All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
ASSOCIATED INDUSTRIAL CONTRACTORS, INC. v. FLEMING ENGINEERING,
INC.
Construction Claims_-negligence--error in surveying construction work
The trial court did not err in a negligence case arising out of a dispute over
surveying construction work performed on a building by inferring that defendant company, who
conducted an electronic survey and identified the points where the wall columns for the addition
should be erected, was more likely than not the source of error because: (1) the evidence showed
the south wall was parallel to the north wall but not at the correct angle, and it is unlikely that
defendant properly plotted the points in a straight parallel line but that plaintiff then incorrectly
placed the columns on different points which created a skewed but nonetheless straight line; (2)
if plaintiff's negligence caused the line to be skewed it is highly probable that the line also would
not be straight; and (3) the evidence does not show defendant checked the survey points to ensure
the north and south walls of the addition would form parallel straight lines.
Justice EDMUNDS dissenting.
Justice PARKER joins in the dissenting opinion.
Appeal pursuant to N.C.G.S. § 7A-30(2) from the
decision of a divided panel of the Court of Appeals, 162 N.C.
App. 405, 590 S.E.2d 866 (2004), affirming a judgment entered
31 May 2002 and an order entered 17 June 2002 by Judge John O.
Craig, III in Superior Court, Rockingham County. Heard in the
Supreme Court 6 December 2004.
Parker, Poe, Adams & Bernstein L.L.P., by R. Bruce
Thompson II, for plaintiff-appellee.
Hedrick, Eatman, Gardner & Kincheloe, L.L.P., by C.J.
Childers, for defendant-appellant.
WAINWRIGHT, Justice.
The present case stems from a dispute over surveying
construction work performed on a building in Swepsonville, North
Carolina.
Honda Manufacturing hired plaintiff, Associated
Industrial Contractors, Inc., to build an addition to Honda's diecast facility. The addition was planned to be eighty feet wide
and one hundred twenty feet long and sit on the west side of the
die cast facility. The building plans required a ten ton bridge
crane to run from the existing Honda building through the
addition on the same runway. To accommodate this crane, the
addition had to be perfectly square with the die cast facility.
Existing buildings surrounding the location prohibited plaintiff
from using traditional surveying methods to identify the points
for the addition's columns. Moreover, windy conditions at the
site prevented plaintiff from surveying the column points with a
plumb bob (a weight attached to a line used for verifying true
vertical alignment). Because of these complications, plaintiff
hired defendant Fleming Engineering, Inc. to conduct an
electronic survey and identify the points where the wall columns
for the addition should be erected.
On 22 December 2000, Johnnie Register, Jr., one of
defendant's employees, conducted the electronic survey. Lanny
Joyce, plaintiff's superintendent for the Honda addition, told
Register that the survey had to set points that were square to
the existing die cast building. Register testified that he
conducted the survey with an electronic transit. According to
Register, this device has a scope that allows the operator to see
string lines on a plumb bob a couple of hundred feet away. The
device also has an LCD screen that reports the angle that the
person has rotated and distances that are being measured.
Register's assistant, John Davis, operated the electronic transit
while Register marked both the center points for the columns andoffset points with nails. Register testified that he did look
back through the [electronic transit] to confirm straight lines
through most of these points.
Following defendant's completion of the survey,
plaintiff began excavation of the site. Based on the points set
by defendant's survey, plaintiff set hubs where the footings
should be placed. Plaintiff then dug the footings. Plaintiff
used batter boards to mark the exact location of the columns.
Batter boards are offset lines which mark survey points by
stringing a line diagonally from each corner of the batter
boards. Plaintiff then erected the columns in accordance with
the points set by defendant's survey.
In February 2001 plaintiff discovered that the south
line of the addition was not properly aligned with the north line
of the addition. The south line was straight but was skewed from
west to east and was not square with the rest of the addition.
On 28 June 2001, plaintiff filed suit, alleging that defendant
negligently failed to survey two parallel straight lines. A
bench trial was conducted during the 13 May 2002 term of
Rockingham County Superior Court. The trial court denied
defendant's N.C.G.S. § 1A-1, Rule 41(b) motions for dismissal at
the close of plaintiff's evidence and at the close of all the
evidence. On 31 May 2002, the trial court entered judgment in
favor of plaintiff and awarded $23,000.00 in damages. The court
deducted $436.00 (the amount plaintiff owed defendant for
defendant's professional services) as a setoff from plaintiff's
award and entered judgment for plaintiff in the amount of$22,564.00. On 17 June 2002, the trial court denied defendant's
motions for a new trial and for judgment notwithstanding the
verdict.
The Court of Appeals affirmed the trial court's
judgment and award. Associated Indus. Contr'rs, Inc. v. Fleming
Eng'g Inc., 162 N.C. App. 405, 590 S.E.2d 866 (2004). The Court
of Appeals majority identified the central issue at trial as
whether [defendant] Fleming negligently misidentified the
location for the columns or whether [plaintiff] AIC [Associated
Industrial Contractors] improperly placed the columns after the
center points for the columns had been correctly set by
[defendant] Fleming. Id. at 407, 590 S.E.2d at 868. The Court
of Appeals held that the record contains sufficient evidence to
support the trial court's determination that [defendant] Fleming
was the negligent party. Id. However, the dissent concluded
that plaintiff failed to establish the applicable standard of
care and the trial court improperly denied defendant's motion to
dismiss. 162 N.C. App. at 419, 590 S.E.2d at 876.
Pursuant to N.C.G.S. § 7A-30, this Court now considers
the issue raised by the dissent. After thoroughly reviewing the
record and briefs in this case, we are unable to discern any
error by the trial court in its handling of the present case.
In response to plaintiff's complaint, defendant alleged
in its answer that plaintiff negligently failed to heed the
generally accepted standards of construction with regards to
placement of anchor bolts in the erection of steel at the site of
the construction in question. Further, at trial, defendant'ssurveyor, Johnnie Register, agreed that the south line of columns
was straight, but skewed in relation to the rest of the addition
by as much as six inches. The parties agree that either
plaintiff or defendant was responsible for the south line of
columns being skewed. Accordingly, the critical issue at trial
was not whether an error occurred which caused the south line to
be skewed, but which party, plaintiff or defendant, committed the
error which caused the line to be skewed. Specifically, the
trial court had to consider whether the south line was skewed
because defendant failed to set the points properly during the
survey or because plaintiff did not set the columns on the points
identified during the survey. At trial, plaintiff argued that
defendant improperly placed the column points. Defendant argued
that it properly placed the column points, but that those points
became misaligned when plaintiff's employees moved a batter board
and recreated the column points.
The context for our consideration of this issue is
whether there was competent evidence to support the trial court's
verdict. In this case, the trial court acted as the trier of the
facts. The findings of fact made by the trial judge are
conclusive on appeal if supported by competent evidence, even if,
arguendo, there is evidence to the contrary. Lumbee River Elec.
Membership Corp. v. City of Fayetteville, 309 N.C. 726, 741, 309
S.E.2d 209, 219 (1983).
Two facts support the trial court's verdict. First,
the fact that the south line was skewed, but still formed a
straight line, supports the trial court's judgment. The evidencepresented at trial showed that the south line was straight, but
skewed rather than parallel to the north line. It is unlikely
that defendant properly plotted the points in a straight,
parallel line, but plaintiff then incorrectly placed the columns
on different points which created a skewed but nonetheless
straight line. In fact, plaintiff's project manager for the job,
Curtis Flanigan, testified that if plaintiff's employees had
improperly placed the columns, and if they had just placed the
columns willy-nilly, [Flanigan would] expect one column to be up,
one to be down, another one to be down, another one to be back
up. Instead, as Flanigan testified, all the columns in the
south line were in a straight line. Simply put, if plaintiff's
negligence caused the line to be skewed, it is highly probable
that the line also would not be straight. Because all four
columns on the south wall formed a straight line, the evidence
supported the trial court's conclusion that defendant was
responsible for the south wall's misalignment.
Second, the evidence does not show defendant checked
the survey points to ensure the north and south walls of the
addition would form parallel, straight lines. Register testified
that his assistant, John Davis, ran the transit instrument while
Register set the points. Although Register testified that he
look[ed] back through the [transit] instrument to confirm
straight lines through most of [the] points, Register did not
confirm all of the points. Specifically, Register did not
testify that he confirmed the south line was properly aligned
with the north line. Davis, who was responsible for confirmingthe lines and angles of the survey points, did not testify.
Thus, the record does not show Register, or anyone else,
confirmed that the south line of columns was properly aligned.
The trial court was entitled to infer that defendant
was more likely than not the source of error from (1) the
evidence showing the south wall was parallel to the north wall
but not at the correct angle, and (2) the absence of evidence
showing defendant confirmed the alignment of the south wall. The
evidence presented in this case supports the trial court's
finding that defendant was negligent. Therefore, the trial
court's finding is supported by competent evidence and is
conclusive on appeal. Id. at 741-42, 309 S.E.2d at 218-19.
We fail to find any legal error in the trial of the
present matter. Accordingly, we affirm the decision of the Court
of Appeals.
AFFIRMED.
No. 107A04 - Associated Indus. Contr'rs, Inc. v. Fleming Eng'g,
Inc.
Justice EDMUNDS dissenting.
The majority concludes that the trial court correctly
determined that, between the two parties, the evidence supported
finding defendant responsible for the error. However, a finding
of responsibility does not necessarily imply a finding of
negligence. The majority identifies but never addresses the
issue raised in Chief Judge Eagles' dissent in the Court of
Appeals, that is, whether plaintiff was required to present
expert evidence as to the standard of care required of defendant.
Absent such evidence, the finder of fact had no basis for
concluding that defendant was negligent.
The practice in North Carolina is to require expert
testimony as to the applicable standard of care whenever a
negligence action is brought against a professional or other
individual who works in an area where the standard of care
involves highly specialized knowledge with respect to which a
layman can have no reliable information. Mazza v. Huffaker, 61
N.C. App. 170, 175, 300 S.E.2d 833, 837 (quoting Jackson v.
Mountain Sanitarium & Asheville Agric. Sch., 234 N.C. 222, 227,
67 S.E.2d 57, 61 (1951)), disc. rev. denied, 309 N.C. 192, 305
S.E.2d 734 (1983); see also David A. Logan & Wayne A. Logan,
North Carolina Torts § 11.10 (2d ed. 2004). An exception to this
rule, on which the majority apparently relies, arises where the
common knowledge and experience of the [fact finder] is
sufficient to evaluate compliance with a standard of care. Delta Envtl. Consultants of N.C., Inc. v. Wysong & Miles Co., 132
N.C. App. 160, 168, 510 S.E.2d 690, 695, disc. rev. denied, 350
N.C. 379, 536 S.E.2d 70 (1999). This exception applies when
professional conduct is so grossly negligent that lay knowledge
is sufficient to make obvious the shortcomings of the
professional. Id. at 168, 510 S.E.2d at 696; see also McGill v.
French, 333 N.C. 209, 218, 424 S.E.2d 108, 113 (1993); Groce v.
Myers, 224 N.C. 165, 170, 29 S.E.2d 553, 557 (1944).
I do not believe that this common knowledge exception
applies in the instant case to relieve plaintiff of its duty to
provide expert testimony as to the standard of care that
defendant was required to meet. As detailed in the majority
opinion, the evidence shows that Honda planned to add to an
existing building an extension that was to be 80 feet wide by 120
feet long. Because it would tie into an existing crane, the
extension had to be in the precise shape of a rectangle with 90
degree angles at each corner. Defendant made the measurements.
Once construction began, however, the 120 foot long south wall
was found to be straight but not parallel to the 120 foot long
north wall. At its far end, the south wall deviated 5.75 inches
from the path it would have followed had it been perfectly
parallel to the north wall. Using this information,
straightforward trigonometric analysis reveals that the angle at
the southern corner where the extension met the existing buildingwas 90 degrees 13 minutes 12 seconds (or 90.2288 degrees) rather
than 90 degrees exactly.
(See footnote 1)
While this small error had large consequences, those
consequences may not be dispositive as to whether any actionable
negligence occurred when defendant measured the angle. Large
effects can result from a minuscule initial cause, as in the
classic example where a kicked pebble triggers a landslide.
While we hope for perfection among professionals, we do not
require it. The record is devoid of any evidence as to the
tolerances those in the surveying profession observe in carrying
out their responsibilities. Nor does the evidence suggest
whether a surveying error is judged on the basis of the magnitude
of the mistake in the original measurement, on the basis of the
results of the mismeasurement, or on both. Without such
evidence, the fact finder had insufficient grounds on which to
decide whether defendant was negligent. Therefore, plaintiff had
the burden of introducing expert testimony as to the standard of
care required of a surveyor, especially where, as here,
conditions challenged or confounded usual surveying techniques.
Accordingly, I respectfully dissent.
Justice PARKER joins in this dissenting opinion.
*** Converted from WordPerfect ***