relating to the moisture problems.
Anderson filed its Answer on 10 May 2004 denying Plaintiffs'
claims.
On 7 June 2004, Anderson amended its Answer to include a
third-party complaint against six subcontractors it had employed in
its construction of Plaintiffs' facility, including Hinnant Masonry
and Moore's Glass. Though Anderson continued to deny Plaintiffs'
claims, Anderson sought relief in the form of contribution and
indemnification from the subcontractors in the event Anderson was
found liable to Plaintiffs. Anderson advanced three claims for
relief against Hinnant Masonry: breach of contract, breach of
warranty, and negligence. Anderson advanced two claims for relief
against Moore's Glass: breach of warranty and negligence. On 24
June 2004, Anderson again amended its Answer to indicate that the
relief sought included damages in an amount greater than $10,000
under all of its claims against Hinnant Masonry and Moore's Glass.
Upon Anderson's motion for summary judgment as to Plaintiffs'
claims, and upon Hinnant's and Moore's Glass's motions for summary
judgment as to Anderson's claims, the trial court granted summary
judgment in favor of Hinnant and Moore's Glass on 4 October 2005,
concluding there existed no genuine issue[s] of material fact[.]
The court denied Anderson's motion for summary judgment against
Plaintiffs. On appeal, though Anderson abandons its negligence
claims against both Hinnant Masonry and Moore's Glass, Anderson
argues that the trial court erred in dismissing its breach of
contract claim against Hinnant Masonry and its breach of warrantyclaims against both Hinnant Masonry and Moore's Glass.
(See footnote 1)
For the
reasons set forth below, we affirm the court's grant of summary
judgment.
I. SUMMARY JUDGMENT STANDARD
Anderson argues that neither Hinnant Masonry nor Moore's Glass
is entitled to summary judgment on the breach of contract or breachof warranty claims because neither Hinnant Masonry nor Moore's
Glass established both that no triable issue exists and that any
affirmative defense barred Anderson's claim. In response, Hinnant
and Moore's Glass argue that the applicable statutes of limitations
operate as complete bars to Anderson's claims. We agree with
Hinnant and Moore's Glass.
Generally, the statute of limitations for a breach of contract
action is three years. N.C. Gen. Stat. § 1-52(1) (2005). A cause
of action for breach of contract accrues on the date of the breach,
at which time the three years begin to run.
Miller v. Randolph,
124 N.C. App. 779, 478 S.E.2d 668 (1996). As Anderson itself
points out in its brief, [t]he statute of limitations for breach
of warranty is also three years,
accruing at breach.
Kaleel
Builders, Inc. v. Ashby, 161 N.C. App. 34, 44, 587 S.E.2d 470, 477
(2003) (emphasis added) (citation omitted),
disc. review denied,
358 N.C. 235, 595 S.E.2d 152 (2004). The result in
Kaleel mandates
the proper outcome in the case
sub judice.
In
Kaleel, a couple hired a general contractor to build their
house. The general contractor, in turn, hired several
subcontractors to complete various aspects of the job. Work on the
house was halted in the fall of 1996, and thereafter the couple
filed a demand for arbitration against the general contractor for
allegedly defective construction of the house, including the work
of the subcontractors. In July 2001, the general contractor filed
a complaint against the subcontractors alleging breach of contract,
breach of warranty, and negligence. This Court held that under theprovisions of N.C. Gen. Stat. § 1-52(1), the applicable statutes of
limitations began to run on the breach of contract and breach of
warranty claims not later than the fall of 1996, when construction
stopped, and that, therefore, the general contractor's claims were
time-barred. We reach the same conclusion in the case at bar
.
In this case, Anderson alleged that Hinnant Masonry breached
the contract in that Hinnant:
a. failed to take proper precautions to
ensure that the construction defects would not
occur;
b. failed to follow general
construction and installation principles in
the design and/or installation of the masonry
and brick that it applied to the Cape Fear
Medical Center so as to protect the building
from water and moisture intrusion, including
but not limited to the installation of
sealants;
c. inadequately supervised the
installation of the masonry and brick at the
Cape Fear Medical Center;
d. failed to perform its contract in a
workmanlike manner; and
e. failed in such other ways as will be
shown at the trial of this action.
Anderson also alleged that Hinnant Masonry breached its warranties
in that Hinnant:
a. failed to select masonry and bricks
that were adequate to prevent moisture from
entering through any wood substructure of the
construction;
b. failed to follow general masonry
installation principles in the application of
the masonry and brick in the construction,
including but not limited to the installation
of sealants;
c. inadequately supervised the
application of the brick and masonry on the
building; and
d. breached its warranties in other
ways as will be shown at the trial of this
action.
As to Moore's Glass, Anderson alleged that Moore's Glass breached
its warranties in that Moore's Glass:
a. failed to properly install the
windows so as to protect the building from the
weather;
b. b. failed to install or properly
install flashing, weather-stripping, glazing
and sealant joints around the window openings
so as to protect the building from the weather
and water intrusion; and
c. failed to manufacture and/or supply
aluminum window units that were adequate to
prevent moisture from entering the building,
thereby causing damage; [and]
d. breached its warranties in such
other ways as will be shown at the trial of
this action.
If Hinnant Masonry breached its contract or any warranty with
Anderson as alleged, such breach must have occurred not later than
4 February 2001, the last date upon which Hinnant performed any
work under the contract. If Moore's Glass breached any warranty
with Anderson as alleged, the last date on which a breach could
have occurred was 31 January 2001. Anderson first filed its claims
against Hinnant and Moore's Glass on 7 June 2004, more than three
years after the claims arose. The applicable statutes of
limitations, therefore, operate as complete bars to Anderson's
claims against both Hinnant Masonry and Moore's Glass.
Anderson, however, argues that the statutes of limitations did
not accrue until the moisture intrusion became apparent or
reasonably should have become apparent to Anderson. In advancing
this argument, Anderson mistakenly relies on the case of
Pembee
Mfg. Corp. v. Cape Fear Constr. Co., 313 N.C. 488, 329 S.E.2d 350
(1985).
Pembee, however, involved the application of N.C. Gen.Stat. § 1-52(16), which states, in pertinent part, that for . . .
physical damage
to claimant's property, the cause of action . . .
shall not accrue until . . . [such damage]
becomes apparent or
ought reasonably to have become apparent
to the claimant, whichever
event first occurs. N.C. Gen. Stat. § 1-52(16) (2005) (emphasis
added). We find that N.C. Gen. Stat. § 1-52(1), not N.C. Gen.
Stat. § 1-52(16), is the controlling statute under these facts as
any damage that may have occurred was to Plaintiffs' facility, not
Anderson's.
Because we find that the statutes of limitations operate as
complete bars to Anderson's breach of contract and breach of
warranty claims, we need not address Anderson's argument that
Hinnant Masonry and Moore's Glass failed to establish that no
triable issues exist on the claims. Also, we need not address
Anderson's assertion that it is entitled to indemnification from
both Hinnant and Moore's Glass since such relief arises solely out
of its claims for breach of contract and breach of warranty.
The judgment of the trial court is AFFIRMED.
Judges STEELMAN and LEVINSON concur.
Report per Rule 30(e).
Footnote: 1