All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
JONESBORO UNITED METHODIST CHURCH, an unincorporated association
v.
MULLINS-SHERMAN ARCHITECTS, L.L.P. and J.H. BATTEN, INC., a North
Carolina Corporation
On discretionary review pursuant to N.C.G.S. § 7A-31 of
a unanimous, unpublished decision of the Court of Appeals, 162
N.C. App. 547, 591
S.
E.2d 598
(2004), affirming an order denying
defendant J.H. Batten, Inc.'s motions for judgment on the
pleadings entered 30 August 2002 by Judge Wiley F. Bowen in
Superior Court, Lee County. Heard in the Supreme Court 6
December 2004.
Safran Law Offices, by Perry R. Safran and Brian J.
Schoolman, for plaintiff-appellee.
Nexsen Pruet Adams Kleemeier, PLLC, by Eric H.
Biesecker, for defendant-appellant J.H. Batten, Inc.
MARTIN, Justice.
On 4 October 1999, defendant J.H. Batten, Inc. (Batten)
entered into a contract (the construction contract) with
plaintiff Jonesboro United Methodist Church (JUMC) whereby Batten
agreed to act as general contractor for the construction of a
Fellowship Hall addition on real property owned by JUMC in
Sanford, North Carolina. According to allegations in JUMC's
complaint, JUMC had concerns about Batten's workmanship
throughout the construction project. Instances of Batten'sallegedly poor workmanship included problems relating to the
alignment and ventilation of the roof, the puckering of roof
shingles, defects in the mortar joints and masonry work,
mislocated purlins, missing insulation, and other matters.
During and after construction, disputes arose between JUMC and
Batten concerning both parties' respective performances under the
contract. The disputes centered around the balance owed for work
performed, the completion of punch list items, and whether Batten
was required to perform additional work under the terms of the
contract or in satisfaction of warranties. The parties entered
mediation in an effort to resolve these disputes.
On 6 August 2001, representatives of JUMC sent Batten a
letter by facsimile transmission confirming a prior telephone
agreement in which JUMC agreed to pay $101,000.00 to satisfy the
construction relationship between JUMC and Batten. The letter
thanked Batten for its willingness to help us settle this today
and invited Batten to indicate its approval of the settlement
agreement by signing and returning the letter by facsimile
transmission. That same day, Batten's managing agent, Harold
Batten, signed the letter and returned it as requested to JUMC.
At the bottom of the page, Batten wrote, I agree that this is a
complete settlement between [Batten] and [JUMC].
On 14 August 2001, JUMC sent Batten another letter by
facsimile transmission. The second letter stated that upon
further review, JUMC disagree[d] on the amount of payment
outstanding. On this basis, the letter purported to rescind[]
the 6 August 2001 settlement offer. After JUMC refused to pay the amount specified in the 6
August 2001 letter, Batten filed suit in Forsyth County Superior
Court on 16 August 2001, seeking $101,000.00 in damages in
satisfaction of the settlement agreement. In the event the trial
court determined there was not a binding settlement agreement,
Batten sought a declaratory judgment to declare the relative
rights and obligations between the parties pursuant to the
Contract. In its answer, JUMC denied that a binding settlement
existed and moved to dismiss, to change venue, and to stay the
proceeding pending arbitration. JUMC further asserted numerous
affirmative defenses, including unclean hands, anticipatory
breach, and estoppel based on Batten's alleged failure to perform
under the contract. JUMC did not file any counterclaims in the
action. After some discovery, Batten filed a motion for summary
judgment, which the trial court allowed on 6 February 2002.
JUMC appealed, and the Court of Appeals affirmed in an
unpublished opinion filed 17 June 2003. The Court of Appeals
concluded that the parties had entered a binding settlement
contract and that no genuine issues of material fact remained to
be litigated. JUMC filed a petition for discretionary review,
which this Court denied on 21 August 2003. J.H. Batten, Inc. v.
Jonesboro United Methodist Church, 357 N.C. 460, 585 S.E.2d 765
(2003).
On 23 April 2002, less than three months after the
trial court entered summary judgment in Batten's favor in the
Forsyth County litigation, JUMC filed a complaint in Lee County.
The complaint stated three claims against Batten: breach ofcontract, breach of express and implied warranty, and
Negligence/Malpractice. Batten filed its answer on 7 June
2002. On 3 July 2002 and 30 July 2002, Batten filed motions for
judgment on the pleadings, which asked the trial court to dismiss
JUMC's claims against Batten because those claims ar[o]se from
the same transaction or occurrence that was the subject of
litigation between the parties in Forsyth County. The trial
court denied the motions on 30 August 2002, and Batten appealed.
The Court of Appeals affirmed in an unpublished opinion. We
reverse.
Rule 13(a) of the North Carolina Rules of Civil
Procedure designates certain claims as compulsory counterclaims
that must be raised in responsive pleadings. Specifically, Rule
13(a) provides that
[a] pleading shall state as a counterclaim any claim
which at the time of serving the pleading the pleader
has against any opposing party, if it arises out of the
transaction or occurrence that is the subject matter of
the opposing party's claim and does not require for its
adjudication the presence of third parties of whom the
court cannot acquire jurisdiction.
N.C.G.S. § 1A-1, N.C. R. Civ. P. 13(a) (2003). A claim is not a
compulsory counterclaim, however, if
(1) At the time the action was commenced the claim
was the subject of another pending action, or
(2) The opposing party brought suit upon his claim by
attachment or other process by which the court did not
acquire jurisdiction to render a personal judgment on
that claim, and the pleader is not stating any
counterclaim under this rule.
Id.; see also N.C. R. Civ. P. 13(a) cmt. As we have previously noted, the ultimate effect of a
pleader's failure to assert a compulsory counterclaim is not set
forth in the rule itself. See Gardner v. Gardner, 294 N.C. 172,
176, 240 S.E.2d 399, 403 (1978). Courts have, however,
consistently held that a party who does not plead a compulsory
counterclaim is, after determination of the action in which it
should have been pleaded, forever barred from bringing a later
independent action on that claim. Id. at 179, 240 S.E.2d at
404. This preclusive effect is necessary to effectuate the
purpose of Rule 13(a), which is to enable one court to resolve
'all related claims in one action, thereby avoiding a wasteful
multiplicity of litigation.' Id. at 176-77, 240 S.E.2d at 403
(quoting 6 Charles Alan Wright & Arthur R. Miller, Federal
Practice and Procedure § 1409, at 37 (1971)); see also Kemp v.
Spivey, 166 N.C. App. 456, 458, 602 S.E.2d 686, 688 (2004);
Winston-Salem Joint Venture v. Cathy's Boutique, Inc., 72 N.C.
App. 673, 675, 325 S.E.2d 286, 287 (1985); Twin City Apartments,
Inc. v. Landrum, 45 N.C. App. 490, 494, 263 S.E.2d 323, 325
(1980). To permit a party who failed to assert a compulsory
counterclaim to raise that claim in a later action undermines the
salutary procedural principle that litigation once precipitated
ought to be concentrated insofar as practicable in one forum,
thereby 'destroy[ing] the effectiveness of Rule 13(a).'
Gardner, 294 N.C. at 179-81, 240 S.E.2d at 404-06 (quoting 6
Charles Alan Wright & Arthur R. Miller, Federal Practice and
Procedure § 1417, at 94 (1971)). Accordingly, it is well settled
that absent a specific statutory or judicially determinedexception, see id. at 181, 240 S.E.2d at 406, a party's failure
to interpose a compulsory counterclaim in an action that has been
fully litigated bars assertion of that claim in any subsequent
action. Id. at 179, 240 S.E.2d at 404; see also Wood v. Wood, 60
N.C. App. 178, 181, 298 S.E.2d 422, 423 (1982); Hudspeth v.
Bunzey, 35 N.C. App. 231, 233, 241 S.E.2d 119, 121, cert. denied,
294 N.C. 736, 244 S.E.2d 154 (1978). See generally Restatement
(Second) of Judgments § 22, at 185 (1982).
At the outset, we acknowledge that the compulsory
counterclaim rule applies only to claims that are mature at the
time the responsive pleading is filed. See N.C. R. Civ. P. 13(a)
(stating that the rule applies to claims a party has against an
opposing party at the time of serving the [responsive]
pleading); see also Country Club of Johnston Cty., Inc. v.
United States Fid. & Guar. Co., 150 N.C. App. 231, 241, 563
S.E.2d 269, 276 (2002); 3 James W. Moore et. al, Moore's Federal
Practice, ¶ 13.13, at 13-33 to 13-34 (3d ed. 2004). In the
instant case,
JUMC's complaint in the Lee County litigation
asserted claims against Batten premised on (1) Batten's alleged
breach of the construction contract, (2) Batten's alleged breach
of express and implied warranties of good workmanship and (3)
Batten's alleged negligence in providing nonconforming and
defective work and failing to perform [its] duties of
construction in accordance with the standard of care for
contractors in the community. A review of JUMC's pleadings and
the evidence of record demonstrates that these three claims, all
of which are based on Batten's alleged failure to complete theconstruction project in a satisfactory manner, were available to
JUMC at the time it filed its answer in the Forsyth County
litigation.
In its answer to Batten's Forsyth County complaint,
JUMC admitted Batten's factual allegation that [c]ertain
disputes [had] ar[isen] between Batten and JUMC regarding
Batten's and JUMC's performance of the [construction]
[c]ontract. In addition, JUMC set forth three affirmative
defenses that expressly relied upon Batten's alleged
noncompliance with the terms of that contract. Specifically,
JUMC alleged that Batten (1) had unclean hands with regard to
its performance under [the construction contract], (2) was
estopped from seeking damages . . . as [Batten] ha[d] not fully
performed under its subcontract with [JUMC], and (3) was not
entitled to recovery of any amounts owed by [JUMC] due to
[Batten's] anticipatory breach of the contract. Similarly
, in
its Brief in Opposition to Plaintiff's Motion for Summary
Judgment in the Forsyth County action, JUMC alleged that in
addition to the dispute over the balance owed on the construction
contract, there were unresolved issues such as additional items
of work to be performed under the [construction] contract,
warranty work, and punch lists.
Thus, JUMC's pleadings in the
Forsyth County action demonstrate that JUMC was aware of the
factual basis for its Lee County claims at the time it filed its
responsive pleadings during the Forsyth County litigation.
Moreover, in its Lee County complaint, JUMC alleged
that as early as 5 December 2000, more than eight months prior tothe initiation of the Forsyth County action, it provided the
architect supervising the construction project with a copy of a
preliminary independent report identifying many non-conforming
workmanship issues, including puckering shingles on many areas
of the roof, concerns with the masonry and mortar joints,
concerns with the location of the purlins, insulation missing in
specified areas, [and] concerns with the elevations of a
specified canopy. According to the same complaint, the
architect made recommendations concerning the outstanding punch-
list and workmanship items on or about 9 April 2001, four months
prior to Batten's filing of its Forsyth County complaint. In
addition, the
Chair of JUMC's
Board of Trustees stated in an
affidavit that JUMC and Batten began to discuss and negotiate
disputes as to payment, additional items of work to be performed
under the contract, warranty work, and punch lists in July 2001,
one month before initiation of the Forsyth County action. Thus,
according to its own factual allegations in both the Forsyth
County and Lee County actions and the sworn statement of the
Chair of its Board of Trustees, JUMC had actual knowledge of the
factual basis for its claims against Batten well before it filed
its answer during the Forsyth County litigation.
Accordingly,
JUMC's claims against Batten were mature at the time JUMC filed
that answer, and those claims are potentially subject to the
compulsory counterclaim bar.
We next turn to the question of whether JUMC's claims
against Batten in the Lee County litigation
arise[] out of the
transaction or occurrence that is the subject matter of Batten'sclaims against JUMC in the Forsyth County litigation. There is
no simple test to determine when a claim arise[s] out of the
transaction or occurrence that is the subject matter of the
opposing party's claim for purposes of Rule 13(a). 1 G. Gray
Wilson, North Carolina Civil Procedure § 13-3, at 259 (2d ed.
1995). As the United States Supreme Court stated in interpreting
a predecessor to the modern federal compulsory counterclaim rule,
'[t]ransaction' is a word of flexible meaning. It may
comprehend a series of many occurrences, depending not so much
upon the immediateness of their connection as upon their logical
relationship. Moore v. N.Y. Cotton Exchange, 270 U.S. 593, 610,
70 L. Ed. 750, 757 (1926) (emphases added). North Carolina
courts have followed a similar approach in applying Rule 13(a),
consistently inquiring whether there is a logical relationship
between the factual backgrounds and legal natures of the claims
under consideration. See, e.g., Kemp, 166 N.C. App. at 458, 602
S.E.2d at 688; Winston-Salem Joint Venture, 72 N.C. App. at 675,
325 S.E.2d at 287; Twin City Apartments, Inc., 45 N.C. App. at
494, 263 S.E.2d at 325.
North Carolina's compulsory counterclaim rule is
identical to its federal counterpart. Compare Fed. R. Civ. P.
13(a) (2005) with N.C. R. Civ. P. 13(a). Not surprisingly,
therefore, our Court of Appeals has looked to the federal courts
for guidance in applying Rule 13(a). In Curlings v. Macemore,
the Court of Appeals adopted the three-pronged analytical
framework employed by the United States Court of Appeals for the
Fourth Circuit and other federal courts. 57 N.C. App. 200, 202,290 S.E.2d 725, 726 (1982); see also 6 Charles A. Wright et. al.,
Federal Practice and Procedure § 1410, at 52-58 (2d ed. 1990).
Under this analysis, courts examine the following three factors
in determining whether two or more claims arose out of the same
transaction or occurrence for purposes of the compulsory
counterclaim rule: '[(1)] whether the issues of fact and law
raised by the claim and counterclaim are largely the same[; (2)]
whether substantially the same evidence bears on both claims[;]
and [(3)] whether any logical relationship exists between the two
claims.' Curlings, 57 N.C. App. at 202, 290 S.E.2d at 726
(quoting Whigham v. Beneficial Fin. Co., 599 F.2d 1322, 1323 (4th
Cir. 1979)) (alterations in original); see also Kemp, 166 N.C.
App. at 458, 602 S.E.2d at 688; Cloer v. Smith, 132 N.C. App.
569, 574, 512 S.E.2d 779, 782 (1999); Brooks v. Rogers, 82 N.C.
App. 502, 507-08, 346 S.E.2d 677, 681 (1986). Although
application of Rule 13(a) is not reducible to any simple formula,
we agree that courts should inquire, at a minimum, into these
three factors when deciding if a claim arises out of the
transaction or occurrence that is the subject matter of the
opposing party's claim. N.C. R. Civ. P. 13(a). Accordingly, we
hereby formally adopt the Curlings factors as a part of our
compulsory counterclaim jurisprudence.
In the instant case, all three of the Curlings factors
suggest that JUMC's claims against Batten in the Lee County
litigation should have been raised as compulsory counterclaims in
the Forsyth County litigation.
In its Forsyth County complaint
,
Batten (1) sought enforcement of the settlement agreement, whichresolved disputes . . . between Batten and JUMC regarding
Batten's and JUMC's performance of the [construction]
[c]ontract, and (2) moved for a declaratory judgment as to the
parties' relative rights and obligations pursuant to the
[construction] [c]ontract. JUMC's complaint in the Lee County
litigation, by comparison, asserted claims against Batten based
on alleged construction defects and premised on legal theories of
(1) breach of contract, (2) breach of warranties, and (3)
Negligence/Malpractice.
Applying the Curlings factors, Batten's claims in the
Forsyth County litigation and JUMC's claims in the Lee County
litigation all raised legal issues arising out of the common
factual background of the construction contract and the
construction project. Moreover, both sets of claims depended in
large part on evidence of the parties' respective conduct
throughout the construction relationship. Finally, the claims
are logically related in that they all concern the parties'
respective performances under the construction contract and their
corresponding liabilities under the construction and settlement
contracts.
JUMC argues, however, that its claims against Batten
cannot be compulsory counterclaims with respect to either of the
claims asserted in Batten's Forsyth County complaint. First,
JUMC contends that Batten's claim seeking enforcement of the
settlement agreement and JUMC's claims for damages based on
breach of the construction contract, breach of warranties, and
negligent construction involve consideration of different factsand different legal principles. While there is some truth to
this contention, Rule 13(a) does not require that the legal
claims be identical. It is sufficient that the nature of the
actions and the remedies sought are logically related in fact and
law.
Brooks, 82 N.C. App. at 509, 346 S.E.2d at
682. Given
that the settlement agreement purports to satisfy the
construction relationship between JUMC and Batten
and that
Batten's alleged failure to perform under the construction
contract was the basis of at least three of JUMC's affirmative
defenses in the Forsyth County litigation, it is clear that any
claims arising out of the construction contract are logically
related to claims
seeking to enforce the settlement agreement.
Indeed, in JUMC's Motion to Stay Pending Arbitration, filed in
conjunction with its answer in the Forsyth County litigation,
JUMC itself describes the dispute over the settlement agreement
as a conflict[] arising out of or relating to the [construction]
contract.
We therefore reject JUMC's argument that its claims
against Batten are not logically related to JUMC's claim
seeking enforcement of the settlement agreement.
Second, JUMC argues that its claims against Batten
cannot be compulsory counterclaims with respect to Batten's
declaratory judgment action because the trial court never reached
final judgment on the latter claim. To be sure, a claim cannot
be barred by res judicata or collateral estoppel unless it was
litigated to final judgment in a prior action. Thomas M.
McInnis
& Assocs. v. Hall, 318 N.C. 421, 428, 349 S.E.2d 552, 556 (1986)
.
But as the United States Court of Appeals for the First Circuitexplained in Dindo v. Whitney, the fact that there was no final
judgment on the merits should be immaterial for purposes of the
compulsory counterclaim bar. 451 F.2d 1, 3 (1st Cir. 1971)
.
Like the First Circuit Court of Appeals, [w]e are not persuaded
that a final judgment is a sine qua non to invocation of the
[compulsory counterclaim] bar because there is nothing in the
rule limning the term 'judgment.' Id. Accordingly, we reject
JUMC's contention that its claims arising out of the construction
relationship
cannot be compulsory counterclaims in Batten's
declaratory judgment action.
In conclusion, the construction contract and the
parties' performance under that contract constitute a single
transaction or occurrence that formed the factual basis for the
parties' respective claims for relief in both the Forsyth County
and Lee County actions. Although Batten's claims in the Forsyth
County litigation and JUMC's claims in the Lee County litigation
are not identical, [t]he issues of law and fact are . . .
largely the same in both actions, . . . require substantially the
same evidence for their determination, and . . . are logically
related. Cloer, 132 N.C. App. at 574, 512 S.E.2d at 782.
Accordingly, JUMC's claims against Batten were compulsory
counterclaims in the Forsyth County action, and JUMC's failure to
assert those claims during that action bars their subsequent
assertion in any later litigation.
Moreover, given that JUMC's
claims against Batten could and should have been asserted as
counterclaims in the Forsyth County litigation
, it is not
inequitable to bar JUMC from asserting those claims in asubsequent action. Indeed, to permit JUMC to bring forth its
claims in such a manner
would subject Batten and our courts to
'the unnecessary delay and expense of repeated fragmentary'
litigation, Hicks v. Koutro, 249 N.C. 61, 64, 105 S.E.2d 196, 200
(1958) (quoting City of Raleigh v. Edwards, 234 N.C. 528, 529, 67
S.E.2d 669, 671 (1951)), and
undermine the salutary principle of
judicial economy upon which Rule 13(a) is premised.
The decision of the Court of Appeals is reversed, and
the case is remanded to that court for further remand to the Lee
County Superior Court for further proceedings consistent with
this opinion.
REVERSED AND REMANDED.
*** Converted from WordPerfect ***