All opinions are subject to modification and technical correction prior to official publication in the North Carolina Reports and North Carolina Court of Appeals Reports. In the event of discrepancies between the electronic version of an opinion and the print version appearing in the North Carolina Reports and North Carolina Court of Appeals Reports, the latest print version is to be considered authoritative.
O & M INDUSTRIES
v.
SMITH ENGINEERING COMPANY, a/k/a SMITH
ENVIRONMENTAL CORPORATION; KURZ TRANSFER PRODUCTS, LIMITED
PARTNERSHIP, and KURZ AND PARTNERS, LIMITED PARTNERSHIP
Liens--mechanics and materialmen's--subcontractor against principal
Summary judgement was correctly granted for a subcontractor seeking payment from the
principal (defendant) under a Notice of Claim of Lien after the general contractor encountered
financial difficulty and stopped work on the project, and the defendant claimed a set-off for the
cost of completion. Defendant had a duty under N.C.G.S. § 44A-20 to retain funds up to the
total amount of the noticed lien; any option to set off the cost completing the project against the
retained amount would not negate defendant's personal liability to plaintiff.
On discretionary review pursuant to N.C.G.S. § 7A-31 of a
unanimous, unpublished decision of the Court of Appeals, 165 N.C.
App. 705, 601 S.E.2d 330 (2004), reversing an order granting
summary judgment for plaintiff entered on 15 November 2002 by
Judge Christopher M. Collier in Superior Court, Davidson County.
Heard in the Supreme Court 18 October 2005.
Hendrick & Bryant, LLP, by Matthew H. Bryant and T. Paul
Hendrick, for plaintiff-appellant.
Smith Currie & Hancock, LLP, by Harry R. Bivens, for
defendant-appellee Kurz Transfer Products, L.P.
Erwin and Eleazer, P.A., by L. Holmes Eleazer, Jr. and
Fenton T. Erwin, Jr., Counsel for American Subcontractors
Association of the Carolinas, amicus curiae.
Vann & Sheridan, LLP, by James R. Vann and Nan E. Hannah,
for Southeastern Association of Credit Management, Inc.,
amicus curiae.
PARKER, Justice.
O & M Industries (plaintiff) instituted this action
against Smith Engineering (Smith) and Kurz Transfer Products,
LP (defendant) under N.C.G.S. § 44A-18, the materialman'sstatutory lien. The issue before the Court for review is whether
the Court of Appeals properly reversed the trial court's entry of
summary judgment for plaintiff under N.C.G.S. § 44A-20. For the
reasons stated herein, we reverse the decision of the Court of
Appeals and remand for consideration of additional issues.
Defendant operates a manufacturing facility in Lexington,
North Carolina, on property leased from an affiliate company. On
or about 14 December 2000, defendant contracted with Smith for
the design and construction of a regenerative thermal oxidizer
system. Smith subcontracted with plaintiff for the construction
and delivery of a three canister thermal oxidizer. Plaintiff
performed by shipping the oxidizer in June 2001. Believing Smith
to be in financial difficulty, plaintiff served a Notice of Claim
of Lien on defendant on 8 June 2001 in the amount of $113,655.00.
The evidence tends to show that defendant was aware of Smith's
financial position.
After receiving the Notice, defendant made two payments to
Smith, one for $164,831.25 on 6 July 2001, and one for
$150,000.00 on 1 August 2001. Smith ceased work on the project
on 13 August 2001, and defendant's estimates of its costs to
complete ranged at various times from $25,000 to over $415,000.
On 22 August 2001, Smith informed defendant that it had filed for
bankruptcy. Plaintiff served another Notice of Claim of Lien on
defendant on 23 August 2001 in the amount of $127,392.12.
Plaintiff instituted this action when it did not receive paymentfrom either defendant or Smith. Plaintiff obtained a default
judgment against Smith.
Thereafter, plaintiff moved for summary judgment, alleging
that defendant was personally liable as the result of the two
post-Notice payments to Smith. Defendant also moved for summary
judgment, arguing inter alia that the additional costs necessary
to complete the project barred plaintiff from recovery. The
trial court denied defendant's motion, allowed plaintiff's
motion, entered judgment against defendant in the amount of
$113,655.00 plus interest, and awarded plaintiff attorney's fees
and costs.
On appeal to the Court of Appeals, defendant argued that
unsettled questions concerning the sufficiency of its retained
funds and its costs to complete the project raised issues of
material fact, thereby making summary judgment improper.
Defendant specifically claimed that it was not obligated to pay
plaintiff in that the cost to complete the project would exceed
the amount otherwise owed to Smith. Defendant also argued issues
of estoppel and novation based on a letter sent by plaintiff to
Smith dated 15 June 2001, and on plaintiff's 23 August 2001
Notice of Claim of Lien sent to defendant, respectively. Relying
upon Lewis-Brady Builders Supply, Inc. v. Bedros, 32 N.C. App.
209, 231 S.E.2d 199 (1977) and Watson Electrical Construction,
Co. v. Summit Cos., 160 N.C. App. 647, 587 S.E.2d 87 (2003), the
Court of Appeals agreed with defendant that a determination of
defendant's costs to complete the project was necessary tocalculate the appropriate setoff amount and reversed the trial
court's entry of summary judgment for plaintiff. The Court of
Appeals opinion did not reach defendant's estoppel or novation
arguments.
In its appeal to this Court, plaintiff contends that the
Court of Appeals failed to address and properly apply the
applicable lien statutes. We agree. We note, however, that we
express no opinion on defendant's estoppel or novation arguments
and assume arguendo for purposes of our discussion herein that
plaintiff's 8 June 2001 notice of lien was valid.
The North Carolina Constitution mandates that the General
Assembly shall provide by proper legislation for giving to
mechanics and laborers an adequate lien on the subject-matter of
their labor. N.C. Const. art. X, § 3. To satisfy this mandate
the legislature enacted statutes which are now codified in
Chapter 44A of the General Statutes. In Electric Supply Co. of
Durham v. Swain Electrical Co., 328 N.C. 651, 403 S.E.2d 291
(1991), this Court, recognizing the central role played by credit
in the construction industry, articulated the importance of an
adequate lien for subcontractors and suppliers of materials and
labor:
Suppliers . . . provide labor and materials to
contractors and subcontractors who perform their
portion of the work on a project. Since the contractor
or subcontractor is generally not paid until the job,
or a portion of it, is completed (and is probably
unable to pay until it, in turn, is paid), their
suppliers extend labor and materials to them on credit.
An adequate lien is necessary to encourage responsibleextensions of credit, which are necessary to the health
of the construction industry.
Id. at 659, 403 S.E.2d at 296.
The statutory provisions at issue in this case are
N.C.G.S. §§ 44A-18 and 44A-20.
(See footnote 1)
Section 44A-18 provides in
relevant part:
Upon compliance with this Article:
(1) A first tier subcontractor who
furnished labor, materials, or
rental equipment at the site of the
improvement shall be entitled to a
lien upon funds which are owed to
the contractor with whom the first
tier subcontractor dealt and which
arise out of the improvement on
which the first tier subcontractor
worked or furnished materials.
. . . .
(5) The liens granted under this
section shall secure amounts earned
by the lien claimant as a result of
his having furnished labor,
materials, or rental equipment at
the site of the improvement under
the contract to improve real
property, whether or not such
amounts are due and whether or not
performance or delivery is
complete.
(6) A lien upon funds granted under
this section is perfected upon the
giving of notice in writing to the
obligor as provided in G.S. 44A-19
and shall be effective upon the
obligor's receipt of the notice. The subrogation rights of a first,
second, or third tier subcontractor
to the lien of the contractor
created by Part 1 of Article 2 of
this Chapter are perfected as
provided in G.S. 44A-23.
N.C.G.S. § 44A-18 (2003).
Section 44A-20 sets forth the duties of an owner upon
receipt of a Notice of Claim of Lien:
(a) Upon receipt of the notice
provided for in this Article the obligor
shall be under a duty to retain any funds
subject to the lien or liens under this
Article up to the total amount of such liens
as to which notice has been received.
(b) If, after the receipt of the
notice to the obligor, the obligor shall make
further payments to a contractor or
subcontractor against whose interest the lien
or liens are claimed, the lien shall continue
upon the funds in the hands of the contractor
or subcontractor who received the payment,
and in addition the obligor shall be
personally liable to the person or persons
entitled to liens up to the amount of such
wrongful payments, not exceeding the total
claims with respect to which the notice was
received prior to payment.
(c) If an obligor shall make a
payment after receipt of notice and incur
personal liability therefor, the obligor
shall be entitled to reimbursement and
indemnification from the party receiving such
payment.
. . . .
Id. § 44A-20 (2003). In the present case defendant is an
obligor under the statutory definition. See id. § 44A-17(3)
(2003). In interpreting a statute, the Court must first
ascertain the legislative intent in enacting the legislation.
Elec. Supply Co. of Durham, 328 N.C. at 656, 403 S.E.2d at 294.
The first consideration in determining legislative intent is the
words chosen by the legislature. Brown v. Flowe, 349 N.C. 520,
522, 507 S.E.2d 894, 895-96 (1998). When the words are clear and
unambiguous, they are to be given their plain and ordinary
meanings. Id. The Court may also consider the policy objectives
prompting passage of the statute and should avoid a construction
which defeats or impairs the purpose of the statute. Elec.
Supply Co. of Durham, 328 N.C. at 656, 403 S.E.2d at 294.
The materialman's lien statute is remedial in that it
seeks to protect the interests of those who supply labor and
materials that improve the value of the owner's property. See
Elec. Supply Co. of Durham, 328 N.C. at 659, 403 S.E.2d at 296;
see also Carolina Builders Corp. v. Howard-Veasey Homes, Inc., 72
N.C. App. 224, 229, 324 S.E.2d 626, 629-30, disc. review denied,
313 N.C. 597, 330 S.E.2d 606 (1985). A remedial statute must be
construed broadly in the light of the evils sought to be
eliminated, the remedies intended to be applied, and the
objective to be attained. Puckett v. Sellars, 235 N.C. 264,
267, 69 S.E.2d 497, 499 (1952).
Under Chapter 44A, Section 18 the first tier
subcontractor is entitled to a lien upon funds owed to the
contractor with whom the first tier subcontractor dealt arisingout of the improvements on which the first tier subcontractor
worked or furnished materials. N.C.G.S. § 44A-18(1). This lien
on funds secures amounts earned by the lien claimant for labor or
materials furnished, whether or not performance or delivery is
complete. Id. § 44A-18(5). The lien upon funds is perfected
upon giving of the notice of claim of lien in writing to the
obligor in accordance with N.C.G.S. § 44A-19 and is effective
upon the obligor's receipt of the notice. Id. § 44A-18(6).
The statutory scheme set out in Chapter 44A, Section 20
to protect the subcontractor's lien on funds once notice has been
given provides: first, that the obligor shall retain funds up to
the total amount of liens as to which notice has been given, id.
§ 44A-20(a); second, that the obligor shall be personally liable
if the obligor makes further payments to a contractor or
subcontractor against whose interest the lien or liens are
claimed; id. § 44A-20(b); and third, that an obligor who makes a
payment after receipt of notice and incurs personal liability is
entitled to reimbursement and indemnification from the party
receiving such payment; id. § 44A-20(c). Significantly, this
section of the statute makes no provision for a setoff against
the retained funds in the event the cost of completing the
project exceeds the amount of retained funds.
The determinative question on this appeal is whether
the payments, totaling $314,831.25, made by defendant to Smith on
6 July 2001 and 1 August 2001 triggered personal liability on thepart of defendant. Based on the principles of statutory
interpretation outlined above, if the notice of lien is
effective, the answer to this question must be in the
affirmative. After stating that the lien follows the funds into
the hands of the contractor or subcontractor to whom payment is
made after notice, the statute says plainly and unequivocally:
and in addition the obligor shall be personally liable to the
person or persons entitled to liens. Id. § 44A-20(b). The
parties do not dispute that defendant has retained approximately
$243,713, an amount exceeding the claimed lien. However,
contrary to defendant's position, the mere retention of funds
equal to or in excess of the amount of the lien is not sufficient
to avoid personal liability.
The retain funds prong of subsection 44A-20(a) and
the further or wrongful payments prong of subsection 44A-
20(b) are discrete. In the absence of the wrongful payments
made subsequent to a Notice of Lien on Funds as described in
N.C.G.S. § 44A-20(b), personal liability on the part of the
obligor is not triggered. However, in the event of an obligor's
wrongful payment, the lien continues upon the funds, and the
obligor becomes personally liable to the noticing party up to the
amount of the wrongful payment, not exceeding the total claims
with respect to which notice was received before the payment.
Id. § 44A-20(b). In keeping with the mandate that mechanics and laborers
be provided an adequate lien on the subject matter of their
labor, the statute creates a risk shifting mechanism for
subcontractors. Prior to notice to the obligor, the
subcontractor bears the risk of loss or nonpayment by the general
contractor. When notice is served, the risk shifts to the
obligor to the extent that the obligor is holding funds. With
this notice the burden of assuring payment of the subcontractor's
lien shifts to the obligor who owns the project, is receiving
construction funds, and receives the benefit of the
subcontractor's labor and materials. The owner is, thus, put on
notice of a general contractor's potential breach and is apprised
of the need to take precautions necessary to protect the project
and to ensure that subcontractors remain on the job.
The court below applied a setoff analysis. However,
the Court of Appeals' reliance on Lewis-Brady Builders and Watson
Electrical was misplaced.
In Lewis-Brady Builders, the plaintiff subcontractor
appealed from the trial court's order, which granted relief to
plaintiff against the general contractor but denied recovery
against the owner. 32 N.C. App. at 210, 231 S.E.2d at 200. The
Court of Appeals affirmed the judgment, finding that because the
owner spent all funds otherwise due under the contract to
complete the project, no subcontractor recovery was possible.
Id. at 212-13, 231 S.E.2d at 201. Lewis-Brady Builders is,however, distinguishable from the present case, in that the owner
in Lewis-Brady Builders made no further payments to the general
contractor subsequent to its receipt of the subcontractor's
Notice of Claim of Lien. Rather, the owner sought new bids for
completion of the project after failing to negotiate terms with
the original general contractor. See id. at 210, 231 S.E.2d at
199-200.
The plaintiff subcontractor in Watson Electrical filed
a Notice of Claim of Lien approximately six weeks after defendant
owners' last payment to the original general contractor on the
project, but several weeks before the defendant owners terminated
the contractor for defaulting on the contract. 160 N.C. App. at
649, 587 S.E.2d at 90. The basis on which the Court of Appeals
affirmed summary judgment in favor of the owners was a finding by
an arbitrator that the setoff exceeded the amount due under the
contract. See id. at 651-52, 587 S.E.2d at 91-92. Again, the
owners made no post-Notice payments to the general contractor,
but arranged completion of the project with another general
contractor.
In this case, defendant had a duty under Section 44A-20
to retain funds up to the total amount of the noticed lien.
Defendant made further payments to Smith, thereby triggering
personal liability up to the amount of the payments, not to
exceed the amount of the claims noticed. N.C.G.S. § 44A-20(b).
Defendant's option, if any, to set off its cost to complete theproject against the retained amount would not negate defendant's
personal liability to plaintiff. Id. Defendant's argument that
under N.C.G.S. § 44-18(1), the lien only attached to the amount
owed the contractor and that nothing was owed to the contractor
must fail.
The critical time for determining whether an amount is
owed for purposes of N.C.G.S. § 44A-18(1) is when the obligor
receives the notice of lien. Id. § 44A-18(6). In this case,
defendant admitted making payments totaling $314,831.25 to Smith
after receiving plaintiff's Notice of Claim of Lien for
$113,655.00. By making the payments, defendant acknowledged that
it owed money to the contractor. See Whitley's Elec. Serv., Inc.
v. Sherrod, 293 N.C. 498, 505, 238 S.E.2d 607, 612 (1977).
Were this Court to adopt the Court of Appeals'
analysis, the purpose of the statute, which is to protect
mechanics and materialmen, would be eviscerated. The reason the
obligor becomes personally liable by making a payment after
receiving a notice of claim of lien is that the obligor is then
on notice that a potential problem exists and, having control of
the funds, is in a position to avoid or rectify the problem.
Summary judgment is appropriate when the pleadings,
depositions, answers to interrogatories, and admissions on file,
together with the affidavits, if any, show that there is no
genuine issue as to any material fact and that any party isentitled to a judgment as a matter of law. N.C.G.S. § 1A-1,
Rule 56(c) (2003).
Under our holding today, unless defendant's remaining
assignments of error asserting estoppel and novation have merit,
questions concerning the sufficiency of the retained funds and
defendant's cost to complete are not relevant and do not raise
genuine issues of material fact. Accordingly, we reverse and
remand to the Court of Appeals for consideration of defendant's
remaining assignments of error.
REVERSED and REMANDED.
*** Converted from WordPerfect ***